ODP COMPUTER INSTALLATION PLAN FY 77
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80-01003A000100120001-1
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
27
Document Creation Date:
November 16, 2016
Document Release Date:
May 11, 2000
Sequence Number:
1
Case Number:
Publication Date:
September 15, 1976
Content Type:
REPORT
File:
Attachment | Size |
---|---|
CIA-RDP80-01003A000100120001-1.pdf | 996.86 KB |
Body:
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
ODP
COMPUTER. INSTALLATION PLAN
~4~ / ~q 1,-7~
O - O/vv3 4
.15 September 1976
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
I INTRODUCTION
II OBJECTIVES AND DIRECTION 3
III PLAN DETAILS 4
- Phase I TASKS 5
- Rhase II TASKS 6
- Phase III TASKS 8
- Phase IV TASKS 10
APPENDIX A
Teleprocessing Support 11
APPENDIX B
- Computer Usage Projections 12
APPENDIX C
- MBO
- Major Milestone Pert Chart
14
General Center Configuration ' 20
and Backup Capabilities
- General Center 21
Machine Utilization
- 3350 Disk Configuration 22
ATTACHMENT Xl
- VM Projections
ATTACHMENT X2
GIMS Projections
ATTACHMENT X3
- Batch Projections
24
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
I. INTRODUCTION
This paper describes the plan developed by Engineering
Division for existing and projected computer systems and
networks within the General and Special Centers over the
Fiscal Year 77 time frame. The basis for this plan is
threefold:
A) Acceptance by the Agency of the OJCS Five
Year Plan of January 1975 calling for the
acquisition of 4 IBM 370/168s.
Policy guidance from the DD/P/ODP concerning
the use of CPUs over this time period, and
C) A three day planning session held at - on
8 through 10 September 1976.
This plan represents the first attempt to address b
ODP Computer Centers as a single processing entity. It
is felt that taking initial steps in this direction now
will aid the planning effort in the future. The period
covered by this plan is September 1976 until November 1977.
It superceeds the existing 18 Month Plan and the draft
GC-03 Computer Installation plan dated 27 May 1976.
The major points of interest during this time frame
are the arrival of the 168-3 and a fourth large scale
machine, the conversion of ASP to JES3 and MVT to MVS, an
enhanced VM processing capability, and an improvement in
GIM availability. As of November.1977, ODP will have
the full capability to back up all major systems with
limited impact on other systems in the General Center.
A T-.bar switch will be installed in the Special Center
to permit sharing a pool of unit record devices among
up to four CPUs at a time.
The concept of a "single system image" for the General
Center was reviewed in light of the increasing complexity
and found to be still viable. The primary reasons for
this assessment are that any disadvantages wrought by
adding CPUs to the network are offset procedurally by
the greatly simplified switching configuration and
the economies of scale that are realized in a large
spooling environment. The single system image allows. CPUs
to be added to a network without a linear increase in
number of operators, RJE links and printers required.
(1)
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
This plan is, divided into four phases with Phase
I
ending 30 September 1976, Phase II ending 31 January
1977,
Phase III ending 30 June 1977 and Phase IV completing
the
plan on 1 November 1977.
Appendix A contains plans for Teleprocessing support-
during this time frame. Appendix B contains workload
projections for the major systems which will be supported
by this plan. Appendix C represents the implementation
schedule of this plan in terms of a Management by Objectives
(MBO) approach. Appendix C also contains the initial and
terminal CPU configuration for the General Center together
with the design for the 3350 disk implementation, and a
Gantt chart of machine utilization in the General Center
during FY77.
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
(2)
Approved For Release 2000/06/01 : CIA-RfEWH)1003A
II OBJECTIVES AND DIRECTION
The plan presented in this paper is designed to
meet our projected requirements in the General and
Special Centers through Fiscal Year 1977 and to improve
the level of service to the user community in terms of
response-, throughput and availability. Specific
objectives are outlined below with respect to each Center:
General Center
A. Conversion of ASP to JES and of MVT to MVS.
B. Smooth transitional period while new hardware
and software are introduced.
C. Installation of a fourth large scale CPU as a
single enhanced VM processor.
D. Backup capability for each major system with
limited impact on other production systems.
E. Data Security and Integrity.
F. Degree of isolation.for the GIM Production system.
Special Center
Obtain specific requirements for CPU power
through coordination with DDO personnel.
B. Perform feasibility study which surfaces issues
impacting on the installation of a larger CPU
in GC47.
C. Install a T-bar switch which permits unit record
equipment and terminal controllers to be accessed
by any CPU in the center. Knowledge gained from
this experience will be a basis for improved
switching configurations in both centers.
D. Install Comten 5 to support the CRS DRS project
and migration to a fourth CPU. IT) CS
Approved For Release 2000/06/01 : CIA-RDP80-OJ903A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
III PLAN DETAILS
The implementation of this plan is divided into
four phases. Each phase is summarized in a paragraph
below. Key milestone dates are enumerated by each
center in the charts that follow.
Phase I _is largely preparatory in nature as the
General Center is made ready for the arrival of the
168-3. A study will be conducted to inform management
of issues concerning processing of Z tapes or non-
labeled tapes under MVS.
Phase II addresses the period beginning roughly,
with the arrival of the 168-3 and ends as it completes
its role as the MVS/JES3 Production Test machine.
During this phase most batch work will be moved to
the 168-2 and GIM Production to the 195to provide a
backup capability for the MVS Global machine. A study
will be conducted to determine the feasibility of inter-
facing VM/370 with TMS. Another study will be under-
taken to surface the logistical constraints associated
with an addition of a fourth large-scale machine in
GC47. The tradeoff between HASP or ASP for the Special
Center will be analyzed. A benchmark study and an RFP for
the fourth large-scale CPU for the General Center will
be prepared.
Phase III begins with the implementation of an
MVS/JES3 Global as the production-status replacement
for the ASP Support system. The GIM Production will be
provided with an enhanced degree of isolation from
other major systems in the General Center. A plan for
the installation of an Uninterruptable Power Source
(UPS) in GC47 will be completed. The Special Center
will implement the TMS-4 Tape Management System.
Phase IV includes the arrival of the fourth-scale
machine and the implementation of an MVS Local Main in
the General Center. VM/370 will migrate from the 168-1
to the fourth machine. Either HASP or ASP will be
implemented in the Special Center Blue depending upon
the decision made in Phase II.
4
Approved For Release 2000/06/01 : CIA-RDP80-0 0 3A000100120001-1
Approved For Release 2000/06/01 CIA-RDP80-01003A000100120001-1
PHASE I
Current - September 30, 1976
General Center
360/652 360/195
370/158
Special Center
GIMDEV
CAMDEV
370/168-1
General Center
1. Order 370/168-3
- Establish firm ship date
2. Order Resource Manager for VM system
3. Complete ODP S/L Tape study
4. Complete 168-3 site preparation
5. MVS/JES3 Activities
- Complete MODS 3
- Complete initial operator training
Complete training guide/procedures
- Complete MVS test plan
Special Center
NIPS
Batch
651
3601651
1. Complete upgrade of tape drives to 6250 BPI.
Approved For Release 2000/06/01 : CIA-RDP80003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDFFfl i 1D03J 000100120001-1
01 October 76 - 31 January 77
General Center
31. October 76
360/652 360/195 370/158 360/652
GIMDEV
CAMDEV
CRS
GIMDEV
2250
CAMDEV
370/1681 370/1682
370/1681
ASP
GIMP
VM
Batch
MVS
rod/test.
1. Implement TMS Rele
ase 4
(11
October 76)
2. Implement Comten I
V
(26
October 76)
3. Provide additional
GIMP 3330 Di
sk
(26
October 76)
4. Update Master Addre
ssing Pl
an
(31
October 76)
5. -Complete 370./168-3
installa
tion
(01
November 76)
6. Complete VM/TMS st
udy
(15 November 76)
7. Implement 168-3 as
full VM
back
up system
(15 November 76)
8. Implement 168-3 fo
r MVS/JES
3 Pr
oduction/Te
st
(15 November 76)
9. Implement Updated 1
68-2 I/O
Gen
(15
November 76)
10. Complete installat
ion of 2
PDP
11/45's
(30
November 76)
11. Update GIMP disk a
ddressing
(30
November 76)
12. Implement updated
195 I/O G
en
(06
December 76)
13. ASP and GIMS to 19
5
(13
December 76)
14. Implement VM Relea
se 3
(13
December 76)
15. Gould Plotter to 1
68-2 via
2914
switch
(13
December 76)
16. SIS complete 370/1
68-4 Benc
h Ma
rk (MVS/VM)
(03
January 77)
17. CMB complete 370/1
68-4 RFP
(03
January 77)
18. Release 2250
(31
January 77)
19. N/P hardware backu
p capabil
itie
s
(31
January 77)
20. Reconfigure tape p
21. MVS/JES3 Activitie
ool
s
(31
January 77)
- Batchmon RSCS te
st versio
n
(01 November 76)
- MVS/MVT catalog
solution
(01 November 76)
- MVSDEV 1581 bloc
ktime
(Oct. - 01 Nov. 76)
- MVS/JES3 weekend
full cen
ter testing
(30 January 77)
31 January 77
x360/195 1 370/158 1
ASP
GIMP
370/1682 370/1683
Approved For Release 2000/06/01 : CIA-RDP> (3g1003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
PHASE II
01. October 76 - 31 January 77
Special Centel
158 Blue 158 Red
NIPS
Batch
1. 370/1.68 or equivalent study
2. SVS local level I
3. Install new Patch Panel
4. Install Comten IV
5. HASP or ASP decision
6. Complete 360/65-1 Contingency Plan
7. Complete implementation of T-bar switching
unit
(15 November 76)
(15 November 76)
(01 December 76)
{01 December 76)
(03 January 77)
(31 January 77)
(31 January 77)
(7)
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
PHASE III
01 February 77 30 June 77
General Center
01 February 77
360/652 .360.1.95
GIMDEV
ASP
CAMDEV
GIMP
370/1681
1. Implement 6250 BP1 drives for VM Bkup & GIM DDUMP
2. Implement MVS/JES.3 Global on 168-3
3. Implement MVS/JES3 Global Backup on 168-2
4. Isolate GIMS Production on 360/195
With GIMS batch work
- With stand-alone capabilities
5.. Implement GI.MS Release 4.0
6. Install 415 UPS
7. Install IBM 3350's for MVS/JES spools
8. Complete. MVS conversion plan
9. Implement VM Resource Manager
10. Upgrade patch panel
11. Expand Comten I and Comten IV
12. Complete VM/VSAM requirement study
13. implement Mini computer base hardware
monitor system
370 1.683
MVS
Prod/test
360/652
GIMDEV
CAMDEV
370/1681
30 June 77
.360/195 370/1 8
GIMP
370/1682 370/1683
MVS
Global
Main
(01
February
77)
(28
February
77)
(28
February
77).
(28
February
77)
(07
March
77)
(28
March
77)
(28
March
77)
(1.7
April
77)
(30
May 77)
(30
May 77)
(27
June
77)
(30
June
77)
(30
June
77)
(8).
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
MVT
Main
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
PHASE III
01 February 77 30 June 77
Special Center
NIPS
Batch
TASKS :
STAR
1. Complete UPS Conversion Plan
- Provide support to CAMS
2. Implement TMS on Red/Blue systems
3. Complete user TMS Conversion Plan
360/65-1
(28 February 77)
(25 April 77)
(25 April 77)
Approved For Release 2000/06/01: CIA-RDP80~ Q 1003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDPRA79~0g3J000100120001-1
01 July 77 - 01 November 77
General Center
r 60/652
GIMDEV
CAMDEV
01 July 77
37011681 _170/1682
.MVT
Main
370/1581 652
GIMDEV
CAMDEV
370/1683
MVS
Global
Main
.370/168
1
MVS
Local
Main
370/168
4*
VM
01 November 77
360/195 370/1581
370/1682
MVT
Main
*or equivalent
TASKS:
1.
Install IBM 3350's for VM mini disk space
(25
.2.
Install 370/168-4 or equivalent
(01
3.
Install IBM 3350's for VM/VSAM space
(31
4.
Complete move of VM to 370/168-4
(01
5.
Implement 370/168-1 as MVS local main
and online global backup
Special Center
(01
_15R_-B-1 ve_ 158 Red-
_3601.65J
NIPS
Batch
TASKS:
1. Implement ASP or HASP on Blue system
370/1683
MVS
Global
Main
July 77)
October
77)
October
77)
November
77)
November
77)
0
Approved For Release 2000/06/01 : CIA-RDP8-0 003A000100120001-1
STAR : CAMS
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1A P P E N D I X A
Teleprocessing Support Plan
At present all GC03 Comtens access our major systems -
VM, GIM production, and GIM development. Comten 1 and
Comten 4 provide RJP support for ASP. Comten 2 and Comten 3
provide support for CRS.
As of August, 1976 the Comtens supported 544 terminals
(excluding RJP devices). The Comten l expansion which
went production in September added 48 terminal ports for a
total of 592. In October, when Comten 4 goes production, an
additional 144 terminal positions will be added. This will
bring our total to 736 ports in GC03. In June 1977 Comten 1
and Comten 4 will each be upgraded to add 64 ports. This
will increase to 864 the number of asynchronous ports.
This number represents an increase of 320 ports over our
August 1976 configuration.
There are approximately 80 terminal requests outstanding.
The expected rate of terminal requests is 130 per year. We
therefore project that terminal growth well into FY78 will be
covered.
Comten 4 will be a backup for ASP/JES RJP. OC has to
relocate or eliminate the analog line drivers used on the
Northrop-Page circuits for Comten 4 to provide backup for
these lines.
The June 1977 Comten 1 and 4 expansion will utilize
the new Comten DLC MIM. This MIM (Modem Interface Module),
provides expanded capabilities.
JES3/MVS testing will be supported by Memorex 3. Eight
bisynch lines will be available for testing.
Comten 5 will be received in November for support of the
CRS DRS project. Comten 5 will have 3 channel interfaces.
This will allow for easy installation of an additional CPU
in GC47.
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
APPENDIX B
Computer Usage Projections
To insure that sufficient processing power will be
available to meet ODP requirements during FY77 each of the
major categories of service were analyzed. The major ODP
categories of service are:
1) The STAR system in the Special Center.
2) NIPS and Batch Processing in the Special Center.
3) CAMS in the Special CEnter.
4) GIMS production in the General Center.
5) GIMS Development in the General Center.
6) VM in the General Center.
7) Batch Processing in the General Center.
The STAR system is currently run on the Red 158 in the
Special Center. This on-line system has recently been the
subject of an optimization study which resulted in improved
response time characteristics. Although additional functions
are planned for this system. its' requirements will not
exceed the capacity of the Red 158 in FY77.
The Blue 158 in the Special Center is used for NIPS,
Batch Processing and as backup for both the STAR and CAMS
on-line systems. This machine will be sufficient to satisfy
these requirements through FY77..
The 360/65-1 in the Special Center is dedicated to the
CAMS on-line system. Both the 65-1 and the Blue 158, in the
backup mode, provide sufficient processing power for this
requirement.
The 360/65-2 in the General Center provides service for
the GIM Development System and some small on-line functions
(SANCA, MILTEL, 2250, etc.). This machine is capable of
meeting the processing requirements of these applicatio-ns
through FY77.
Approved For Release 2000/06/01 : CIA-RDP801011%63A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
The remaining applications, VM, GIMS production and
Batch Processing are run in the General Center. These
service categories are characterized as growth applications
with significant increases in processing power requirements
over time. Attachments X1, X2 and X3 present, graphically,
CMB's projections of requirement growth for these applications
through FY77.'
The VM projection is presented in terms of the number
of concurrent users logged on during peak periods. These
period are typically, mid-morning and mid-afternoon of each
working day. The?ODP FY77 plan calls for this requirement
to be satisified by the 168-1. This machine, with the added
software enhancement of the Wheeler Scheduler, should be
able to provide good service for up to 160 concurrent users.
Should demand rise to the 1'80 concurrent user level projected
in this plan, some degradation in response time may be
expected near the end of FY77.
The GIMS Production Projection is presented in terms of
number of transactions per day. The GIMS on-line transaction
day is measured from 0800 hours to 1800 hours with weekends
excluded. The 360/195 will be more than sufficient to
process the maximum projected demand through FY77.
The final service category, Batch Processing in the
General Center, will be run initially under the ASP scheduling
supervisor. When the MVS system is ready for production use,
in the spring of 1977, this work will be run in the MVS/JES3
environment.
Batch Processing in the General. Center is measured in
terms of 360/65 equivalent hours. The 370/168 is rated as
capable. of producing 4 360/65 CPU equivalent hours per hour
while the 360/195 is rated at 7 360/65 CPU equivalent hours
per hour. The 168-2 and 168-3 in the General Center will be
capable of meeting the projected demands for this service in
FY77 and allow for some MVS development time as well.
Approved For Release 2000/06/01 : CIA-RDP 3gfl 003A000100120001-1
OBJECTIVE AND ACTION PLAN
0@JECTIYE
ove F
A
p
NO.
OBJECTIVE
1. Implement TMS Release 4 in General Center
2. Implement Comten IV in General Center to
provide RJP backup and additional VM and
GIM lines
3. Update General Center Master Addressing an
4. Complete 370/168-3 site preparation
Increase ODP computer processing capacity,
availibility and reliability.
Complete 370/168 or equivalent study for
tudy in Genera Center
Complete 370/168-3 installation in Genera
Center
Implement updated software system for the
370/168-2 in the General Center
10. Implement updated software system for the
? 360/195 in the General Center
11... Move ASP Support and the GIMS Production
Special Center.
Implement Update system software SVS Loca
Level I in Special Center
system in the General Center to the 195
01Y20b9 "' ?1'RCI ESTIMATE
PERIOD
SEP - OCT~
NOV - DEC I F
MAR - APR
MAY _,,.1111) _
} F%CECDING PLAN
MEETING PLAN
< CEHIND PLAN
-
" FEl1 ` ARC j
I' FA7CT~ t a
j t o (, S
f? fi- ~n,- V u'-. J 'j
LA
Approved For Release 2000/06/01 : CIA-RDF 80-01003A000100120001-1
OBJECTIVE AND ACTION PLAN
Apps
F PER I I IS A LI)'8
Jul A1,f1
SEP ? Oct
FY 77 Cont
00A.101 R " 1 ibb
12. Install additional Patch Panel in the
Special Center
13. Install Comten V in the Special Center
14. SIS complete 370/168-4 Bench mark MVS/VM
l5. CMB complete 370/168-4 RFP
16. Provide backup hardware capabilities for
the N/P area
T7._ Reconfigure the General Center tape pool
to add the 6250 BPI drives and as
required by updated functions.
18. -Complete,study for HASP or ASP decision
in the Special Center
19. Complete 360/65-1 contingency plan for
the S ecial.Center
2 . Implement 6250 BPI tape drives for the
VM and GIMS system
21. Implement MVS/JES3 Global system soft-
ware on the 370/168-3 in the General
Center
001f 0120 'l RI nuRc, fsi IMA TE
MYR 1 0OLLARS
Approved For Release 2000/06/01 : CIA-RDP180-01003A000100120001-1
IYE'C"" -57 MAr.
MAC th'' Ylr*/ ~ uti
09JCCTIVf OFFICE RCSPONSItjLF OFFICER ~~ 1'1 RI:RUR(.T C rIMATE
NOA rved or a ea0/0 010 1200
1
PLPI n I Tnl'+
pp MiA aoI 1 nR^
Ar~~
TIVE
707LC
IP .Anr1 f __..
.IAN t r' fl
.
?
MAR pI II
MAY ? JUN
F L*CF.FnnNG PLAN
= MELTINr PLAN
< CF.'IINO PLAN
ACTION PLAN (Milestones)
COMPLETION MONTH: SCHEDULED O; ACTUAL X
acT
N ~~'
DEC.
.3ra..~
r
MAQ-
flr'!t-
Ihn/
,un.
Jam
/4u(,
~~ c F j
FY 77 Cont
22. Implement MVS/JES3 Global backup
capabilities on the 370/168-2
0
23. Isolate GIMS production system on the 195
in the General Center
0
24. Complete plan for installation of UPS-in
the Special Center
0
.25. Implement updated GIMS software Release
4.0
0
26. Install 415 UPS in the General Center
0
27. Install upgraded disk, 3350 for MVS
spools and additional VM mini space
0
28. Implement TMS in :the Special. Center for
the Red/Blue systems and complete
0
conversion plan
29. Implement VM resource manager
0
30. Upgrade Patch Panel in the General Center
0
31. Expand Comten I and Comten IV
0
:320. Complete VM/VSAM study
0
F
ORM 3629
7. 7%
Approved For Release 2000/06/01 : CIA-RD~80-01003A000100120001-1
OBJECTIVE AND ACTION PLAN
33. Install IBM 3350's for additional VM
mini space
34. Complete 370/168-4 or equivalent site
preparation in the General Center
JAN FER_J
MAR APR
MAY
4 EXCEEDING, PLAN
= MEETING PLAN
EEHIND PLAN
0E`I MI i% Mn' I1)1?9- 1 "(13*j1, 1JUL IFUG
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
Y R;ORCF ESTIMATE
0426 -,
IMPLEMENT A ? __UP.,9 P roved For Release 2000/06/01 : CIA-RDP80-tq(3~000100120001-1
MVS USER CONVERSION PLAN
(G14
GENERAL CENTER
FY 77
MAJOR MILESTONES
M_V SIL~GlO 684 G20 ._.LNSTALI
PROD-1683 G1 M P L E KHL-~GG LOBAL 15 ITE PREP (1684)
1683 BKUP !G11
UM SYSTEM GLOBAL
ISOLATE GIMS;'G12 1
1684 ;Dl?NCH MARK (VM/MVS
COMPLETE (1684)--M
IMPLEMENT 3350'2 FOR MVS SPOOLS
IMPLEMENT 3350' 2
G19 OR-VM-mIITr`SVAcE
COMPLETE VM/VSAM REQUIREMENT STUDY
Approved For Release 2000/06/01 : C1A-RDP80-01003AO00100120001-1
TMPI FMFNT f G05)BAICHLGOULD,
195 10 GENE /TO 1682
MASTER ADDR rr-n' 1MPLFMENT (rnr, \
PLAN \ ) 1682 10 GEN`\ TO 195
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
SPECIAL CENTER
FY 77
MAJOR MILESTONES
LOCAL LEV I
ASP/HASP DECISION
651 CONTINGE
PLAN
CH "" COMTEN V
PANEL
IMPLEMENT -T
Approved For Release 2000/06/01 : CIA-RD~80-01003A000100120001-1
Approved For Release 2000/06/03e Ac FMRW003A000100120001-1
Configuration and Backup Capabilities
Current (PHASE I)
GIMDEV
CAMDEV
2250
SANCA
a6Q/195-1
Batch
SIM
370/ 1682
ASP
GIMP
ASP Bkup Night VM Night Batch
GIMP Bkup C.C. Bkup
C.C. Bkup
01 November (PHASE IV)
GIMDEV
CAMDEV
SANCA
36Q119 379L158 ._ 370/1681
GIMP
GUI Batch CRS
SIM
MVS
Local
Main
SIM Bkup
3,Q682_ 370 1683
MVS
MVT Global
Main Main
Night VM VM Bkup ' SIM Bkup
Global Bkup C.C. Bkup
CRS Bkup Global Bkup
GIMP Bkup
Approved For Release 2000/06/01 : CIA-RD[80-01003A000100120001-1
370Z158 370/1681
GIaNERAL CENTER
Approved For Release 2OI`OZ INW-.: CFP IR@E#M(F-OW$ 3ff0Q?p00120001-1
TIIASE
I
PHASE
II
GIMID/CAMD/2250/SANCA/SHOEBOX
CRS
1581 NIGHT i
BATCH/S
105 ASP/GIM
1~I
BKUP
ASP GIMS SI
BATCH BKUP
PHASE
III
GETS/GIM BATCI1/SIM
TTAIN
ATCH
1682 ASP/GIM' B
SIM/BAT H BKUP ASP/GIMS BK P GLOBAL/GIMS/SIM BKUP
:1681
(1.684)
MVS PROD/TEST
VM BKUP
,?l INNS GLOBAL/MAIN
q
PHASE
IV
Approved For Release 2000/06/01 : C1A-RD,P80-01003A000100120001-1
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
3350 Disk Congifurations for FY77
MVS Spool Pack Configuration (March 1977)
1681
1682
16$3
1581
STRING SWITCH
1681
1682
1683
1-581
A2F
C2F
C2F*
VM Mini.. Disk Configuration (July 1977)
MVS VSAM Configuration (October 1977)
1681
1682
168
Equivalent of
24 3330 Modls
Equivalent of
24 3330 Modis
Equivalent of
24 3330 Modls
*Used for VM until VM string is installed in July 1977
**Used for VSAM Data Sets until VSAM string is installed in October 77
Approved For Release 2000/06/01 : CIA-RDP80-0100U;;01 00120001-1
180
-0
120
0
J
80
Jan
76
VM Appr&63 M Release 2000/06/0 . 00pgq(7120004-1
I ~ E
I
Apr Jul Oct Jan
76 76 76 77
Apr
77
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
Jul
77
Oct
77
Jan
78
GIMS 4J9 Fl elease 2000/06/0] : CIA-RDP80-01003A0p 1 120001-t
Jan Apr Jul Oct Jan Apr Jul Oct Jan
76 76 76 76 77 77 77 77 78
Approved For Release 2000/06/01 : CIA-RDP80.01003AO00100120001-1
O
Jan Apr Jul Oct Jan
77 77 77 77 78
Approved For Release 2000/06/01 : CIA-RDP80-01003A000100120001-1
GENERAL CE N 7 FAQ BA T C P or { ease
pprov e ag E C 7 I A;/06/0 - 80-01 OO3A0gglp9120001-
Peak Days
pvera9,e pays