EQUIPMENT INSTALLATION
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP78B04770A000800130005-6
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
1
Document Creation Date:
December 28, 2016
Document Release Date:
July 2, 2004
Sequence Number:
5
Case Number:
Publication Date:
July 30, 1965
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 21.28 KB |
Body:
Approved For Re*e 2004/07/29: CIA-RDP78B04770AO00130005-6
SECRET
25X1
PAR 238
30 Jul 65
SUBJECT: Equipment Installation
TASK/PROBLEM
1. Install and check out the following equipment at the customer's
facility:
a. Roller Transport Reversal Processor (12-Inch), (RT-12R).
b. Roller Transport Processor (24-Inch), (RT-24).
2. There was no activity during the month of July 65.
PLANNED ACTIVITY
3. The RT-24 processor will be shipped during August at the customer's
convenience.
4. The RT-12R will be shipped as scheduled on 5 August 65 with instal-
lation to start at the customer's facility on 9 August 65.