REPORT OF SIGNIFICANT LOGISTICS ACTIVITIES FOR PERIOD ENDING 13 DECEMBER 1984
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP87-00352R000200030022-0
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
3
Document Creation Date:
December 22, 2016
Document Release Date:
April 17, 2009
Sequence Number:
22
Case Number:
Publication Date:
December 13, 1984
Content Type:
MEMO
File:
Attachment | Size |
---|---|
![]() | 86.4 KB |
Body:
Approved For Release 2009/04/17: CIA-RDP87-00352R000200030022-0
13 December 1984
MEMORANDUM FOR: Deputy Director for Administration
FROM: Daniel C. King
Director of Logistics
SUBJECT: Report of Significant Logistics Activities for
Period Ending 13 December 1984
aA.;nictratinn nn 13 December 1984.
1. Progress Report on Tasks Assigned by the DCI/DDCI:
The tasking regarding proselyting of Agency employees is
well under way. A clause for insertion in our contracts and an
employment agreement for Agency employees have been prepared and
forwarded to the Executive Director via the Deputy Director for
2. Events of Major Interest That Have Occurred During
the Preceding Week:
b. Cafeteria Renovations: Renovations continued during
the weekend of 7 to 10 December 1984. Three 12-hour shifts
were worked by the general contractor and by subcontractors.
(1) North Cafeteria: No work was done in the North
Cafeteria this week. The final taping, patching, and
sanding operation for the new ceiling to accept the
basecoat for the paint is tentatively scheduled to start
on 21 December.
25X1
Approved For Release 2009/04/17: CIA-RDP87-00352R000200030022-0
Approved For Release 2009/04/17: CIA-RDP87-00352R000200030022-0
SUBJECT: Report of Significant Logistics Activities for
Period Ending 13 December 1984 25X1
(2) South Cafeteria: Demolition of the ceiling area
in the South Cafeteria is complete. The installation of
the new dry wall ceiling metal hanging support work is
complete. The hanging of the new dry wall ceiling has
been completed up to the loft area in the middle bay
area, and final sanding and patching operations were
started. Dry wall hanging operations are nearing
completion in the south bay area. Work is scheduled to
resume on 14 December.
c. Pedestrian Tunnel Repair: Eighty percent of the new
sidewalk was poured the week of 3 December. Forming for the
steps and sidewalk leading to the bus stop began on
6 December; however, due to low temperatures, the concrete
pouring for these areas will be delayed until the end of the
d. Seventh Floor Terrace and Penthouse Roof
Replacement: All hot asphalt work on the back side of the 7D
and 7E Corridors was completed the week of 26 November. Work
began on the south side of the 7E Corridor (up to the plywood
barrier) during the week of 26 November. Approximately half
of the hot asphalt work on the front side of the 7D and 7E
Corridors has been completed. All terrace roofing work on
the front side of the 7D Corridors will be done on weekends.
e. Agency Telephone Book: Now that the dylux proof has
been approved for printing, the Printing and Photography
publication. Although a lot of press
and bindery work remains to be completed, P&PD is hopeful
that the telephone book will be completed by the end of
Division (P&PD), OL, is preparing to go to press with this
2
S E C R E T