Sanitized Copy Approved for Release 2009/11/23: CIA-RDP80-0081OA002700790004-2
Sanitized Copy Approved for Release 2009/11/23: CIA-RDP80-0081OA002700790004-2
Sanitized Copy Approved for Release 2009/11/23: CIA-RDP80-0081OA002700790004-2
CENTRAL INTELLIGENCE AGENCY
INFORMATION REPORT
This Document contains Information affecting the Na-
tional Defense of the United States, within themean-
ing of Title 18, Sections 793 and 794, of the U.S. Oode, as
amended. Its transmission or revelation of its contents
to or receipt by an unauthorized person is prohibited
by law. The reproduction of this form is prohibited.
25X1
SECRET/CONTROL - U.S. OFFICIALS ONLY
COUNTRY Hungary
SUBJECT Hungarian Railroads
DATE OF INFO.
PLACE ACQUIRED
REPORT
DATE DISTR.
NO. OF PAGES
REQUIREMENT
REFERENCES
THE SOURCE EVALUATIONS IN THIS REPORT ARE DEFINITIVE.
THE APPRAISAL OF CONTENT IS TENTATIVE.
(FOR KEY SEE REVERSE)
le Budapest Northern Railroad Bridge.
Steel girders for the span of the Ujpest bridge are assembled near the old Horthy
Miklos bridge on Boraros tor. The bridge is expected to be finished about mid 1954.
2. Budapest Southern Railroad Bridge.
A new span has been completed, besides the reconstructed old span.' The emergency
span is being dismantled. The bridge will eventually carry vehicular traffic and
double railroad tracks.
3.. Budapest Subway.
Cave-ins have ocourred during work on the Budapest subway at Kosauth t(r and at the
National Theatre.
4. Locomotives.
The boilers of 40 locomotives constructed by the Mavag Works for the Hungarian State
Railroads have been found to be faulty. Because they did not prove to be steam-tight,
it was decided to scrap theme
5. Hegyeshalom Budapest Line.
25X1
Automatic signal oontrolL I is being installed along the Hegyesha-
lomBudapest line.
6. Budapest-Baja Line.
The line from Budapest to Kunszentmikl6s has double tracks. It is then single track
from Kunszentmiklos-Ki.sVlSrF6s-Kiskanhalas-Jfnoshalma-Bacsaln s to Baja. The line from
Baja-Alarony4k-Szekszard-Cece-Pusztaegres is single track. After Pusztaegres it is
double track.
SEGRET/CONTROL U.S. OFFICIALS ONLY
STATE X ARMY X NAVY X AIR X FBI J JAEC
(Not.: Washington Distribution Indicated By "X"; Field Distribution By "#".)
21 October 1953
Sanitized Copy Approved for Release 2009/11/23: CIA-RDP80-0081OA002700790004-2
Sanitized Copy Approved for Release 2009/11/23: CIA-RDP80-0081OA002700790004-2
SECRET/CONTROL U.S. OFFICIALS ONLY
7. Dunapataj-Baja Line.
A new single track railway line is being built on the left bank of the Danube from
Dunapataj via Kaloosa-Dusnok to Baja. It is expected to be finished by the end of
1953.
8. Bridge at Baja.
The Danube bridge at Baja has not been improved. The bridge is still single track,
with a roadbed laid over the railroad track, so that road traffic must be stopped
when trains are passing.