Approved For Release 2002/06/11: CIA-RDP66B00728R000400060049-7
DE-061-64
20 October 1964
Received your note of 15 October 1964 with the cost breakdown for
ten men--days of engineering services and your report of expenditures
and commitments.
The expenditure and commitment report looks good and with two
additional items will be quite satisfactory. On your next report will
you include an estimate of total expenditures and commitments through
31 December 1964 plus estimated total expenditures and commitments to
complete the Job. This will keep us informed on estimated future
expenditures and commitments as well as current expenditures and commit-
ments. From this we can also determine whether we are moving toward
a potential overrun if that should occur.
Please let me know when you feel additional funding is necessary
on the contract. I have forwarded a copy of the engineering services
breakdown to Paul and as soon as he obtains money for this as well a I&TINTL
the additional work in the amount of will amend the con
to cover these items.
As soon as we have received a signed contract from you we se d
in your first invoice number 2121-2320 in the amount of S,tATINTL
that time we will also amend the contract to cover the additional areas
that we had discussed at our meeting with you last week.
Sincerely,