1. CHINESE COMMUNIST RAILWAY INSPECTION 2. SSUFANG RAILWAY SHOP, TSINGTAO

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP80-00810A000700430006-1
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
8
Document Creation Date: 
December 22, 2016
Document Release Date: 
October 20, 2009
Sequence Number: 
6
Case Number: 
Publication Date: 
April 13, 1953
Content Type: 
REPORT
File: 
AttachmentSize
PDF icon CIA-RDP80-00810A000700430006-1.pdf382.3 KB
Body: 
Approved For Release 2009/10/20: CIA-RDP80-0081 OA000700430006-1 CENTRAL INT_ELL.I.GEN.CE AGENCY INFORMATION REPORT This Document contelna info4metlon afeottn$ the Ne- ttonsi Defense of the United 8tetes, within the mean- ing of Title 18.8ecttons 780 end 7K at the U.5.Oode. es emended. Its trlnamiasioa or revelation of its oontenp to or receipt by on unsuthoriosd pelt I* 8xohtbtted by law. The reproduction of this farm is ptohthlted. CONFIDENTIAL/CONTROL- U.S. OFFICIALS ONLY SECURITY INFORMATION SUBJECT 1. Chinese Communist Railway Inspection 2. Ssufang Railway 6hopy.Tsingtao REPORT 25X1 DATE DISTR. '3 ?I -1953 NO. OF PAGES 6 REQUIREMENT NO. RD REFERENCES 125X1 THE SOURCE EVALUATIONS IN THIS REPORT ARE DEFINITIVE. THE APPRAISAL OF CONTENT IS TENTATIVE. (FOR KEY SEE REVERSE) a.group of Soviet railway specialists reported the yesults of an inspection of the Northwest Trunk Line,l the Chengtai Railway, and 25X1 erections of the Lunghai Railway to senior officers of the Chinese Communist Ministry of Railways. The inspecting party was made up of Cha-kang-te-yeh-fu (2610/1481/6671/5102/1133), a consultant; Hsi-lin (6007/2651), a bridge technician; Tsu-pu-k?o-fu (4371/1580/0668 1133), a depot and station technician; and Ao-ni-shih-k'o-fu (1,159/1141/4258/0668/1133), an engineer. LU Cheng-ts'ao (0712/2973/2347), the vice minister of the Chinese Communist Ministry of Railways, accompanied the grapp. The principal mission of the inspection group was a survey of the Paoch'i-T'ienshui railway and of engineering projects in T'ienshui and Lanchow. 2. As a result of the inspection, the following criticisms were made: a. Preliminary surveys of complex terrain features such as those at Wuch?iao-ling (N 37-11) E 103-01) were inadequate. b. Construction and maintenance were difficult because the original plans called for a 1,160-meter tunnel with a gradient of five in 1,QOO; for a'90- kilometer stretch just west of the tunnel, which included gradients of 20 in 1,000 and would requi'e the use of two locoiriotives; and for numerous, high bridges, roadb s " rid 'funnels. CONFIDENTIAL/CONTROL - U.S. OFFICIALS ONLY [STATE ARMY ,~ NAVY I ,. I A I R I . I FBI I I AEC Approved For Release 2009/10/20: CIA-RDP80-0081 OA000700430006-1 Approved For Release 2009/10/20: CIA-RDP80-00810A000700430006-1 CONFIDENTIAL/CONTROL - U.S. OFFICIALS ONLY -2- c. Existing roadbeds were not included in construction plans. d. Engineers did not understand the earthwork problems in the construction of high roadbeds, some more than twelve meters high. e. Engineers did not follow the ministry's recommendations in building roadbeds according to the "layers reinforced with piles" method. f. There was a lack of coordinated development and planning. Only 38 percent of the Northwest Trunk Line, 57 percent of the earthwork for the 1 enshui- Lanchow Railway, and two percent of the housing construction had been completed g. There was no relationship between project development, investment, and project value. h. Project price lists (sic) were not organized and there were no cost estimates. i. The force of 60,000 laborers and the machinery on the Northwest Trunk Line project were not used efficiently. j. WU Ko-chin (2976/0668/0036), the deputy director of the Northwest Trunk Line Engineering Administration, was unable to answer important questions raised by the inspecting party and was unable to provide a project progress chart. k. Adequate data was not collected prior to the planning of bridge and tunnel construction. Bridges were constructed with arches so small that water' destroyed them immediately. 1. Engineering personnel authorized construction modifications at will. The buttresses, structure, dimensions, and depth of the Weiho (N 3L+-, E 109- ) bridge were altered. m. Engineers did not use construction material from the immediate area. n. Engineers failed to construct embankments and structures for flood pre- vention work in the proper sequence, to install sufficient railings and ballast, to erect aqueducts before tunnel construction, and to provide adequate mechanized equipment. Sixty persons, each manipulating a rope, were used in place of a pile-driver to imbed reinforced concrete piles for bridge foundations. 3. The following recommendations were made: a. A special plan should be prepared for roadbeds twelve meters in height with specific instructions regarding the gradient of adjacent land. b. The ballast for sleepers on bridges should be 20 to 25 centimeters thick. c. More attention should be given to the use of signal equipment, water supply facilities, and other operational equipment. d. Large depot and terminal planning should be centralized in one agency. e. Engineering graduates should be assigned to large stations to study railway operations. CONFIDENTIAL/CONTROL - U.S. OFFICIALS ONLY Approved For Release 2009/10/20: CIA-RDP80-00810A000700430006-1 Approved For Release 2009/10/20: CIA-RDP80-00810A000700430006-1 CONFIDENTIAL/CONTROL - U.S. OFFICIALS ONLY -3- f