LOGISTICS SERVICES DIVISION WEEKLY REPORT PERIOD ENDING 5 OCTOBER 1983
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP87-00352R000100100031-3
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
3
Document Creation Date:
December 22, 2016
Document Release Date:
August 6, 2009
Sequence Number:
31
Case Number:
Publication Date:
October 5, 1983
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 135.82 KB |
Body:
STAT
Approved For Release 2009/08/06: CIA-RDP87-00352R000100100031-3
LOGISTICS SERVICES DIVISION
WEEKLY REPORT
PERIOD ENDING 5 OCTOBER 1983
I. Progress Report on Tasks Assigned by the DCI/DDCI:
No items this reporting period.
II. Items/Events of Major Interest:
a. Installation of Carpet in DCI Suite: On 29 September
1983, 114 square yards of special color carpet tiles were in-
stalled in 7D5606 Headquarters Building, the secretarial area
of the DCI suite.
b. Com
pletion
of
Outstanding Requests: Car
pet wa
s in-
stalled in t
he PEP
Buil
ing, at the Motor Pool o
ffices,
and the
entrance to the Gym
at
the Headquarters Building on 30
September
and 1 October 1983. Additionally, all outstanding requests for
carpet installation and shampooing and for drapery service, which
were available for work, were completed under FY 1983 contracts.
c. Safe Inventor : As of 3 October 1983, the inventory of
safes in the metropo itan area is current. Moves, relocations,
and PTI's of safes will now be input into the computer on a
regular basis in order to maintain accurate figures. Any infor-
mation which is needed pertaining to safes can be obtained
easil querying the Safe System. To date there is a recor
STAT of safes, broken down as follows:
STAT
d. Transportation: Limousine service was provided for
EUR/LOG from through 30 September 1983.
e. Window Washing: A contractor will commence washing both
the outsides and insides of windows throughout the Headquarters
Building on 5 October 1983. Completion of this project is ex-
pected to take approximately one month. A Headquarters Notice with
detailed information is being distributed to all components.
f. Renovations at Head uarters Building: The sheetmetal
Shop is in the process o fabricating window grills, and critical
power has been installed in Room 2D0105 for the Office of Data
Processing.
A new door has been installed, masonry work has been com-
pleted and painting will be completed this week in Room 3B2612
for the Africa Division, DDO.
Carpentry work has been completed and the electrical
work has started in Room 1B27 for the Office of Communications.
Approved For Release 2009/08/06: CIA-RDP87-00352R000100100031-3
Approved For Release 2009/08/06: CIA-RDP87-00352R000100100031-3
With regard to the HSTS expansion in Room GD45, the
electricians have completed the relocation of the overhead lights
in this area, and the Sheetmetal Shop is fabricating a stand for
the air handler unit.
The Carpenter Shop started on 3 October
1983
to con-
struct a
for the
wall with two doors and two windows in
Office of Communications.
Room
1B2102
GSA has advised that work in Room;GC57, GC47, and GC47/
BC27 for the Office of Data Processing will be delayed because
of asbestos material covering pipes in the area. GSA will need
special suits, medical evaluation of electricians who were on the
job, and overtime to complete the jobs.
g. Move of Executive Registry to 6E2914, Headquarters
Buildin : Construction drawings were completed or minor work in
Room 7E12, and work will commence after completion of the move of
the Executive Registry to Room 6E2914.
h.l , Modifications (Phase IV): The Architec-
tural Design Staff (ADS), LSDOL, is currently reviewing existing
raised floor specifications and drawings to establish contract
documents and construction drawings needed to complete these
renovations.
i. I Building Renovations: Drawings for reno-
vations to Suite 200, were sent to the
Field Engineering Branch, Real Estate and Construction Division,
OL, for plumbing input.
j. Survey for SAFE Terminals: A survey has been conducted
for construction of 11 SAFE terminals, the preliminary design
has been approved for the area, and construction drawings are
underway for Room 4F24, Headquarters Building, for the Office of
East Asian Analysis, DDI.
k. Drawings: Drawings to convert existing area in Room
6E05, Headquarters Building, into a VTR for the Office of Global
Issues, DDI, were completed and were issued to the Space Mainte-
nance and Facilities Branch (SM&FB), LSD/OL, on 29 September 1983.
Working drawings for minor renovation in Room 2F20,
Headquarters Building, for the Office of Personnel were completed
and were submitted to SM$FB.
Drawings for the renovation of the courier's lounge in
Room GB1911, Headquarters Building are currently on hold awaiting
input from the Headquarters Engineering Branch, RECD/OL, re-
garding plumbing.
Approved For Release 2009/08/06: CIA-RDP87-00352R000100100031-3
Approved For Release 2009/08/06: CIA-RDP87-00352R000100100031-3
1. Design Proposals: Representatives of ADS and the East
Asia Division met to discuss the future configuration of Rooms
4G29-4G43. ADS is currently working on two design proposals.
A design proposal has been submitted to the International
Activities Division, DDO, for Room GG27, Headquarters Building.
III. Significant Events Anticipated During the Coming Week:
Base Stand for Air Handler: The Plumbing Shop is making
a base stand for the air an ler which is to be installed in
Room 3G13/19, Headquarters Building, for the Office of Global
Issues, DDI, starting 6 October 1983.
Acting Chief
Logistics Services Division