INFORMAL PROGRESS REPORT, RD-103

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78-03330A004100090007-6
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
1
Document Creation Date: 
December 22, 2016
Document Release Date: 
January 4, 2012
Sequence Number: 
7
Case Number: 
Publication Date: 
March 7, 1960
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP78-03330A004100090007-6.pdf44.06 KB
Body: 
Declassified in Part - Sanitized Copy Approved for Release 2012/01/04: CIA-RDP78-0333OA004100090007-6 7 March 1960 SECRET SDN No. RD 0-1135/23 of Copy 11 Page 1 of L SUBJECT: Informal Progress Report, RD-103\ fcL3 ' This letter constitutes the Forty-seventh Monthly Report, submitted in compliance with. Contract RD-103, covering the month of February, 1960. TASK 5. DEVELOPMENT OF AS-5 SYSTEM System No. 2 has been checked out, with the ex- ception of the power amplifier drawer. Most of the drawer wir- ing is now complete, and its several sub-assemblies are current- ly being tested. It is expected that final assembly of that compon- ent will be completed by March 9, 1960. Durin the ne od, System No. 1 will be moved to the Before shipping System No. 2 to the East Coast, local testing will be made be- tween the two systems. TASK 8. AS-6 DATA TELEMETERING SYSTEM The final report on the AS-6 Base Station is in the process of publication and should be completed during the next report period. The Field Unit final report will follow the Base Station report through the publication process. TASK 10. FABRICATION OF RS-16B Work on the Instruction Manual is well under way and should be completed during this reporting period. The four battery packs remaining on this contract were delivered during the reporting period. SECRET DOC /Q 3 REV DATE 1 1980 BY /$ ORIG COMP d4' OPI TYPE .14 ORIG CLASS st- PAGES REV CLASS 'ti JUST - NEXT REV a2LQ AUTNt HR 10?8 Declassified in Part - Sanitized Copy Approved for Release 2012/01/04: CIA-RDP78-0333OA004100090007-6