ESTIMATED PROJECT COST
1.
Construction and Furnishings
A.
Construction
(1)
7 type C-2 dwellings (F-1) $13,995
$97,960.00
(2)
Site Grading and Paving,
13,201.00
(3)
Exterior Utilities
6,510.00
Subtotal
$117,671-00
(4)
Government Furnished Materials
and Equipment
8,666.00
(5)
Direct Government Cost
1,853.00
(6)
Indirect Government Cost
11,330.00
(7)
Contingency
12,633.00
Subtotal
34,482.00
Estimated Total cost
of construction
152,153.00
B.
Furniture and Appliances
(1)
Furnishings each house @ $660.
4,620.00
(2)
5 Refrigerators @ $330.
1,650.00
Subtotal
6,270.00
Total Project Estimate
158,423.00
C.
Over-all Project Contingency Total
4,,577-00
Total Project Costs
163,000.00
II.
Funds in FY 1956
A. Object Class 09
$ 20,000.
B. Object Class 10
143,000-
Total
163,000.00