1. EAST GERMAN ATOMIC POWER PLANT AT NEUGLOBSOW 2. SOVIET SUPPORT OF THE EAST GERMAN ATOMIC POWER PLANT PROGRAM

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP80T00246A046000140001-5
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
5
Document Creation Date: 
December 22, 2016
Document Release Date: 
June 25, 2010
Sequence Number: 
1
Case Number: 
Publication Date: 
December 15, 1958
Content Type: 
REPORT
File: 
AttachmentSize
PDF icon CIA-RDP80T00246A046000140001-5.pdf334.03 KB
Body: 
Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246A04E CENTRAL IMTEEUGENCE AGENCY REPORT INFORMATION REPORT cD Ha COUNTRY A wt a?aw" SUBJECT if GOMM Ats hum P.t edi PLACE ACQUIRED DATE OF INFO. Ao . t..Q** Ueda nmv ~Qr 2 TNif Omuta "MUM 1NDORaIApON ~IfiGANOYW[ NATIOUL an&= It VNM UNIM "M N1sITS, q 611! NO N TNNI p IM NUN M PNOIININNA 25X1 1 DATE DISTR. 15 December 1958 NO. OF PAGES 2 NO. OF ENCLS. SUPPLEMENT TO REPORT NO. D; TRW IS t AYJX= 4 1, The pk.:at 1 s officio-1 designation. is Ateakrai twexix T T;euglobriow. "X" atends for Constr9. .ion Ste 1- pamsea Or a seav poorer p? ant. tr action stage of the at .c The r"v"nor 1fpe 'ifts designated ""0 this :? e a Soviet decignation0 The following temperatures were repoy?ted regardi;.sg the superheated water tied at the reactor's steam, generators'.. heed fraction temperature 269.5? Centigrade tai.1 fraction temperature 2r>?~ > 5? Centigrade Supplier. firma to 'the atomic parer` plant are the follo4ng: .'V Beir oreigo' VF.B Stahlbau 11i"k r SwAft -V Tse3 ? rer rr! ~b Rostock V& Rohr]eitungs- t nd Apparatebau lachers2.aben VEE ItWA, !! ~ me-g men VEB. Was serauftoarmit.:ng ;due+etberg VE? Rohr-leitungsbatrieb Bit erfeld VEB ITB (Ii - 6an~ $ bn g .VEB Lueftung Neterbkeu Vii Berle n Wastes material will be clumped in special containers at the so-called burial grounds. Waste materials include radioactive ate water, radioactive chemicals and r adioac Mina g ;w; Vara a a) of I& C ijaI --i: vers, as weir.. as contaminated mac line parts, tools, etc , Excavated earth in MAY 1958sordera , were 25X1 Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 . resulting from levelling work and railroad construction activities vas dumped into Wulvits Lake located east of the plant, filling it up 25 to 30 percent. The railroad line from Rheinsberg to the- plant was completed and put into service in late.Aprril 1958. Road construction betveen Greases and 24ns was progressing. Concreting work on this road was completed as far as the bridge crossing the Polsaw Canal near. Mans. Stasensr street leading from this point to the atomic plant was being provided with a one-lane concrete surface in late April 1958.? 3. Ant 60 mom 1 red at the doo W'WUM site, including. 20 from. Entvurfabuero fuer Industriebau (deriigni ng' office for industrial building), and 40 from Bne gie-Projektlonen Berlin (EP). The Leningrad GUTA designing office cooperated in the p3aleminge Sr. Franke of ITB (Ingenieur>Tiefbau-Brandenburg) was supervisor of the building activities during the time under observation. At a meeting with the manager of Energie- Pro 1ektierung 8s:?linsit was learlyd that the first construction stage would be completed in late 1961. In order to attain this-goal, the members of the were were obliged to do regular overtime work. It was iermore announced that the plant is to serve large-scale experimental work rather than serve econae.o purposes. On the. grounds of the experience gained future atomic power plants will be built. On the other hand information gained from employees and management indicated that the* deadline for completion of the.plant has been postponed from 1960 to 1964 in view of the difficulties arising. After his return from l4oecow, along with the delegates Plaahowaky, Sohibiilla and Breitenwincher, of VE8 Energie-Projektierung Berlin, Schneider* announced that ten more power reactors are to be built in the GDR W 1970. Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 sfr.ni FT 25X1 . 25X1 VEB Atom kraaf tweek I 95 (verdrtderhr H4 stab aus Gin AL40 51) hfeurupp nRhetnsbet a - . Wb.S ertQiten9eti Mo s +ab 1:50 000 I I i Hel mifz -See Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5 Legend: 1 Reactor 2 Electric power plant 3 Engine house 4 Laundry 5 Administration 6 Pumping station 7 Water inlet 8 'dater processing plant 9 Water discharge 10 Smokestack 11 Shaft 12 Cooling water pipes - B 2-meter surface gradient Cooling mater is taken from Nehmitsseea > Waste water is discharged into Stechlinseeer-^ the water returning to Nehmitzsee , along a canal connecting both lakes,, Since the volume of water of Stechl.inaee, = .is Inadequate, it is intended to provide i"resh watea~v f'yrom Muer i tzeee, Koelpinsee and Plauersei = to -Stechlinsee F^' at a. rate of 0,6 cubic meters/ sec. Since all these lades. are lacking of water in firms of drought, the only solution would be providing water from the Peeve River via Maichinersee [ j by pumping it o -er the watershed. Sanitized Copy Approved for Release 2010/06/25: CIA-RDP80T00246AO46000140001-5