WERNEUCHEN AIRFIELD

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP82-00457R009000080010-0
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
4
Document Creation Date: 
December 22, 2016
Document Release Date: 
September 14, 2012
Sequence Number: 
10
Case Number: 
Publication Date: 
September 27, 1951
Content Type: 
REPORT
File: 
AttachmentSize
PDF icon CIA-RDP82-00457R009000080010-0.pdf347.23 KB
Body: 
'r .. .. .. ..., .. ~~. tinx~-HUM EGIt IT?C INFORDdATION :x~wnny (Soviet one REPORT ,_erneuchen Airfield i1r i.)STAFi D -- ,. ENCLOSURES (No. & TYPE LLQATF PRFPARFn 27 September 1951 Me field- Truck soldie?s with their baggage left'a tr in and then a r orce V the airfield, e car and trucks 50X1-HUM th a er oaded with oxygen bot les. were observe a the field. 50X1-HUM 'between 7 and 12 f ugust, no aircraft were seen at the field. The first hangar seen from the west was closed. The two hangars farthest to the east were open and 50X1-HUM han'ars were -?uarrled. construction had progressed a a norria rate. Q ) About noon a grroximatel 10 ^ i f a t of .'7er e roaa to ee e . (47 7 wua-u uaruerea in zne ->>arracits buildings. (2) Trucks were observed at the field. . On 31 July 1951, seven twin-engine aircraft with double rud0er assemblies were towed out of the hangar No 3 at "erneuchen airfield. (1) The aircraft engines were then run fo? about 30 minutes after which the planes were brought back into the hangars Hannars T ;o 1 and 2 were closed ands guardeda Hangar T,o 4 .was closed but not guarded and hangars 1o 5 and 6 were er=pty. In the afternoon, 1 officer and 65 air force soldiors with their baage arrived by train 50X1-HUM nn c=^"+- 1-- 4-lnr. ....,..l%.L _Y 1 n._ 4. T"ost of the laborers did grading work on the eastern section of the landing field. Three tractors were used there. The drainage ditch was provided w-+.th pipes as far as about 150 neters fron the runway, The rail way bed of the spur track was comrleted except .or the strip from Park Str rise to the water ,-,corks, where the top layer of crushed stones were not f~~ lled in. cork had to be disconti 'hez the r.achines were.in a bad condition. the target date for the! completion ha TO }e postponed ~0 50X1-HUM .. October 1;51. (5) Soviet inspectors -illegedly found that the concrete cover in a .strip of the runway did not have the prescribed thicimess. erefore a strip of about 20 meters of the runway was toA and rebuilt. An advance detail of CLASSIFICATION XRET-CO MOLJLTS .,F?-'I0S'A_,S 01 T LY Declassified in Part - Sanitized Copy Approved for Release 2012/09/14: CIA-RDP82-00457R009000080010-0 Declassified in Part - Sanitized Copy Approved for Release 2012/09/14: CIA-RDP82-00457R009000080010-0 SLC.fET-COI TROL/bS OF;" iI'll TALC c,Fliy laborers of the Dauunion Firm had allegedly left for Strausberg airfi??ld where a new concrete runway was to be built. (6) On 23 and 24 August, the hangars at the field were 3u.arded and no aircraft were observed. Bread deliveries were reduced to a daily quantity of 550 to 6.).: keg about IOU men ha d an that they were to be replaced by old troops from Jueterboj Only air force officers, E:'e and trucks the latter50X1-HUM assigned to pick up the bread r:ticns, entered and left the f:ie zd, 6a t:bcat 201 men were excavat`.ng east of the rung ay. power shovel was utilized there. i:hile passing along the runway source obsnr=-od that about 1 400 r:neters of the western section was concreted,. The old spur trace ,";as removed. A strip of about 350 meters between the eastern and western sections of the runvay was still to be concreted. The drainage ditch :h bean at LIP +i v Jtern end of the runway and oxbonded toward the west .,3as excavated to a length of 1 000 meters. Furrows hicis run on both sides of the runway lead the :?:at~r from tFie slo{):ng runway to the drainaTe ditches. Three ad I.itional cranes .were set u at the loading site on the northern edge of the field., so that the dui pcars were loaded by five cranes. About 30 laborers were excavating for the spur track on the southern edgy of the fie1c"o Ties vi re laid on a section of the Line. ` .. Between 6 and 10 August, a total of 3.600 laborers were 50X1-HUM working at .the field. .,In additional porter shovel. with a capaci? of 1-cubic i Teter was used. An area of 141,000 square meters was concreted. (7). The drainage pipes, north and south of the runway and in the restricted areas, were laid in concrete beds 20 cm thick. All the pipes were heavily reinforced. On 3 i:,ugust, eight twin-engine aircraft were towed out of han:Jar No 3, west of the flight control building, and brought to ;rangar 17~o 1. They were arranged in such a manner to take 50X1-HUM up as little space as possible. .e pipes _la to be. cf nsidersbly stronger because aircraft were to rr .v - at the f eld which hind n.:.t ye C .Pen by Gerrlans and .-hich had a -.vzng span of 120 :meters. 50X1-HUM r3' ^etween 13 ant' 13 August, 3,300 1-,borers were employed ^t the f g el.ds. Five .new steam engines 3 new Diesel engines,two 1-cubic rmmeter over shovels and 2- -cubic meter. rlixers were additionally used. The narrow-gaurye field ra11V~Jay trackage vas extended to 21 kn,. An area of 1648 r00 square meters ids concreted. (8) On 14, August , Colonel Zukolov or Zukolorov from order inspected the field, e C01=01 cads _n enar e,izi u -n 50X1-HUM airfield construction projects in the soviet Gone of Gernlany. Sl-'*a4,.11 SROL/UrS c