OL/NBPO WEEKLY REPORT - PERIOD ENDING 20 AUGUST 1986
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP89-00063R000200200016-7
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
3
Document Creation Date:
December 27, 2016
Document Release Date:
November 7, 2011
Sequence Number:
16
Case Number:
Content Type:
MISC
File:
Attachment | Size |
---|---|
![]() | 96.94 KB |
Body:
Declassified in Part - Sanitized Copy Approved for Release 2011/11/08: CIA-RDP89-00063R000200200016-7
OL/NBPO WEEKLY REPORT - PERIOD ENDING 20 AUGUST 1986
1. Progress Reports on Tasks Assigned by the DCI/DDCI:
None.
2. Items or Events of Major Interest That Have Occurred During the
Preceding Week:
a. The New Building Project Office (NBPO), OL, provided a tour of
the New Headquarters Building (NHB) for 15 Printing and Photography
Division (P&PD) personnel on Thursday, 14 August. P&PD has been providing
continuously good service to NBPO's many requests for design, printing, and
photographic service. The tour afforded an opportunity for personnel who
are always on the tail-end of requirements to see first-hand what the
requirements are all about. Informal feedback from P&PD reports that the
group was very appreciative of the tour and impressed by the construction
STAT progress in the New Headquarters Building.
STATE
STAT
STAT
b. The New Building Project Office (NBPO), OL, has been informed
by Printing and Photography Division (P&PD), OL, that NBPO's request for
updated aerial photography is scheduled for Tuesday, 19 August.
will provide the pilot and aircraft, and P&PD will handle the
photography.
Declassified in Part - Sanitized Copy Approved for Release 2011/11/08: CIA-RDP89-00063R000200200016-7
Declassified in Part - Sanitized Copy Approved for Release 2011/11/08: CIA-RDP89-00063R000200200016-7
LN6
STAT
e. The barrel skylight was installed at the new Rt. 123 Security
k o? Control Center on 18 August. A roof slab and the slab-on-grade will be i
STAT
poured this week thus completing the building shell.
f. Heavy rains caused some damage to the interior of the New
Headquarters Building. In addition to standing water on the lower floors,
b some sections of water-soaked drywall will have to be removed. This
situation will be alleviated once the building is closed in.
Declassified in Part - Sanitized Copy Approved for Release 2011/11/08: CIA-RDP89-00063R000200200016-7
strip barricade wall. The FHWA is looking into the matter. Other than the
capstone, most other work, except landscaping on one side of the wall, is
complete. The FHWA reports that the capstone work is not expected to be
c. The August status report from the Federal Highway
Administration (FHWA) on the George Washington Memorial Parkway (GWMP)
Acceleration Lane Project states that the contractor is still havin
problems getting capstones made, and recently requested an alternatg/.
material be used for the capstone along the entire length of the median
completed until the end of September at best.
hould be accomplished by mid-September and will be done on a
d. The last third of the South Lot at Headquarters was opened for
parking on 18 August. There remains some finish work in South Lot which
non-interference basis with parking.
Declassified in Part - Sanitized Copy Approved for Release 2011/11/08: CIA-RDP89-00063R000200200016-7
STAT
g. The load management system for the Powerhouse is scheduled to
be factory tested on 20-21 August. This system will, in the event of a
power failure, automatically assume control of the Headquarters power
system by starting generators and picking up loads on a preprogrammed /??//
/Y)
priority basis. The system is scheduled to be shipped immediately after
testing.
3. Events Anticipated During the Coming Week:
STAT
Chief, New Building Project Office
D/OL
C/FMD/OL
Declassified in Part - Sanitized Copy Approved for Release 2011/11/08: CIA-RDP89-00063R000200200016-7