INFORMAL MONTHLY PROGRESS REPORT NO. 8 FOR THE PERIOD 7 AUGUST 1955 TO 4 SEPTEMBER
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP81B00878R000200120019-2
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
5
Document Creation Date:
December 9, 2016
Document Release Date:
June 16, 1999
Sequence Number:
19
Case Number:
Publication Date:
September 4, 1955
Content Type:
PERRPT
File:
Attachment | Size |
---|---|
![]() | 232.63 KB |
Body:
25X1A5a1
Approved For Repas QW78R000
Informal Monthly Progress Report No. 8
for the period
7 August 1955 to 4 September 1955
25X1A5a1
System No. I
25X1A5a1
Copy 1 of 7 copies
This document contains information affecting the
National Defense of the United States within the
meaning of the Espionage Laws, Title 18,, . U. S. C. ,
Sections 793 and 794. Its transmission or the
revelation of its contents in any manner to an
unauthorized person is prohibited by law.
Approved For Release ZQ
800878 R000200120019-2
Approved For Rase 200 'I B078R000200120019-2
40 ANTENNAS
Sample reflectors have been received .for S and X fre-
quency bands. The S-band dish has been tested and.approved.
Delivery is to begin during the week of September 5. The
original delivery schedule was to have begun during mid-
August. Completed antennas can be made ready for shipment
within a day or two after delivery from the vendor.
2.0 INFORMATION AMPLIFIER
Six amplifiers are ready for delivery upon receipt of
the redesigned cover and can assembly on September 6.
Two hundred printed boards for the amplifier are out
on bid to. several vendors.
Environmental tests (to be discussed separately) dic-
tated some rework on the power supply can. This. amounts to
soldering hermetically- sealed connectors. to a thin steel plate
and securing the plate to the aluminum can with a combination.
gasket-adhesive seal. These changes were also incorporated
into the amplifier can. A visual inspection did not provide a
reliable check on the sealing of the connectors to the aluminum
can,
Two of the reworked units will be ready :for delivery
during the week of September 5.
3..0 INFORMATION RECORDER
One recorder, including the electronics, is essentially
complete and is undergoing tests. The preliminary tests have
given added confidence in the friction-typ.e capstan drive. It
may be necessary to use ball-bearings throughout the capstan
drive assembly. Design details regarding