REVISED PROJECT SCHEDULE FOR PROPOSED NEW HEADQUARTERS BUILDING
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP89-00244R000200230019-0
Release Decision:
RIFPUB
Original Classification:
K
Document Page Count:
1
Document Creation Date:
December 21, 2016
Document Release Date:
May 5, 2008
Sequence Number:
19
Case Number:
Publication Date:
October 14, 1982
Content Type:
MISC
File:
Attachment | Size |
---|---|
![]() | 23.9 KB |
Body:
Approved For Release 2008/05/05: CIA-RDP89-00244R000200230019-0
14 OCT 1982
Revised Project Schedule for Proposed New Headquarters Building
1.
2.
3.
4.
9.
10.
Award A-E contract and Start Project Design
December 1982
Complete Schematic Design
April 1983
Complete Preliminary Design
August 1983
Complete Construction Documents for Parking
Deck
November 1983
Award Construction Contract for Parking Deck
February 1984
Complete Construction Documents for New
Headquarters Building
May 1984
Award Construction Contract for New
Headquarters Building
August 1984
Complete Construction of Parking Deck
November 1984
Partial Beneficial Occupancy of New
Headquarters Building
February 1987
Complete Construction and Occupy New
Headquarters Building
August 1987