INFORMAL MONTHLY PROGRESS REPORT NO. 8 FOR THE PERIOD 7 AUGUST 1955 TO 4 SEPTEMBER

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP81B00878R000200120019-2
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
5
Document Creation Date: 
December 9, 2016
Document Release Date: 
June 16, 1999
Sequence Number: 
19
Case Number: 
Publication Date: 
September 4, 1955
Content Type: 
PERRPT
File: 
AttachmentSize
PDF icon CIA-RDP81B00878R000200120019-2.pdf232.63 KB
Body: 
25X1A5a1 Approved For Repas QW78R000 Informal Monthly Progress Report No. 8 for the period 7 August 1955 to 4 September 1955 25X1A5a1 System No. I 25X1A5a1 Copy 1 of 7 copies This document contains information affecting the National Defense of the United States within the meaning of the Espionage Laws, Title 18,, . U. S. C. , Sections 793 and 794. Its transmission or the revelation of its contents in any manner to an unauthorized person is prohibited by law. Approved For Release ZQ 800878 R000200120019-2 Approved For Rase 200 'I B078R000200120019-2 40 ANTENNAS Sample reflectors have been received .for S and X fre- quency bands. The S-band dish has been tested and.approved. Delivery is to begin during the week of September 5. The original delivery schedule was to have begun during mid- August. Completed antennas can be made ready for shipment within a day or two after delivery from the vendor. 2.0 INFORMATION AMPLIFIER Six amplifiers are ready for delivery upon receipt of the redesigned cover and can assembly on September 6. Two hundred printed boards for the amplifier are out on bid to. several vendors. Environmental tests (to be discussed separately) dic- tated some rework on the power supply can. This. amounts to soldering hermetically- sealed connectors. to a thin steel plate and securing the plate to the aluminum can with a combination. gasket-adhesive seal. These changes were also incorporated into the amplifier can. A visual inspection did not provide a reliable check on the sealing of the connectors to the aluminum can, Two of the reworked units will be ready :for delivery during the week of September 5. 3..0 INFORMATION RECORDER One recorder, including the electronics, is essentially complete and is undergoing tests. The preliminary tests have given added confidence in the friction-typ.e capstan drive. It may be necessary to use ball-bearings throughout the capstan drive assembly. Design details regarding