STATUS OF SAFE SITE CONSTRUCTION COSTS
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP86-01019R000200050027-0
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
5
Document Creation Date:
December 16, 2016
Document Release Date:
July 28, 2005
Sequence Number:
27
Case Number:
Publication Date:
March 18, 1981
Content Type:
MF
File:
Attachment | Size |
---|---|
![]() | 206.03 KB |
Body:
Approved pr Release 2005/08/03 : CIA-RDP86-0 19R000200050027-0
19 M1k 1981
MEMORANDUM FOR: Chief, Consolidated SAFE Project Office,
ODP
FROM:
Chief, Real Estate and Construction
Division, OL
SUBJECT: Statu6s of SAFE Site Construction Costs
1. lie ardin telephone conversations among Messrs.
I and the undersigned, the
-o owing is a review of how the General Services Admin-
istration (GSA) has used the funds provided for the site
preparation work for Project SAFE.
bidding a.dnilriistration
$ 56,900
b. GSA travel in connection with
paragraph a. above $ 305
c. GSA printing costs for construction
plans, specifications, and bidding
documents - $ 4,666
d. AYB cost for preparing plans
and specifications $ 128,262
e. Construction Contract Award
price
a. GSA design management and contract
980,000
36,701
c.o.1 Requirement for security
mesh above partitions $ 4,000
c.o.2 Route electrical riser
from "D" Vault in stairwell instead
of in existing electrical riser
because of congestion in the
present closets $ 3,297
f, GSA construction supervision
g. Change Orders
OL 1 1018
r, Approved For Release 2005/08/03 : CIA-RDP86-01019R000200050027-0
Approvedgr Release 2005/08/03 : CIA-RDP86-019R000200050027-0
SUBJECT: Status of SAFE Construction Costs
c.o.3 Same as c.o. 2 above
but for service from Vaults "A"
and "C" and for some electrical
changes in "A" Vault $ 9,054
c.o,4 Additional demolition not
shown on the drawings including
office walls in Battery Room area,
sinks, fire hose cabinet, electrical
closet and panels $ 12,494
c.o.5 Change in acid drain in
Battery Room $ 2,600
c.o.6 Change in chilled water
line routing due to conflict with
"C" Vault construction $ 14,116
c.0.7 Reduce quantity of acid
drain including demolition and
repairs - Credit $ (1,694)
c.o.8 Change in electrical.
riser from "B" Vault as was done
in other risers $ 3,852
c.o.9 The electrical in-floor
ducts were found to be more extensive
than shown on the drawings causing
additional cost for removal and
repair $ 2,855
c.o.10 Alter elevations of
chilled water lines at 3 crossings
to pass one line beneath the other $ 4,059
c.o. 11 Change air conditioning
supply and return ducts at the
Escalator Room $ 1,046
f ? Approved For Release 2005/08/03 : CIA-RDP86-01019R000200050027-0
Approved-Epr Release 2005/08/03 : CIA-RDP86-0I9R000200050027-0
SUBJECT: Status of SAFE Construction Costs
h.
Reserve funds to reimburse the
McLean
Field Office for the expenses in-
curred
for construction support such as
draining and filling chilled water system
during contractor connection work
3 900
$T2 i' f- ,-413-
2. In addition to the expenditures above, there are
the following additional changes pending. These changes
are not yet numbered and the prices are not firm.
a. Revision to accoustical ceiling
for a credit $ (2,000)
b. Raise plaster height from exist-
ing point to new coiling height, approx.
6 inches in majority of Phase I area $ 5, 000
c. Patch plaster at columns in Battery
Room $ 2,000
d. Increase depth of acid pit $ S,000
e. Raise existing electrical conduit
passing through contract area $ 1,650
f. Claim by contractor to accomplish
repairs to underfloor duct $ 10,000
g. Changes to explosion proofing the
Battery Room $ 10'C00
h. Bring UPS into UPS Room
$ 5,000
i. Install bus duct from "C" Vault
to UPS including service for Phase II
$ 100,000
J. Lower ceiling in E corridor to
aeconmodate piping needs
$ 3 000
r 650
Approved For Release 2005/08/03 : CIA-RDP86-01019R000200050027-0
Approved,Lpr Release 2005/08/03 : CIA-RDP86-019R000200050027-0
SUBJECT: Status of SAFE Construction Costs
3. Summary
Funds transferred to GSA
FY77
101,200
1,02 ,000
FY80
7,000
5,500
516,600
(400,000).
FY81
I55`004
$1,419,300
Funds used or identified to be used
by GSA as of 27 February 1981
1,266,413
139j 650
$1 406 063
Contingency Remaining
4. The ongoing nature of construction work will be
that additional.changes will be needed and that the cost
of estimated changes may vary. As examples of this, the
following is forecast from GSA for your information*
a. The actual change order cost for the bus
duct work has been negotiated down from $100,000
to approximately $89,000.
b. The explosion proofing work for the Battery
Room has been reexamined and redesigned. The final
cost for this work is now expected to drop from
$10,000 down to the $2,000 - $3,000 range.
c. The need to increase the depth of the acid
drain pit now appears to be unnecessary and may not
become a change.
-4-
Approved For Release 2005/08/03 : CIA-RDP86-01019R000200050027-0
Approved,r Release 2005/08/03 : CIA-RDP86-019R000200050027-0
SUBJECT: Status of SAFE Construction Costs
d. An areaway shown on the drawings to be
existing does not in fact exist. To construct
the areaway is estimated to be in the $4000 -
$6,000 range.
e. A temporary wall may be required around
the air handler that is installed to serve Phase
II on a temporary basis to reduce the impact-of
Phase II construction on an operational Phase I
area,
S. I hope that this information will be helpful to
you in tracking the site preparation increment of Project
SAFE. If you desire, I can provide you with an updated
accounting on a quarterly basis for the remainder of the
site preparation work for Phase I and for Phase II. The
update would be in essentially the sane format as this
ne,noraaiadu -. Should you need further information, please
advise.
Distribution:
Orig - Adse
I - 0L/RECD/13EB Official
1 - OL/RECD/HEB Chrono
1 - OL, Reader
OL/RECD/1
_Sm.
(16 March 81)