ALBANIAN RAILROAD CONSTRUCTION NEARS COMPLETION; FINISH NEW HIGHWAY, LAUNCH NEW MOTOR SHIP
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80-00809A000600360649-2
Release Decision:
RIPPUB
Original Classification:
C
Document Page Count:
3
Document Creation Date:
December 22, 2016
Document Release Date:
July 22, 2011
Sequence Number:
649
Case Number:
Publication Date:
December 4, 1950
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 125.41 KB |
Body:
Sanitized Copy Approved for Release 2011/07/22 :CIA-RDP80-00809A000600360649-2
' CLASSIFICATION CONFIDENTIAL
CENTRAL INTELLIGENCE AGENCY REPORT
INFORMATION FROM
FOREIGN DOCUMENTS OR RADIO BROADCASTS CD N0.
COUNTRY Albania DATE OF
-----~~~ -_ ~r~--u~~~== - A.DL1J, uigAway, roan, water
HOW
PUBLISHED Daily nexepapers
WHERE
PUBLISHED Tirana
DATE
PUBLISHED 15 Jul - 31 Aug 1950
LANGUAGE Albanian
THIS DOOVY[NT CONTAINS IN TORY ATIOX A//LDTINO TN[ NATIONAL D[i[Nf[
Of TN6 UXIi[D ETlT[S WITHIN TN[ Y[A NINO Of [l PIO NAO[ ACT t0
V. S. C.. )I ANO !i. AS AYtNOl O. IT[ TRANSYI9lIDN OR TNt R[Yt CATION
01 ITS CON T[NT! IN ANT YAN N[R TO AN UNAViNO RIi [D IERSON IS PR O?
NI LIT[0 LT LAW. R[IROOVCTION 01 TN IS ID RY I[ PRO XI lIT[0.
DATE DIST. ~ Dec 1950
SUPPLEMENT TO
REPORT NO.
THIS IS UNEVALUATED INFORMATION
ALBANIAN RAILROAD CONSTRUCTION NEARS COMPLETION;
rIHISH NEW HIGHWAY, LAUNCH NEW MOTOR SffiP
PEpiN-ELBASAN LINE WELL UNDER WAY -- Tirana, Bashkimi, 31 Aug 50
The 32-kilometer Pegin-Elbasan railroad line, now under construction, is
well under way. Thus far, 79.38 percent of the earthwork and 71 percent of
the concrete work have been finished. Of the total trackage of 35 kilometers,
6,007 linear meters have been laid so far.
Tracks are being laid from Peqin to the Paper station, and preparatory
work has been done for laying tracks in the direction of Elbasan.
Twelve bridges have been completed. The Bishgem tunnel, a mayor project,
was finished fln 25 August.
The following map shows the present status of the line:
Sanitized Copy Approved for Release 2011/07/22 :CIA-RDP80-00809A000600360649-2
Sanitized Copy Approved for Release 2011/07/22 :CIA-RDP80-00809A000600360649-2
CONFIQEI~TOAI
- 2 -
CO1VI'IDENTIAL
Sanitized Copy Approved for Release 2011/07/22 :CIA-RDP80-00809A000600360649-2
Sanitized Copy Approved for Release 2011/07/22 :CIA-RDP80-00809A000600360649-2
Peshkopi (Albanian Telegraphic Agency) -.- The ~~Rz.~a~~ gtate Enterprise has
,just finished the new motor road which conaectc> the chrome mine at Bulqize with
the Tirana-peshkopi rosd at Qafe a Dullit. The new road is over 4.2 kilometers
long.
Work on the road was begun in May. previously, the ore removed Prom the
mine was carried to Qafe a Dullit by cableway. The new road goes all the way
to the gal~eriee of the mine.
About 7,500,000 lek have been spent on the new road.
NEW ROAD OUTLET FOR BULQIZE MINE -_ Tirana, Bashkimi, 29 Aug 50
~QNF~L~ENTlA~
CONFIDENTIAL
DURRES YARD BUILDS MOTOR CRAFT -- Tirana, Zeri i popullit, 15 Jul 50
Durres -- The Durres Shipyard, which 5 years ago had orily one small shed
for the repair of a few insignificant vessels, has ,just launched the motor
ship 10 Korrik. The shipyard is now building motor boats, motor sailers, and
mod.era motor ships.
Vasil 7[haaxhi is the captain of the 10 Korrik.