MINUTES OF 22 SEPTEMBER 1983 WORKING GROUP MEETING
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP85-00142R000100030026-2
Release Decision:
RIPPUB
Original Classification:
C
Document Page Count:
2
Document Creation Date:
December 22, 2016
Document Release Date:
May 18, 2010
Sequence Number:
26
Case Number:
Publication Date:
September 29, 1983
Content Type:
MEMO
File:
Attachment | Size |
---|---|
![]() | 81.12 KB |
Body:
('!'tr,lrtr,-
Sanitized Copy Approved for Release 2010/05/18: CIA-RDP85-00142R000100030026-2
29 September 1983
MTIORANDUM FOR: Requirements and Technology
Acquisition Working Group
Chairman
Minutes of 22 September 1983 Working Group Meeting
1. The Requirements and Technology Acquisition Working Group met on
Monitoring the meeting was
2. I convened the meetin asking for corrections to the
minutes of the 8 September meeting. noted that his component is
LMS, as opposed to IRS. No other corrections were noted.
3. I presented a briefing on the OC requirements cycle.
He explained that OC is trying to formalize the requirements process,
including the call for communications requirements from Agency components,
but there really are two requirements processes. The first, which OC is
doing fairly well, addresses future levels of existing services. The
second, which OC is.,doing less well, addresses the need for new and
different services. In the discussion prompted by remarks, it was
clear that any requirements methodology has to deal effectively with both
types of requirements.
4. handed out some material extracted from Ma0nagi~n the
Systems eve omen Process and recommended the group adopt this ok as the
basis for its requirements methodology. The group agreed after some
discussion of how much should be included in the requirements process. The
group's focus will be a fairly narrow one, leaving the larger issues to the
Information Services Planning Working Group. (Copies of the book were
ordered and will be distributed as soon as they arrive.)
S. Discussion of the scope of the group's work led to a review of the
proposed working group charter. The group wanted more emphasis on the
technology acquisition aspects of our work and several other chances. A
revised draft will be circulated prior to our next meeting.
25X1
25X1
25X1
25X1
25X1
25X1
25X1
25X1
25X1
25X1
Sanitized Copy Approved for Release 2010/05/18: CIA-RDP85-00142R000100030026-2
Sanitized Copy Approved for Release 2010/05/18: CIA-RDP85-00142R000100030026-2
6. The next meeting of the working group is scheduled for Thursday, 6'
October 1983, at 0930 in'Room 4C32. (Note the change of time to accommodate
the ISB meeting at 1100). The agenda for that meeting, which is scheduled
for 60 minutes, is as follows:
a. Approval of minutes of the previous meeting.
b. Miscellaneous old business.
c. A final review of the working group charter.
d. Discussion of deliverables for the ISB.
e. Discussion of a requirements methodology.
0/Compt/IHG~ (28 Sep 83)
Sanitized Copy Approved for Release 2010/05/18: CIA-RDP85-00142R000100030026-2