Inspection Report No. 5 - RT-49/RF-49 (Classified)

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78-02820A001200030011-3
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
3
Document Creation Date: 
December 9, 2016
Document Release Date: 
August 23, 2000
Sequence Number: 
11
Case Number: 
Publication Date: 
June 17, 1966
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP78-02820A001200030011-3.pdf148.17 KB
Body: 
y OPTIQNAL FORM NO. 10 5010-107 C% r-o-Q9W0000 App +e 4Fpr ReIewe 2000/09/08-lffl%:ff 8-0282A001200030011-3 Memorandum EP 66-137 TO : The Files: Contract 3640-2105-4 DATE: 17 June 1966 25X1A9a -'VROM Mr. 25X1A5a1 ,i.eU13JECT: Inspection Report No. 5 -RT-49/RP-49 with .WNW 1. Project Description: 25X1C1a1 2. Contractual Information: a. Target Cost: $152,595.,00 b. Request for Procurement Action: 24 June-1964 c. Initiation Date: 29 June 1964 d. Completion Date: 1 June 1965 e. Deliverable Items: 300 RT-49's, 150 RP-49's 3. Date of Meeting: 31 May 1966 4. Place of Meeting: Falls Church, Virginia . Persons Attending: Exctudi % downgra pproved For Release 2000/09 030011-3 Buy U.S. Savings Bonds Regularly on the Payroll Savings lan Approved For Rele a 200 -RDP78-0282 A001200030011-3 EP 66-137 ,.TBJECT: Inspection Report No. 5 - RT-)+9/RP-)-E9 with 25X1A5a1 5. Persons Attending: Agency Non-Agency 25X1A9a Mr. Mr. 25X1 A5a' 25X1A5a1 6. Contractor's Performance: a. On schedule and expected to remain so: No b. Within obligated funds and expected to remain so: No c. Satisfactory technical progress: Yes 7. Project Status: delivered ten preproduction models late last summer and was given au orization to proceed with production last September. The program was turned over to their West Virginia facility for production. The first production units began arriving at our warehouse in early February. Several deliveries have been made since then. While the power supplies have been acceptable, we have not been as lucky with the trans- mitters. All of the 27 transmitters delivered were rejected. These units were all rejected for poor workmanship- top and bottom covers did not match, screws improperly seated, paint poorly applied, etc. IAMM At this meeting, - displayed one of the latest transmitters to be completed. Visual inspection of this unit showed no apparent defi- 25X1A5a1 ciencies. therefore, felt that they had overcome the difficulties in bui.ldin~-49 as far as mechanical problems are concerned, and delivery could proceed rapidly. Approximately 30 units are virtually completed and were being held at West Virginia pending our inspection of the first transmitter. Another 75 units are essentially completed with only assembly of the heat sink, main chassis, and back cover remaining. 25X1A5a1 feels a problem exists. . . . Approved For Release 2000/Q Q8g D , 'M~A001200030011-3 25X1A5a1 ti Approved For Release 2000/09/08 : 62820A00`l 200030011-3 EP 66-137 JTBJECT: Inspection Report No. 5 - RT-49/RP-49 with 25X1A5a1 25X1A5a1 -feels a problem exists in meeting the power output specifi- cation. A number of units were measured at the low, middle, and high end of each band when operated into a 40 ohm resistive load. The average power for the ten prototypes was measured last fall as 14.3 watts, 15.2 watts, and 13.7 watts for Bands 1, 2, and 3 respectively. (These measure- ments could not be duplicated the week prior to this meeting.) Figures 25X1A5a1 supplied to - by us on ten service test models built by 25X1A5a1 indicate 11.9, 12.9, and 10.7 watts average under similar conditions. 25X1A5a1 The average reading of 28 production units was 14.1, 11.5, and ... 11.5 watts, while the averag~r another 21~inits was 15.4, 13.1, 25X1A5a1 and 12.1. This latter group of 21 units was produced with more care toward selecting final transistors than was exercised in the group of 25X1A5a1 28 units. - proposed the following acceptance criterion-each transmitter submitted must meet a minimum average power output equal 25X1A5a1 to that of the ten produced transmitters. By this criterion, 25X1A5a1I nine of the 21 units would have been rejected. A number of agreements were reached. will continue to build 25X1A5a1 the RT-49 in West Virginia except for final alignment and assembly. This last step will be performed at Falls Church where - engineering 25X1A5a1 personnel can keep closer control. - will have a quantity of trans- 25X1A5a1 mitters shipped to Falls Church on 3 June 1566. These will be inspected visually and electrically at Falls Church and then hand-carried to T&I. Based upon the results of T&I's inspection we may accept, reject, or modify our acceptance criteria. No change in acceptable output power 25X1A5a1 was agreed to at this meeting. was complimented on the amount of data they had compiled concerning power output but we deferred considering any changes until we have an opportunity to test the next group of transmitters delivered. 25X1A9a Distribution: R&D Subject File OL/PD/PCB/CAS R&D Lab OC-OS ESB Monthly (3) EP Chrono 25X1A9a OC-E/R&D-EP b jp I 3 (17 June 1966) Ext down, Approved For Release 2000/09/08 : Cl