PROGRESS IN CONSTRUCTION OF STALIN STEELWORKS AND OTHER INDUSTRIAL PLANTS IN HUNGARY
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80-00809A000700110175-4
Release Decision:
RIPPUB
Original Classification:
C
Document Page Count:
2
Document Creation Date:
December 22, 2016
Document Release Date:
September 14, 2011
Sequence Number:
175
Case Number:
Publication Date:
May 15, 1953
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 99.45 KB |
Body:
Declassified in Part - Sanitized Copy Approved for Release 2012/02/08: CIA-RDP80-00809A000700110175-4
r-
CLASSIFICATION COta'IDEhPLAL
SECURITY ILiFORM(1TION
CENTRAL INTELLIGENCE AGENCY
INFORMATION FROM
FOREIGN DOCUMENTS OR RADIO BROADCASTS
REPORT
CD NO.
DATE OF
COUNTRY Hungary
SUBJECT Economic - Metallurgy, building industry, chemi-
'~ cal construction
W
IBLISHED
TE
BLISHED
Budapest
21 Nov 1952
- 12 Jan 1953
rx a . x .exr . , . .,, x x.r~ x. re,rxrr
r1rxc uxrtm s ?ne..rtx~x rxcauxuacvxn nc n, rccn axa ire
.xe n?, or r?e ru.. coot. ?r ?xwom. in u??rxn mox ox .cva?
c?n ox or nr caxnxn ro a rucvr n x ? ? u,ro r sow u
. u?ma u
saxirnen e. u.. ... ....,,.,,.... _.. .. ..... ____ ._
DATE DIST. /J~i~$y 1953
SUPPLEMENT TO
REPORT NO.
Newspapers as indicated.
PROGRESS IN CONSTR[R;TIGN OF STALIN Si'EEIWORKS
AND OTHER INDUSTRIAL PLANTS IN HUNGARY
WILL COMPLETE NEW UNTIS OF STALIN STEELWORKS -- Budapest, Nepszava, 1 Jan 53
The major units of the Sztalin Vasmu (Stalin Steelworks) are to be completed
1n 1953. These will include the first 704-cubic-meter blast furnsce, two epen-
hearth furnaces, and the steelworks ~i~, The shed of the steelworks is large
enough to coTrtain 25 six-story houses. The rolling mills will be laid out i.n
iyi3? There will be txo rolling mills, each large enough to accommodate two
buildings, each the size o? the Budapest parliament building,
The harbor, power plant, 1,200 new apartments, and the palace of culture
will also be finished by the end of the year,
The palace of culture ~ii11 have an o,uditerium with a stage and motion pic-
ture screen, a ballroom, library, reading room, and lounge.
CEMENT WORKS NEAR COMPLETION -- Budapest, Magyar Nemzet, 21 Nov 52
The Dunai Cementmu (Danubian Cement Plant) now under construction At Va:
will have two 150-meter klinker furnaces, The furI]aCP.B will be housed i_n a
330-meter long building,
The cement works will provide the Sztalin Vasmu (Stalin Steel;vrf~) with
limestone, and barges from the Sztalin Vasmu will bring foundry al:~g to the
cement works, The furnaces and cableway for the T)nnni r ?>o>,+m? ,;;,, ,,,,,,,,, r..__
BUILD CHEFfICAL WORKS AT KAZINCHARCIKA -- Budapest, Nepszava, 1 Jan 53
Construction of the Borsodi Vegyimuvek (Borsod Chemical rr7orks) is ex~cte:?
tc increase the population of the village of Kazincbarcika to 16,000,
STATE
ARMY
CLASSIFICATION
NSRB
Declassified in Part - Sanitized Copy Approved for Release 2012/02/08: CIARDP80-00809A000700110175-4
Declassified in Part -Sanitized Copy Approved for Release 2012/02/08 :CIA-RDP80-00809A000700110175-4
The new chemical xorks x111 utilize the brown coal of Borsod Megye. The
new coal grader, xhich rill begin operating in 1953, will supply coal to the
power pleat and to the cokery,
The power plant x311 supply energy to the entire industrial regim of Borao3
Sid to the IIungarian plains,
The cokerywill represent ';he first attempt at converting Hungarian brown
coal itrto metallurgical coke.
COMPLETE STOREHOUSE AT KAZINCBARCIKA _.. Budapest, S~abad Nep, 12 Jan 53
The storehouse of the ICe.zincbarcilrai Kombinat (Kazincbarcika Combine) xas
completed on 10 January 1953?
The storehouse is 126 meters long, 28 meters high, and nearly 50 meters
aide. It was assembled from 707 prefabricated reinforced concrete units hav-
ing atotal weight of 31000 tone. A single pair of arches weighs 80 tons, and
each roof unit xeighs 2-g tone,
It took 3 months for a construction crew of 21 members to assemble the
building,
TC BUILD NEW TUBING PLANT -- Budapest, Magyar Nemzet, 27 Dec 52
A aev tubing plant x111 be built between Soroksar and Dunaharaszti near
Budapest, The new plairt rill help manufacture the enormous tubes required Por
the Budapest Subway,
COMPLETE NEW DIAINTENANCE GARAGE __ Budapest, Nepszava, 4 Dec 52
A garage and repair shop capable of housing and servicing 50 motor vehiclF-.
has been completed for the TEFU, NV, (Teherfuvarozo Nemzeti Vallai.at, Na-
tional FYeight Trucking Enterprise) in Nyiregyha~a, AL1 the washing, lubricat-
ing, and servicing equipment is completely automatic.
Declassified in Part -Sanitized Copy Approved for Release 2012/02/08 :CIA-RDP80-00809A000700110175-4