MONTHLY PROGRESS REPORT, (Sanitized)

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B04747A001600020090-4
Release Decision: 
RIPPUB
Original Classification: 
K
Document Page Count: 
7
Document Creation Date: 
December 28, 2016
Document Release Date: 
April 19, 2000
Sequence Number: 
90
Case Number: 
Publication Date: 
April 7, 1964
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP78B04747A001600020090-4.pdf458.52 KB
Body: 
Approved For ReIeap 2000/06/07 : CIA-RDP78BO474 00160002 Memorandum STATOTHR .., ,',STATOTHR -. Declass Review, NIMA/DoD TO: Cortracting Officer STATOTHR FROM: SUBJECT: Monthly Progress Report, Contract' DATE: 7 April 1964 A. General STATOTHR The progress report is seperated into several sections, the first of which is a percentage summary of the schedule. This is followed by a statement on the progress and remarks on work completed, work in process and planned work effort. Finally a table showing each task and the percentage complete is supplied. The progress this month has been slightly slower than desirable. Our vendor for the coordinatograph tracks had one of these crack in the hardening process and a new one had to be ground. The ball screw vendor has reported that the screws were not yet within tolerance and could not be shipped. The vacuum platen vendor was called for a progress report and he claims not to have even received our purchase order. We have the original order copy and can verify that it was sent but it must have been lost in the mail or at his plant. This has never happened before and he said that he will place our order on a rush basis. On top of this one of our principal engineers has had a lengthy bout with the German Measles and his particular task portion has fallen behind schedule. We are in constant touch with these critical venders however, and are doing everything possible to expedite matters. B. Schedule Percent Required Major Project Tasks Percent Complete By Project :;chedule I System Engineering Il Subsystem D sign Ill Construction and/or 100% 100% Ap Oi di vrReteas61~000/06/07 : O W RDP78BO4747AO01600020090-4 AppTovgq,F6or ReJse 2000/06/07 : CIA-RDP78B0 47A001600020090-4 Mem o Page 2 IV Testing and Debugging V Final Inspection 30% 0% C. Summary of Progress 1. Room Specificat~TATOTHR Earlier this month MM cc"' ed from GSA to discuss the cooling and power problems. We sen a sketch confirming our Rhone discussion. STATOTHR STATOTHR STATOTHR We spoke with Mr. about the exact choice of pins for the 20 data bits, 2 Sign bits and 8 Special functions. Apparently there is some flexibility in the choice of these pins and the programmer can select an arrangement with certain restrictions that will make his work easier. We are not sure how this works out but it should be examined. 3. F lectronic Control Some of the most complex circuits in this system are contained in the velocity control section. These have very precise requirements upon them for speed of response, accuracy and stability. To accelerate their life test, the breadboard circuits have been performed almost entirely in a Tenny environmental test chamber which cycles the ambient temperature from near zero to over 1000F periodically. The test Is actually more severe than the environment expected but this activity hastens the demise of susceptable components. Even under these conditions the velocity control circuits do work and now they will now be removed from the chamber and placed into the electronic racks on card modules. Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020090-4 App rovelj For Re ase 2000/06/07 : CIA-RDP78BOW47AO01600020090-4 Memo o: l6 Page 3 D. Planned Work Effort The general schedule is as follows: Apri I 1. Use servo test apparatus 2. Transfer velocity loop breadboard circuits to rack modules. May 1 . Test servos on coordinatograph TWT/bd Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020090-4 Approved For Reljse 2000/06/07 -,Cl -RDP78BO4 7AO01600020090-4 e .} spa 4 vi'vrr wI roL