OUTLINE OF ENVIRONMENTAL ASSESSMENT

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP89-00244R000100040064-9
Release Decision: 
RIPPUB
Original Classification: 
K
Document Page Count: 
7
Document Creation Date: 
December 14, 2016
Document Release Date: 
July 9, 2003
Sequence Number: 
64
Case Number: 
Publication Date: 
July 31, 1981
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP89-00244R000100040064-9.pdf342.99 KB
Body: 
`^ Approved FoSlease 2003/08/13: CIA-RDP89-00200100040064-9 STAT Skidmore, Owings & Merrill Memorandum Date: To: From: Subject: Introduction July 31, 1981 Walter Arensberg, SOM Outline of Environmental Assessment This memo contains the outline of the Environmental Impact Assessment which Skidmore, Owings & Merrill has proposed in accordance with Task 1.4 of the Work Program for the Central Intelligence Agency's Master Plan project. The outline incorporates comments received on a draft presented earlier. The outline is based on guidelines found in three documents, the National Capital Planning Commission's "Revised Environmental Policies and Procedures" (Federal Register, Vol. 44, No.. 218, November 8, 1979), the General Services Administration's Order No. PBS 1095.4A, "Preparation of Environmental Impact Assessments and Impact Statements," October 5, 1979, and the CIA's Instruction No. L145-16, "National Environmental Policy Act Implementing Procedures" revised July 30, 1979. It should be noted that the sequence of items under IV.B, Impacts, is preliminary and may be changed. Also, the descriptions of analyses to be carried out under each item is not meant to be exhaustive. As the planning process moves ahead, and as our consultation with local agencies develops, additional issues may be added. Outline Summary Purpose of and Need for Project. A. Description of the proposed Master Development Plan B. Background information and Rationale for the Consolidation - not all personnel accommodated by original facility; 1972 Preliminary Master Plan approved; project would enhance efficiency of Agency operations, generate time savings, improve security. C. Planning Process - NCPC and other agencies. Alternatives Considered A. No change. B. Partial consolidation. Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040664 -4 Approved Foolease 2003/08/13: CIA-RDP89-00200100040064-9 C. Siting options: building locations, heights, massing; parking con- figurations (surface and structured); phasing. IV. Environmental Assessment: Impacts and Mitigating Measures. A. Overall assessment methodology and summary impact matrix. B. Impacts. 1. Subsurface Conditions: effects due to soil types, underground water levels. 2. Landforms: effects on slope stability, drainage patterns, run- off. 3. Vegetation: maintenance of existing wooded areas and plant- ings to maximum extent possible; compliance with Fairfax Environmental Quality Corridor guidelines. 4. Water and Sewer: adequacy of existing water supply and sanitary sewer system; compliance with County and regional treatment guidelines for sewer discharge. 5. Storm Drainage: adequacy of existing system and compliance with County storm water detention guidelines. 6. Energy Conservation: adequacy of existing power supply sys- tem; measures to conserve energy consumption in new facilities through advanced design of buildings and systems. 7. Solid Waste: estimated contribution by new development to local disposal and landfill facilities. 8. Traffic: additional peak hour vehicle trips generated by new development; projected volumes at major site access points; measures to mitigate traffic impacts on local access roads; policies regarding car and van pooling by Agency employees; impacts on bus service to Agency; possible changes in com- muting patterns; reduction in Agency shuttle service; truck access patterns; traffic impacts during construction. 9. Air Quality: Additional emissions from increased automobile traffic; impacts due to construction. 10. Noise: additional traffic noise; noise impacts during con- struction. 11. Land Use: change in percentage of site developed; potential usage of Scattergood Thorne tract. Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040064-9 Approved Folalease 2003/08/13: CIA-RDP89-00200100040064-9 12. Zoning: compatibility with Fairfax zoning ordinance. 13. Aesthetic: general policy of buffering Agency from surrounding area; preservation of tree buffers; limitations on height and massing of buildings; new landscaping; limitation of amount of new parking and use of parking structures. 14. Historic Preservation: avoidance of development that may interfere with Historic Districts or other designated structures. 14. Socio-Economic: GSA plans for using or releasing office space vacated by Agency personnel; regional employment shifts. 15. Community Services: adequacy of local fire protection, ambu- lance services, and refuse collection services to cover new development. 16. Local Plans and Policies: compatibility with plans and policies of; o General Services Administration o National Capital Planning Commission o Fairfax County o Metropolitan Washington Council of Governments o Northern Virginia Planning District Commission o Virginia Department of Highways and Transportation o National Park Service o Local utility companies V. Listing of Agencies and Persons Consulted VI. Listing of Reports and Documents Referenced. VII. Technical Appendices. A. Traffic B. Air and Noise C. Natural Features D. Utilities E. Water, Sewer and Drainage Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040064-9 Approved Foe6lease 2003/08/13: CIA-RDP89-002 D00100040064-9 Skidmore, Owings & Merrill Memorandum Date: July 29, 1981 STAT To: entral Intelligence Agency From: Walter Arensberg/SOM Subject: Project Activity Network Plan. Purpose This memorandum describes the Project Activity Network Plan which Skidmore, Owings ,& Merill has prepared in accordance with Task 1.3 of the Work Program for the Central Intelligence Agency's Master Development Plan Project. The attached chart and the text below incorporate comments received from the CIA on drafts presented earlier. Project Activity Network Plan The Project Activity Network Plan illustrates the Planning Team's work program for preparing the Central Intelligence Agency's Master Development Plan, Master Utility Systems Plan, and Environmental Impact Assessment. Shown on the chart are the principal milestones and tasks, with their dates, duration and phasing. The guiding framework for the work program is the review process of the National Capital Planning Commission. The CIA intends that the Master Plans.and EIA be presented formally to the NCPC at its regular meeting in early January, 1982. This means that, according to NCPC procedures, the documents and drawings must be submitted in final form 60 days in advance, or by the first week in November, for staff review. This gives slightly less than four months for the completion of the Plan and EIA. In addition, the NCPC has agreed to hear an "informational presentation" of the draft Master Plans and EIA at its meeting in the first week of October. The purpose' of this session is to obtain feedback from Commission members and ensure that their main concerns are addressed. As indicated on the chart, the work program breaks down into four basic phases, each one culminating in a major review, decision, or presentation. A discussion of these four phases follows: 1. Data Collection and Development of Master Plan Alternatives: This phase begins with the kick-off meeting and proceeds im- mediately to data collection and development of design criteria for the Master Plan (subtasks 2.1 and 2.3 of the proposal), as well as preparation of the outline of the Environmental Assessment (1.4). The first major milestone in this phase is the early consultation meeting with local agencies which occurs two weeks into the project. OL 1 3216 Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040064-9 Approved F Memorandum July 29, 1981 Page Two lease 2003/08/13: CIA-RDP89-00200100040064-9 The purpose of this meeting is to provide basic information about the Master Plan project to agencies whose interests may be affected, to give them an opportunity to express their concerns, and to establish a basis for further consultation on critical issues such as traffic, landscaping, and air/noise impacts. Early and continuing contact with key outside agencies will be crucial in facilitating the Master Plan review process. The early consultation meeting will lead into two major activities, the development of schematic alternatives for the Master Plan (2.6) and data collection and preliminary impact analysis for the Environ- mental Assessment (4.1). Parallel to these will be the collection of baseline utility systems data (3.1). The development of schematic alternatives will last about four weeks (late July to late August) and consist of an iterative process in which the Planning Team generates site plan concepts, reviews them internally and with the CIA , and refines them. The process culminates in a final selection meeting (2.7) with the CIA scheduled for the last week in August. This meeting will produce an agreed-on site plan, building configuration, circulation layout, and parking arrangement. The survey of the existing site (2.2) is to begin in the second week of the project. This includes ground control for the aerial photo- grammetry, the fly-over itself, and field surveying of topography and existing structures. The production of maps showing survey in- formation will begin during this period and continue into Phase 2. 2. Plan Refinement and Environmental Assessment: In this phase, lasting about five weeks, more detailed plans of the selected scheme will be prepared (2.8). Schematic drawings will be produced showing the site plan, circulation patterns, elevations, landscaping,and parking. Information from the site survey and the environmental and utililties data collection exercises will be fed into this refinement process. Once the scheme has been elaborated to a sufficient level of detail, a preliminary cost estimate will be pre- pared (2.9). While the Plan is being refined, the environmental impacts of the selected scheme will be analyzed (4.3), along with the impacts of alternatives such as "no-build", construction of less that the target amount of new space, and other siting arrangements. The analysis of utility requirements of the selected scheme (3.2) will also take place during this period. Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040064-9 Approved FC*Iease 2003/08/13: CIA-RDP89-00200100040064-9 Memorandum July 29, 1981 Page Three 3. Preparation of Final Plans: This phase lasts for approximately one month and is devoted to incorporating comments received from the NCPC and producing final versions of the Master Development Plan, Master Utility Systems Plan, and Environmental Impact Assessment. During this time the presentation model and renderings will be prepared. The final documents and drawings will be finished by the end of October, reviewed with the CIA, and submitted to the NCPC in the first week of November. 4. NCPC Staff Review and Formal Presentation: In the sixty days between Plan submission and the NCPC's formal review, the Planning Team will be available to assist the CIA in providing information about the Plans and EIA. The NCPC staff will review the submitted material, circulate it to local agencies, and prepare a memo for the Commissioners. The Planning Team will join the CIA and GSA in making the final presentation to the Commission at the beginning of January, and will make revisions, as required, to incorporate NCPC comments. Outside Agency Consultation: During each phase, the Planning Team and the CIA's project coordinator will maintain close contact with local agencies to ensure that the Master Plan, Utilites Plan, and Environmental Assessment are compatible with policies and plans of those agencies and that their interests are reflected in the design and impact analysis. The Activity Network Chart illustrates the continuing agency contact that will be maintained during Phases 1, 2 and 3. At this point, the following organizations have been identified as the ones with whom consultations should occur: o General Services Administration o National Capital Planning Commission o Metropolitan Washington Council of Governments o Fairfax County Planning Board and Executive o Northern Virginia Planning District Commission o Washington Metropolitan Area Transit Authority o Virginia State Highway Department o Virginia Electric Power Company o Fairfax County Water Authority o Falls Church Public Utilities Department o C&P Telephone Company o Local homeowners' associations Finally, the chart indicates the dates for submission by the Planning Team of its monthly progress reports to the CIA. Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040064-9 Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040064-9 2.2 PREPARE SURVEY MAPS NCPC REVIEW AND ? DATA COLLECTION AND DEVELOPMENT OF ALTERNATIVES PLAN REFINEMENT AND ENVIRONMENTAL ASSESSMENT PREPARATION OF AL PLANS PRESENTATION 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/3 10/12 10/19 0/26 11/2 11/9 1/4 1 I I I I 1 1 1 1 I I I I I I I I I I__________I 2.1 COLLECT PLAN DATA Finalize Program 2.3 ? Begin Project Early Consultation 1.4 EIA OUTLINE Outline Approval 4.1 COLLECT EIA DATA & PERFORM PRELIMINARY IMPACT ANALYSIS H H 3.1 COLLECT UTILITIES DATA 2.8 REFINE SELECTED DESIGN (INCLUDING GEOTECHNICAL INVESTIGATION) 4.4 PREPARE EIA DRAFT 4.3 ANALYZE ENVIRONMENTAL ALTERNATIVES & IMPACTS 3.3 DRAFT UTILITY PLAN ? Informational Presentation to NCPC H 7.0 PREPARE FINAL ILITY PLAN ? 3.4 UTILITY COSTS ? PUBLIC AGENCY & COMMUNITY CONSULTATION F H PUBLIC AGENCY & COMMUNITY CONSULTATION NCPC CONSULTATION W/AGENCIES NCPC INTERNAL REVIEW TEAM REVIEW It REVISIONS O CLIENT MEETINGS Formal Presentation to NCPC O NCPC PRESENTATIONS OUTSIDE AGENCY Z~s CONSULTATION Approved For Release 2003/08/13 : CIA-RDP89-00244R000100040064-9