OL/NBPO WEEKLY REPORT - PERIOD ENDING 1 OCTOBER 1986
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP89-00063R000200220046-2
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
3
Document Creation Date:
December 27, 2016
Document Release Date:
June 10, 2011
Sequence Number:
46
Case Number:
Content Type:
MISC
File:
Attachment | Size |
---|---|
![]() | 168.69 KB |
Body:
Sanitized Copy Approved for Release 2011/06/10: CIA-RDP89-00063R000200220046-2
OL/NBPO WEEKLY REPORT - PERIOD ENDING 1 OCTOBER 1986
1. Progress Reports on Tasks Assigned by the DCI/DDCI and
a. The New Building Project Office (NBPO), OL, has
received inputs from those components having a role in the New
Building Support Budget regarding potential savings in t+tet-
FY-88 through FY-92. LThe NBPO will provide its input to the
Director of Logistics prior to
1 November 1986.
b. On 26 September }98--, the New Building Project
Office (NBPO), OL, conducted a tour of Directorate of
Intelligence (DI) space under construction in the North Tower
of the New Headquarters Building. DI representatives included
the A/DDI and key managers from the Management, Planning and
Services Staff and the Intelligence Producers Council. No
significant issues were brought up by the DI representatives
STAT during the tour.
2. Items or Events of Major Interest That Have Occurred
During the Preceding Week:
a. On 29 September the Director of Logistics briefed
Col. Howard, an Army Focal Point Officer, on the organization
and missions of the Office of Logistics. The Chief, New
Building Project Office provided an overview of construction of
/ the New Headquarters Building (NHB) and conducted a tour of the
construction site. Col. Howard is a Corps of Engineers
Officer, and therefore was extremely interested in all facets
STAT of the NHB construction project.
b. The testing of the load management system for the
Powerhouse emergency generator system (Bid Package 3) scheduled
for 30 September 1986 was cancelled by the contra
Ua
operationally simulated testing of the critical c
STAT will be tested at a date to be established later.
STAT
c. On 29 September, the New Building Project Office,
OL, conducted a tour of the New Headquarters Building for
representatives of the Office of Scientific and Weapons
Research. No significant issues were raised during the tour.
Sanitized Copy Approved for Release 2011/06/10: CIA-RDP89-00063R000200220046-2
Sanitized Copy Approved for Release 2011/06/10: CIA-RDP89-00063R000200220046-2
d. On 29 September, the Chief, New Building Project
ice, OL, acting as Chairman of the CIA Transportation
support construction of a precast concrete barrier no higher
than the existing brick wall (seven feet) on Route 123 and
extension of the wall to include all homes in Section 7. The
wall would be finished on both sides with exposed aggregate.
t. The citizens and TAC Chairman ?i}ly agreed to
T`1-y~ tc *+ n t i Lip a- n A 7; =
during a 2 July +9-U0 meeting with the same group. These issues
were the decorative finish of the precast concrete panels and
extension of the precast concrete barrier on Route 193 to
include three additional homes.
Advisory Committee (TAC) held a meeting with residents of
Everm , Section 7. The purpose of this meeting was to present
the overnment's response to issues raised by the community
STAT e. As part of the Bid Package 3 contract, concrete
paving has begun at the south side of the Headquarters
Powerhouse. This work, which is expected to take approximately
four weeks, will provide a new parking area and access roads to
STAT the Powerhouse. ~_ ;,; 1( 1 1' r, ,., C-
C,/ L gi_Ci? 7 h?.[ ,
f . Th George Washin tonMemorial Parkway gate
guardhouse at eadquarters< as removed on SetarUty 27
l~~ S September. The new Security Control Center will be built at
,,the same location and is scheduled for completion in March
(~ S
STAT
g.A Ain ui10 representativenvisited the Bigelow carpet
factory in Summerville, Georgia- . The 94,600
square yards of carpet purchased for the New Headquarters
Building (NHB) was inspected in various stages of
manufacturing. The first run of approximately 13,000 square
yards will be delivered to the site on 4 October for
installation in the NHB later this fall.
3. Events Anticipated During the Coming Week:
a. Paving of the first third of the North lot will
begin
1 October. After light poles and striping are completed, the
ki
ill b
ng area w
e returned to the Agency.
STAT par
b. We will schedule a Traffic Advisory Committee
meeting for 90% design review of the Routes 123/193 road
projects.
Sanitized Copy Approved for Release 2011/06/10: CIA-RDP89-00063R000200220046-2
IJ&F6/01.
Sanitized Copy Approved for Release 2011/06/10: CIA-RDP89-00063R000200220046-2
4. Chief's Perspective:
a. The constructions of the New Headquarters Building
and associated projects (Powerhouse, Security Control Centers,
Roads and Parking Lots) is progressing well. We are focusing
attention on safety within the building site as well as
acceleration and refinement of completion dates. With respect
to the latter we have tasked Office of Information Technology
components to identify the specific areas to which they require
early access for site preparation, in wiring and computer
installation. We will then task General Services
Administration to work with Centex to complete these areas
early, ie., prior to beneficial occupancy of the building. (R.
b. We have been and will continue to devote
considerable time to briefings and tours of the New
Headquarters Building (NHB). We are focusing primarily on
components scheduled for NHB occupancy, but also are meeting
special requests such as those arranged thru Director of
Logistics, eg. representatives from the Foreig Buildinas
Office and the U.S. Army Focal Point Officer.
c. Our senior secretary, Ihas been
selected for a position in the Office ot Development and
Engineering. Her last day in New Building Project Office will
be 31 October 1986. It is important that OL/Pers obtain a
quality replacement for her - hopefully in time to provide an
overlap.
d. I believe the New Building Project Office needs to
spend more time on the building site - particular our
engineers. I will be forwarding a memorandum to the Director
of Logistics in the near future requesting the assignment of an
additional Logistics officer (non-engineer) to assist us in
meeting that objective.
D/OL
C/FMD/OL
Chief, New Building Project
Sanitized Copy Approved for Release 2011/06/10: CIA-RDP89-00063R000200220046-2