STATEMENT OF WORK 9 AMPERE-HOUR PRISMATIC MERCURIC OXIDE/ZINC CELL
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP09-02457R000100330010-9
Release Decision:
RIFPUB
Original Classification:
K
Document Page Count:
3
Document Creation Date:
December 22, 2016
Document Release Date:
September 13, 2012
Sequence Number:
10
Case Number:
Publication Date:
July 14, 1977
Content Type:
MISC
File:
Attachment | Size |
---|---|
CIA-RDP09-02457R000100330010-9.pdf | 88.07 KB |
Body:
Declassified and Approved For Release 2012/09/13: CIA-RDP09-02457R000100330010-9
STATEMENT OF WORK
9 Ampere-Hour Prismatic Mercuric Oxide/Zinc Cell
1. INTRODUCTION
This document describes the U. S. Government's need for the
development and engineering of a capability to fabricate moderate
numbers of highly reliable, sealed, high energy density mercuric
oxide/zinc cells. One hundred ten (110) sample cells will be
delivered for evaluation 9 months after contract start. Later
phases of this program may involve the construction of 550 cells
for qualification in FY-79 and 1 -- 2,000 cells for operational
use in FY-80. This contract action involves the first phase only
(Task 1).
2. PROJECT GOALS
The contractor will review existing electrochemical and
mechanical performance parameters and process techniques for
mercuric oxide/zinc cell construction. The contractor will then
duplicate the design of this cell which could reasonably be expected
to meet the target specifications. Sample cells will then be
tested against those specifications. Additional design work will
be conducted to overcome any shortcomings in performance. A
statistically significant number of cells will be constructed
and tested to confirm design performance against the electrical,
mechanical, and enviornmental requirements. One hundred ten (110)
engineering samples will be delivered to the government for test
and evaluation. All engineering test data, design drawings, and
process specifications will be included in a final report.
Declassified and Approved For Release 2012/09/13: CIA-RDP09-02457R000100330010-9
Declassified and Approved For Release 2012/09/13: CIA-RDP09-02457R000100330010-9
3. TARGET SPECIFICATIONS
a. Voltage
b. Capacity
c. Rate
d. Shelf Life
le. Leakage
f. Deflection
g?
Temperature
h. System
i. Environmental
j. Life
k. Size
4. PROGRAM PLAN
Attached (Figure 1)
5. DELIVERABLES
a. One hundred ten (110) each hermetically-sealed,
corrosion resistant cells meeting the target
specifications.
1.34 nominal 1.0V cutoff
9AHr @ 2 ma @ 75?F
15mA max at 75?F
90% rated capacity after 3 years
at 75?F
10-8 cc/sec Helium @ STP
0.050" at center of case under
any rated condition of temperature,
rate or discharge
55?F to 140?F
Mercuric oxide/NaOH:H20/Zinc
Type I equipment
3 years combined storage and use
1.4" X 1.6" X 0.6" max
b. Five (5) copies of monthly letter reports on
technical and financial status. .
c. Five (5) copies of a final report including test
data, design drawings, and process specifications
6. TECHNICAL PROPOSAL REQUIREMENTS
The technical proposal should contain:
a. The background and test data base necessary to design
the required cells.
.b. Envisioned design alternatives including, if possible,
a preferred design concept.
Declassified and Approved For Release 2012/09/13: CIA-RDP09-02457R000100330010-9
Declassified and Approved For Release 2012/09/13: CIA-RDP09-02457R000100330010-9
c. Design calculations to indicate theoretical
feasibility of meeting each of the target
specifications.
d. A detailed project plan.
e. A list of applicable references and supporting
documents.
f. A detailed cost proposal for 10 and 100 deliverable
units.
14 July 1977