TASHKENT PLANT PRODUCES DEFECTIVE BULBS
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80-00809A000600320282-3
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
2
Document Creation Date:
December 22, 2016
Document Release Date:
August 30, 2011
Sequence Number:
282
Case Number:
Publication Date:
June 20, 1950
Content Type:
REPORT
File:
Attachment | Size |
---|---|
CIA-RDP80-00809A000600320282-3.pdf | 86.02 KB |
Body:
Sanitized Copy Approved for Release 2011/08/31: CIA-RDP8O-00809AO00600320282-3
DATE
PUBLISHED
HOW
PUBLISHED
WHERE
PUBLISHED
..
CLASSIFICATION SECRET SECIEF
CENTRAL INTELLIGENCE AGENCY
INFORMATION FROM
FOREIGN DOCUMENTS OR RADIO BROADCASTS
Economic; Technological - Electrical industry
Daily newspapers
USSR
30 Mar - 5 Apr 1950
Russian
TN1~ V NIOT CONTAINf IN,OIIIATION AFFECTING TNT NATIONAL DEFENSE
or THE 01117[0 RAII0 WITNI. Till N0ANIN% OF GGMONAGG ACT It
G. C.. 21 AND Il. AG AN
ITS TNUi0U15111 III 00 ,iisoi If P1
SOURCE Newspapers as indicated.
CD NO.
DATE OF
INFORMATION 1950
DATE DIST. Jun 1950
NO. OF PAGES 2
SUPPLEMENT TO
REPORT NO.
THIS IS UNEVALUATED INFORMATION
TASHKENT PLANT PRODUCES DEFECTIVE BULBS
COMPLAINTS SWAMP BULB PLANT -- Pravda Vostoka, No 79, 5 Apr 50
Almost every day, letters from Riga, Novosibirsk, Baku, Leningrad and
other cities arrive at the Tashkent Electric Bulb Plant. The plant offi-
cials skim over the first few lines, then mark on the envelope, "For fi-
nance and sales department" or "For technical control department." Upon
reaching the appropriate department, the letters are then stuffed into a fat
folio marked "Complaints."
Literally hundreds of complaints against the quality of products are
pouring into the Tashkent Electric Bulb Plant. (Comrade Fayzi is the direc-
tor of the enterprise.) Tens of thousands of rubles a year have to be dis-
bursed in the settlement of claims by consumers against the plant.
There are huge losses in rejected bulbs at the plant itself. The com-
plaint folios don't begin to give a full picture of the losses.
Last year, the plant undertook to cut losses 40 percent. A technical
conference was held and measures to improve the situation were discussed and
approved. Nothing, however, has happened since. Materials remain of uneven
quality, technology is not standardized, and the experiences of successful
enterprises are completely ignored. Many necessary instruments are not avail-
able. Precision work is done by rule-of-thumb; shops are dirty.
The plant Party bureau has failed to exercise its right to check on the
managerial activities of the plant's administration. (Comrade Stepovaya is
chairman of the bureau.) It has, not seen to the implementation of the mea-
sures adopted at the technical. conference. The plant collective must launch
a concerted drive for technological progress, cutting of production costs,
and elimination of rejects.
STATE NAVY
ARMY AIR
MRS
FBI
- l _a_- ?U
r~wwgi'q
aTanntm
Zd~
Sanitized Copy Approved for Release 2011/08/31 CIA-RDP80-00809A0006OO320 282-3
Sanitized Copy Approved for Release 2011/08/31: CIA-RDP80-00809A000600320282-3
SECRET
PRODUCES NEW GENERATORS -- Leningradskaya Pravda, No 76, 30 Mar 50
By 27 and 29 April the Elektrosila Plant, Leningrad, will get out two
high-power turbogenerators, and also the stator for a hydroger_eretor.
Final machining of the rotor for a high-power hydrogen-cooled turbo-
generator has been completed 20 hjurs ahead of schedule. Assembly of tha
rotor is now under way.
GETS NEW MOTOR INTO PRODUCTION -- Kommunist, No 79, 2 Apr 50
The Yerevan Electrical Repair Plant has successfully completed its
March plan. It repaired above plan 24 electric motors and built a great
number of welding transformers above its quota. A new electric motor went
into production.