RAIL SPUR CONSTRUCTION HUNAN AND KIANGSI PROVINCES CHINA
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP78T04741A000300010018-7
Release Decision:
RIPPUB
Original Classification:
T
Document Page Count:
4
Document Creation Date:
December 28, 2016
Document Release Date:
May 24, 2002
Sequence Number:
18
Case Number:
Publication Date:
June 1, 1971
Content Type:
NOTES
File:
Attachment | Size |
---|---|
![]() | 1.61 MB |
Body:
SECRET
Approved For Release 2002/06/18 : CIA-RDP78T04741A000300010018- TPP
NATIONAL PHOTOGRAPHIC
INTERPRETATION CENTER
PHOTO
INTERPRETATION
NOTE
RAIL SPUR CONSTRUCTION
HUNAN AND MANGSI PROVINCES
CHINA
25X1
25.X1
TOP SECRET
Declass Review by NIMA / DoD
GROUP I. EXCLUDED FROM
AUTOMATIC DOWNGRADING
JUNE 1971
COPY NO
1 PAGES
PIN-088/71
Approves orTWelease 2002/06/18 : CIA-RDP78TO4741A000300010018-7
Approved For Release 2002/0&$11 CIA-RDP78TO4741A000300010018-7
Approved For Release 2002/06/18 : CIA-RDP78TO4741A000300010018-7
25X1
RAIL SPUR CONSTRUCTION, HUNAN AND
KIANGSI PROVINCES, CHINA
1. Two major rail spurs off the
Chu-chou to Nan-chang rail line were
observed under construction on photogra-
25X1 phy
2. Roadbed and grading for the
easternmost spur (in Kiangsi Province)
originate at 27-47-OON 114-42-35E, 3
nautical miles (nm) east-southeast of
Fen-i, and extend generally south for
approximately 80 nm, to 26-57-OON
113-58-15E. When this rail spur was
,,25X1 first observed on Iy a
few miles of r E I
con-
struction. Since then, however, the
roadbed has been extended to just north
of San-wan, and approximately 30 nm of
track has been laid. The completed
section of rail extends from Fen-i, to
a point 6 nm south of An-fu, at
27-17-30N 114-36-OOE, where some proba-
ble rail construction equipment was also
observed. Two rail yards were also
observed along this rail spur, one under
construction just north of Yung-hsin
and another, containing some rolling
stock, at An-fu.
3. The other rail spur (in Hunan
Province) originates at 27-39-35N
113-31-10E, just east of Li-ling. This
line consists of roadbed and grading
and extends in a generally southern
direction for approximately 70 nm,
terminating at 26-52-50N 113-35-OOE,
5 nm north of Cha-ling. No activi-';y
was observed at the origin at the rail
25X1
25X1
spur on photography
4. There is a 30-nm gap between
the two termination points with no
apparent linkup visible. Activity at
the ends of each spur appears to be
mining.
Approved For Release 2002/06/18 : CIA-RDP78T04741A000300010018-7
TOP SECRET
HUNS'
-1-
TOP SECRET
25X1
FIGURE I. RAILSPUR CONSTRUCTION, HUNAN AND KIANGSI PROVINCES,CHINA
25X1
Approved For Release 2002/06/18 : CIA-RDP78T04741A000300010018-7
-'--4--Competed r?ii fir
25X1
25X1
Approved For Release 2002 8SEURP78TO4741A000300010018-7
Approved For Release 2002) 8SEMff P78T04741A000300010018-7