SLOW PROGRESS IN CONSTRUCTION OF HYDRO-ELECTRIC POWER PLANTS
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP82-00457R007500470003-2
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
2
Document Creation Date:
December 27, 2016
Document Release Date:
November 27, 2013
Sequence Number:
3
Case Number:
Publication Date:
May 17, 1951
Content Type:
REPORT
File:
Attachment | Size |
---|---|
CIA-RDP82-00457R007500470003-2.pdf | 162.31 KB |
Body:
?',1 ? , f'..1 71 -.7
Declassified in Part - Sanitized Copy Approved for Release 2013/11/27 : CIA-RDP82-00457R007500470003-2
(.:EN likAL ELLIGENCE AGENC-I REPORT
ilftt0014
Ih
WIRT'
Yugoslavia. .
11 '41WoEJrON RE PC
C POZEN EAE.
IBJECT Slow Progress in Construction of Hydro-
Taectric Power Plants
t"LiA,CF.
ACQUIRED
DATE OF
INFO.
DATE DISTR. 3.7 May 51
NO. OF PAGES. - 2
NO, OF ENCLS.
(LISTED BELOW)
SUPPLEMENT TO
REPORT NO,
50X1
50X1-HUM
PSES, OCSI;VECT COUT.T11,751E11P0aNAT/OC (IPPECITOSTPIP.ISATIOHOLOIFIZOSS
,P.4.'" TEM SPITZD
8TO7S1 toraini TIPAIUMS OP TOE SOT,TOCASS ACT SO
'4,', C;;._DS 1111?3 TP? APIPTOST,. TCOMOVISStO'S U TSB CEITSLOTION
tn, rrr? CCiTTEOJS tri SET CAPSICS TO CM OITACTOOTtiZED PERSCP PSO.
3y E? LAM. .1TPPSODUCTt03 07 TOM Fong tO PSOPISCITO,,
. AW73410.
THIS IS UNEVALUATED INFORMATION
50X1-HUM
?1. Progress in the const-ructicn of new hvdrneeleetric power stations is very
slow
a. Jablanica (approximately 70 kilometers southwest of Sarajevo): ,
Fressure pipe tunnels and underground powerhouse have just been come
pleted. Work is only starting OD the 80-meter long dam. There has
been no equipment installed in the powerhouse. The power station is
supposed to start operations by the end of 1951, but under present
conditions, it will probably be 1953 before operations begin..
b. Vuzenica on the Drava River (approximately 85 kilometers east of
Dravograd): So far only the foundations of the powerhouse and half
the dam across the river have been completed.
c. Moste on the Sava River (58 kilemetere northwest of Ljubljana): All
construction work has been completed but no equipment has been installed.
d. Vlasina on the Vrla.River (2 kilometers?south of Surdulica): This
plant is operating at only 20 percent capacity.
Vinodol (approximately 25 kilometers east-northeast of Susak): Pressure
pipes are being installed. Of the three reservoirs, only one at Lake_
Bajer is finished, and a dam is under construction across a second one. -
No equipment has been.installed in the powerhouse. -
1.
Mavrovo, 1acedonia (three plants situated near Drebar): 'Xorkeis
proceeding so slowly that it. will be several years before these plants
will be finished.
20 Most of the equipment for these power stations is supplied by Litostroj
and Rade Konoar; the former- builds the turbines and the latter the
generators. .Litostroj is now beginning work on the construction of the
following turbines3 .
STATE
rnm
a. Three 2,200 kilowatt turbines for Ozalj IT
b. Two 2,500 kilowatt turbines for Zavrelje
c. One 10000 kilowatt turbine for Otocac.
CLASSIFICATION 5iiatET76-0DER0L - U.S. 0
pmvy NSRD IDISTRIBUTION!
AIR
rrei
Flicilo"-
e.1.;
? 4.':?
50X1 -HUM
Da% rlird 01,-- 7 ?
No Change in Cass.
Clan. Cho.1,7gtd. To; TS
Auth.: 10-2
Date; 77 75(
50X1
neclassified in Part - Sanitized Copy Approved for Release 2013/11/27: CIA-RDP82-00457R007500470003-2
Declassified in Part - Sanitized Copy Approved for Release 2013/11/27: CIA-RDP82-00457R007500470003-2
lama at% ,ggo ;Qat Li Et LA a 3
'COMOL ICT? ;3,, OFFICIALS ONLY
CENTI, 7.; INTELLIGENCE ACIENCY.
- 2 -
tf.on of the Ea:km-Ting turbinos is planned:
Four turbines devolophig 50p 000 kilae,ratt,-s for Mavrovo
b. Six 3r, 500 IcilouaLt tuxbirles ro7 Vlazirm
co SS!..x turbl_nes dovrloping 33000 kilowatts for Jablanice
do Four 1?1000 1-.:,:,w;z1L turbines fc,r Zvorniko
coltzg .? 3
inrailTRAT. - TT c: 41PPTP-A7Q nurIr
Declassified in Part - Sanitized Copy Approved for Release 2013/11/27: CIA-RDP82-00457R007500470003-2
50X1