PROPOSED PMB OPERATIONAL CONTROL SYSTEM
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP73T00325R000100020034-4
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
2
Document Creation Date:
December 28, 2016
Document Release Date:
June 3, 2008
Sequence Number:
34
Case Number:
Publication Date:
February 26, 1970
Content Type:
MEMO
File:
Attachment | Size |
---|---|
![]() | 71.72 KB |
Body:
Approved For Release 2008/06/03: CIA-RDP73T00325R000100020034-4
93 CURL I
NPIC/PPBS/PPD-02-70
26 February 1970
MEMORANDUM FOR: Chief, Plans & Programs Division, PPBS/NPIC
SUBJECT : Proposed PMB Operational Control System
1. During the past twenty months the PMB has been utilizing MIS
information to monitor the Center's production schedules.
2. The PMB has had sufficient experience to determine that:
a. The MIS does not provide information in a timely enough
fashion to effectively monitor production scheduling.
b. The MIS does not provide the scope of a project in terms
of the products to be produced.
3. To meet their own needs for effective production control,
each group has implemented their own record keeping and control system.
4. In addition the RAD has implemented a record keeping and control
system which makes use of the MIS work phase notice.
5. Recently the FMB took a hard look at all these systems and
agreed that a new system should be developed that will incorporate the
best features of the RAD and IEG system.
6. The advantages of the new system are:
a. Production control information will be as timely as is
necessary.
b. The user of the system will know the size and scope of a
given project.
c. Much of the work has been completed only the tying of the
two systems together remains to be done.
7. The disadvantages of the system will be that initially:
a. The system will be essentially a manual card system.
b. Actual man hours charged against a project will not be
shown in any listings other than the current MIS listings.
SECRET
GROUP 1
Excluded from automatic
docnaradlug and
decfasslti atlan
Approved For Release 2008/06/03: CIA-RDP73T00325R000100020034-4
Approved For Release 2008/06/03: CIA-RDP73T00325R000100020034-4
0 SECRET ?
NPIC/PPBS/PPD-02-70
8. When the proposed improvement to the MIS is completed, this
proposed PMB system will be tied to the MIS.
a. The PMB system will be converted to a drum base file.
b. Actual man hours from the MIS weekly drum base file will
be transferred to the appropriate PMB file.
c. Users of the PMB file will have the capability to
retrieve via remote console information relevant to their
projects including man hours in a timely fashion.
9. Much of the work for the interim PMB manual card system has
been established and/or completed.
10. One program remains to be written to tie the IEG and BAD
systems together.
11. It is estimated that between 2-3 weeks of effort will be
required to complete this system.
Plans & Programs Division
PPBS/NPIC
SECRET
Approved For Release 2008/06/03: CIA-RDP73T00325R000100020034-4