TRIP REPORT(Sanitized) 17-18 AUGUST 1964

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B04747A002700030071-2
Release Decision: 
RIPPUB
Original Classification: 
C
Document Page Count: 
2
Document Creation Date: 
December 28, 2016
Document Release Date: 
August 2, 2002
Sequence Number: 
71
Case Number: 
Publication Date: 
August 24, 1964
Content Type: 
MFR
File: 
AttachmentSize
PDF icon CIA-RDP78B04747A002700030071-2.pdf128.25 KB
Body: 
Approved For Relse 2002/08/20 : CIA-RDP78B04747A000030071-2 24+ August 1964 SUBJECT: Trip Report 17-18 August 25X1 25X1 25X1 25X1 1. The visiti was for the purpose of discussing proposed and additional-cnanges on e Chip Compara- 25X1 tor. Previously submitted by the contractor were ose changes suggested just prior to delivery These were discussed and accepted by the contract monitor as required changes. Questioned, however, was the cost of a number of the proposed changes, and a cost breakdown was asked for in these instances. Additional minor modifications were 25X1 discussed and the contractor will submit a cost breakdown on these items.5X1 The stop-work order and its effect on contract delivery was gone over will furnish correct information as well as the 0 interface on the minimum and maximum output p values so that can correlate :;s::] their counters accordingly. Deliverable items under the E can 25X1 were discussed .ill submit an addendum to the operational and 25X1 maintenance manual; will provide procurement data to the spare parts list and will submit the equipment drawings as soon as possible. 25X1 2. The visit Iwas for the 25X1 purpose of determining contract progress on the Chip rin er 25X1 beginning to take hold and is showing progress in the preliminary design area. Their hold-up is and has been the lack of clearances for the necessary personnel. Names have been submitted but clearances are not yet forthcoming. This has been taken up with the contracts people and is being followed closely. Several design ideas were presented, mostly on the film-gate and transport system. It was agreed would send 25X1 copies of trip reports and activities reports to the project monitor through the appropriate Post Office Box and that all else of a non-technical or contracts matter would go to the contracting officer. The possibility Declass Review by NIMA / DoD Aj Approved For Release 2002/08/20 : CIA-RDP78B04747A002700030074-2 Approved For Rel a 2002/08/20: ClA:R1DP78W4747A0 00030071-2 SUBJECT: Trip Report, 17-18 August 1964 Possibly this information is already available in some form ment exists, the contractor feels this should be a separate effort. of a film type study to ascertain the best base-emulsion combinations 25X1 for the desired output was discussed. If it is determined this require- 3. The visiti as made to determine progress 25X1 on the High Speed Coordinatograph. Progress is very satisfactory, there being the final electronic hook-ups and check-out to be made, control panel fabrication, and exterior protective skins where required. It is anticipated will be sent to Q toward the middle 25X1 of September for the purpose-77-electronic training on the instrument. It is also recommended that TID send a person at the same time to learn the operational and mechanical maintenance aspects of the instrument. Delivery of the plotter can be made anytime after 30 September 1964. The contractor has intentionally lengthened final fabrication and electronic assembly (original delivery date was 1 June 1964) at the request of the project monitor. This was done to insure a well designed operable instrument since time was available due to lack of building facilities. The estimate for installation facilities completion is now 1 October 1964, therefore been advised to submit a request 25X1 for contract extension to tha a e. 4. A visit IIwas extended to visit thelIinstallation 25X1 therefore, priorities have been established for time-sharing. The pro- blem is sent in by teletypewriter, translated and stored on disc drums. From then on depending on time available and priority, the computer goes from problem to problen, very seldom there being time to go through one complete problem without priority interruption. I was told the computer works on an average of two tenths of a minute each time on each problem. Each user is billed only that time required to complete his computation.2 5X1 I I A total of 25 stations can be operating at the same time, This is an experimental set-up to determine man-computer interface, methods of making computer time more available to the average company, development of compilers to translate everyday problems into computer language, and a score of other problems common to present day computer use. The computer is the work horse with 120 remote sta- tions F_ I 25X1 undersigned area to see thel _ Contact can be made through the It is recommended well worth the time of any visitors in the &A 25X1 Approved For Release 2002/08/20 : CIA-RDP78BO4747AO02700030071-2