CONSTRUCTION OF A TUNNEL IN PRAHA- LETNA MADE BY THE CZECHOSLOVAK CONSTRUCTION WORKS, NATIONAL CORP. PLANT BARABA.
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP83-00415R009100130013-2
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
2
Document Creation Date:
December 22, 2016
Document Release Date:
July 17, 2012
Sequence Number:
13
Case Number:
Publication Date:
June 28, 1951
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 113.07 KB |
Body:
Declassified in Part -Sanitized Copy Approved for Release 2012/07/17 :CIA-RDP83-004158009100130013-2
E, .,;.;,Q+_i+?r.'h'~ori of a tunnel in :;
Date of event: ch 1951.
~~~~G'C~S~I a~
~~~i~lC~AtJ ,
a ~ ~-
Tonal corp. plant &4RABA.
- The construction of the tunnel in Praha VII"- Leiria is
carried out by the Czechoslovak Construction Works, nat.corpe,
plant BAFi.AI3A. offices of -the firm: PPraha VII. Letohradska l~.Ja..
Other offices etc. are directly at the place of the construction,
opposite the Technical Museum. At present this buil~.i.ng houses
the Directorate of the Stavoproject.
Situation of the tunnel:
The tonne begins 'gat the Captain JAROS Embanlsinent, just where
the new bridge ends under which there is a viaduct for the embankment
traffic. The tunnel ends at the corner of two street (Nod stolou and
Dobrovskeho u~ne) behind the main building of the ~q'i n-i stry of the
Interior in Praha III. 50X1-HUM
Nor cars of the Prague ~~ can pass through it.
By-tunnel:- Parallelly with the main tunnel aside-tunnel is being
construed (narrower and lower than the main- one, with a speoial
airing system}o This side-tunnel is connected with the main one
by three side corridorso
This tunnel is supposed to be used
as an air-raid shelter, 50X1-H U M
V,rorking hours: three shifts, 8 hours each. ~Tork begins at 6.a.m.
T~ta~es: Skilled workers get Czocrs. 28,50 per hour, unskilled workers
are paid Cz,:crs~. 12, and 16, per hours T~Vork is done according to
a fi.~:ed schedule, and biased one tivi.th anotYiero Plant BAR,ABA employed
many clerks (who had been released recently from the b~?inistries and
civil. service) as unsYa.lled workmen.
Height of the tunnel:
~Pidth of the tunnel:
of a normal. street where two ~ars can pass along each
other. 50X1-H U M
Declassified in Part -Sanitized Copy Approved for Release 2012/07/17 :CIA-RDP83-004158009100130013-2
Declassified in Part -Sanitized Copy Approved for Release 2012/07/17 :CIA-RDP83-004158009100130013-2
Chief of the Cadre dept:
TR1?i~ f~''
_1 = Ministry of Interior
2 = Dobrovskeho Mice (Street)
3 = SoK. Slavia (football play-ground)
~. Nad stolov. (street)
5 . Kostelni uliee (street)
6 ~ Stefanikuv most (Stefanik~s bridge)
7 = ~'rovisorni dreveny most (temporary wooden bridge)
1:13.500.
- -.
50X1-H U~
In o Tt~'TT;~' (gnu),,
50X1-HUM
CHABERA (fnu),
see sketcho
50X1-HUM