PROGRESS REPORT FOR JANUARY 1961 ON THE CLIP MODIFICATION RD 45, TASK ORDER CC
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP78-03642A001500040018-2
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
2
Document Creation Date:
December 27, 2016
Document Release Date:
November 1, 2012
Sequence Number:
18
Case Number:
Publication Date:
February 21, 1961
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 43.38 KB |
Body:
Declassified in Part - Sanitized Copy Approved for Release 2012/11/01: CIA-RDP78-03642A001500040018-2
(
PROGRESS REPORT
FOR
JANUARY 1961
ON THE
CLIP MODIFICATION
RD 45, TASK ORDER CC
21 February 1961
A-Du
NgA1/4),
/54(, 11
Declassified in Part - Sanitized Copy Approved for Release 2012/11/01: CIA-RDP78-03642A001500040018-2
Declassified in Part - Sanitized Copy Approved for Release 2012/11/01: CIA-RDP78-03642A001500040018-2
During a recent visit of the Project Officer early in
January, he requested that we start work immediately on the
prototype attache case. As an economical measure, we sug-
gested that the height of this case be increased slightly
to permit the use of the present standard
thereby avoiding the need of designing and fabricating
an additional size. In addition, it was further requested
that the case be provided
By the end
of the month, the wooden frame of the case had been fabricated,
and the microswitch well and lock wells out out. The micro-
switch assembly was completed and suitable looks were obtained
Sample
and reworked to provide the maximum area
eluded in this report.
FUTURE WORK
The
during the first
week in February and should be ready for inspection by the
customer by the middle of the month.
FINANCIAL STATEMENT
Total Amount of Contract
Expenditures for January 1961
Total Expenditures to 51 January 1961
Balance of Contract
Expiration Dates 1 July 1961
?
Declassified in Part - Sanitized Copy Approved for Release 2012/11/01: CIA-RDP78-03642A001500040018-2