REPORT ON AGENCY PROCUREMENT MANAGEMENT
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80B01676R001600250026-2
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
4
Document Creation Date:
December 14, 2016
Document Release Date:
January 23, 2003
Sequence Number:
26
Case Number:
Publication Date:
October 4, 1966
Content Type:
MF
File:
Attachment | Size |
---|---|
![]() | 165.6 KB |
Body:
Approved For Release 2003/02/27 : CIA-RDP80B01676R001600250026 --
M RA11XJM FOR: Executive Director-Comptroller
CT : Report on Agency Procurement Management
. Forwarded herewith is the report prepared by the consultant
It provides
a highly perceptive and useful view of the Agency's procurement ac-
tivities and makes a number of very cogent recommendations for the
improvement of our activities in this field.
2. Many of the recommendations are stated in terms of general
principle. They do not detail specific steps to be taken, how those
steps should be phased., nor the adjustments required of the components
affected. We feel that there is advantage in this, in that consider-
able latitude is available for accommodation to unique problems that
might arise in the course of implementation. Specific details of
implementation were not feasible in a report such as this; nor were
they contemplated. In reviewing the report we have found it useful
to keep its findings and recommendations separated. We believe that
even if the recommendations are not accepted the findings still indi-
cate clearly the need for strong corrective action.
3. The report treats procurement in its broadest sense, includ-
ing purchasing, management of stock inventories, logistics support,
R&D contracting and management, and related production. The report
concludes that there is no central authority below the executive level
over these activities, and recommends that a Special Assistant for
Procurement, under the Deputy Director for Support, be appointed to
function at the apex of the procurement pyramid,, to serve as Agency
policy and coordinating officer on all procurement matters. The
actual management of the major procurement activities would be divided
between two directorates management of the normal supply and logis-
tics procurement activities would be under the Office of Logistics
in the Support Services; R&D procurement and related production (and
the special procurement of OSA) would be under a new R&D Procurement
Office in the Directorate of Science and Technology. To make these
two separate operations fully effective, each would require the
support of an automated management information system. The develop-
ment of these management information systems--the consultants see
them as sub-systems of one over-all system--is viewed as an integral
factor in effective implementation of the recommendations. There
are anumberr of other recommendations that are either part of the
Approved For Release 2003/.DZ20 :FCIA RDP80B01676R00160048b
Approved For Release 2003/02/27 : CIA-RDP80BO1676R001600250026-2
over-all organizational concept or that are intended to strengthen
current procedures. These include the consolidation of an audit
functions under the Audit Staff of the Office of the Inspector General
and establishment of a formal revolving fund for financial management
of the Agency's procurement pool.
4. We strongly commend the report for your favorable considers-
tion and state our endorsement of the main thrust of its findings.
In doing so, however, we wish to note certain factors that should be
weighed in any decisions to accept and implement the recommendations.
We have also proposed assignments of responsibility for i plements.-
tion if the major recommendations are accepted. We have also suggested
in paragraph la.d., below, the employment of outside assistance in the
implementation of some of the recommendations. Our comments on the
major recommendations, as summarized in Chapter VI of the report,
follow:
25X1
Approved For Release 2003/02/a CC3AiR1P80B01676R001600250026-2
25X1 Approved For Release 2003/02/27 : CIA-RDP80BO1676R001600250026-2
Next 4 Page(s) In Document Exempt
Approved For Release 2003/02/27 : CIA-RDP80BO1676R001600250026-2
Approved For Release 2003/02/27 : CIA-RDP80BO1676R001600250026-2
Their contribution to consideration of those problems has been con-
structive. Their broad basic conclusions about the Agency's organi-
zation for procurement, especially in. the field of FAD.. present a
course of action for resolving a problem that will grow in importance
an the Agency finds itself drawn more deeply into c x ,lex F programs.
J. S. Earm n
Inspector General