OVERRUN OF PROJECT(Sanitized) AND PROJECT #10147, PI PRINT ENLARGER(Sanitized)

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B04770A002800020008-3
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
3
Document Creation Date: 
December 28, 2016
Document Release Date: 
May 19, 2005
Sequence Number: 
8
Case Number: 
Publication Date: 
October 18, 1967
Content Type: 
MFR
File: 
AttachmentSize
PDF icon CIA-RDP78B04770A002800020008-3.pdf130.57 KB
Body: 
Approved For Release Declass Review by NGA. D RAF T NPIC/TDS/D- -67 18 October 1967 respectively). SUBJECT: Overrun of Project #10197, V' wgraph Maker [Contract I land Projec #10147, PI Print Enlarger Contract project 9619 and 9618 1. This memor,,a6dum presents a suggested format for a letter to I orporate ersonnel requesting that they review the subject projects. 2T1,The Projects for the Viewgraph Maker and the PI Print Enlarger are presently under separate contracts with the t - predicts that both of these contracts will require about a 50% overrun to complete. The Government is seriously concerned about the magnitude of these overruns and the fact that they were not anticipated sooner. It is hoped that will carefully examine its performance on these contracts to determine if they are representative of the standards by which is to be judged. significant historical data for each project Comments are included to'pes__,_~,.gnifeat aspects of cited documents or events. ~- At this time, the Government can find no gross technical de/ ciencies in the basic concept of the equipment being furnished under the subject contracts; although a thorough evaluation of technical performance must of Approved For Release 2~$ t?t. IA-RD r- k. 11 r- f 800020008-3 25 Approved For Release 201E FIN tr'ntA-RDP78BO477OA002800020008-3 of course, rest on the acceptability of the delivered items. However, 9 the target costs of the contracts have already been- and 25 estimates considerable design and engineering effort yet to be carried out. This, and comments from (July monthly report for the PI Print Enlarger (Statement A.3. - "Redesign was effected in a number of major areas."), suggest that technical performance was open to some The most disturbing aspect of performance rests in its 25 inability to predict costs either before or after contract negotiations. The Government puts great trust in a contractor's ability to accurately account for past costs and to predict future costs with a reasonable tiit"(~ F,) ~~f hetlSl2S !'~ AbIhi fA flF(Ph~^~'. ~~i rCehO'd~~ ~{V1t '2 coca." rla[4 w0.~Qaaa dCr Fc,1yit /L\ i4F~'~, i\\*CV 1 cf~ Ski, degree of accuracy. When the contractor grossly underestimates his future efforts, he creates administrative delays that prolong the completion of the project. He may also disturb the Governments R 4 D budget to such an extent that other projects are jeopardized. In the two projects under discussion, consistently predicted via its monthly reports that the projects were in no financial difficulty. were delayed, but verbal contacts with last monthly reports 25 project managers predicted 25 suddenly predicted a 50% overrun on the PI Print Enlarger, the Government was immediately concerned about the financial status of the Viewgraph Maker. However, two personnel reported that 25 the latter project would not have an overrun. Within two weeks, this statement was contradicted by the sane personnel and a 50% overrun was estimated. Approved For Release 2005/0 e-DP78B04770A002800020008-3 Approved For Release ) ~T CIA-RDP78B04770A002800020008-3 4 and for the Viewgraph Maker. The contracts were negotiated and signed should have estimated its target costs on the basis that only one contract would be signed. Since both contracts were let, and since both projects had considerable common technology, design, and even component parts, should have been in a position to exploit,' aS informed the Government's Contracting Officer flit it will not accept its estimated total costs to complete the projects as a ceiling price. Therefore, the Government is confronted with an uncertain total cost for either project and cannot assess the cost effectiveness of the equipment. `~-.&. Due to the magnitude of the estimated overruns n and because of uncertainty of these overruns, the Government to have spent a considerable unt of money and received virtually nothing for it. The Government1requests that review both projects and suggest any alternative courses of action that would be of more advantage to the 25 25 Support Systems Branch, DS/TDS Attachments: Historical Data for Project #10197, Viewgraph Maker Historical Data for Project #10147, PI Print Enlarger Distribution: Original - Route $ File /Contracting Officer, NPIC Originator a NPIC/TDS/DS 3 Approved For Release 200 JL.ffR fLA-RDP78B04770A002800020008-3 submitted independent proposals for the PI Print Enlarger