CONTRACT CHANGE PROPOSAL #15, FACTORY TRAINING OF CUSTOMER TECHNICIANS TO BE INSTRUCTORS, LOT II, SCHEDULE II EQUIPMENT
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP89B00487R000300490025-3
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
2
Document Creation Date:
December 22, 2016
Document Release Date:
August 9, 2011
Sequence Number:
25
Case Number:
Publication Date:
September 25, 1957
Content Type:
MEMO
File:
Attachment | Size |
---|---|
![]() | 97.57 KB |
Body:
25 September 1957
Sanitized Copy Approved for Release 2011/08/09: CIA-RDP89B00487R000300490025-3
F APC~,~~j
OPY OF
Subject: Contract Change Proposal #15,. Factory Training of Customer
Technicians to be Instructors, Lot II, Schedule II Equipment
Reference: (a) Contract BC-2.04, as amended
(b) Telecon 3 September 1957, BH to TLB
(c) Letter dated 17 September 1957, SWB to TLB
In accordance with your requests of references (b) and (c) we herewith
submit our proposal for the factory training of two (2) Air Force personnel
to be trained as instructors for equipments delivered under Schedule II of
the reference (a) contract.
It is proposed that the initial training of the personnel will be concerned
with Configurations A-1, A-2 and B due to the fact that Configuration C
will not be available for FOG until February or March of 1958. The
training for Configurations A-1, A-2 and B. will be accomplished over an
eight (8) week period. This initial training will be concerned with schedules
similar to that of the previous training program at our factory for your
seven (7) technicians. in the fall of 1956. It will include all phases of
these configurations, associated ground. support equipment, field main-
tenance techniques and related subjects.
Instruction will be conducted eight (8) hours per day, five (5) days per week,
Monday through Friday. There will be a series of lecture classes, however,
most of the instruction will be given at our Maintenance and Overhaul facility.
This Depot level type of instruction will expose the trainees to complete
.operation. and maintenance techniques. for these equipments. It is planned
that a single instructor will be assigned for the complete duration of this
training schedule. In addition, it is planned that project engineers, prod-
uction personnel,. design engineers and field service engineers will be
utilized to give the trainees the most complete subject coverage. They will
be furnished schematic drawings, blueprints, charts and miscellaneous
training material during the course of the program. Training aids which
were developed. during the previous training program will used.
It is planned that after this eight (8) week schedule two (2) weeks will be
spent at Del Rio during which time the trainees will be exposed to the
techniques and procedures of all phases of field operation and will be
instructed by our Senior Field Service Engineer,
25X1
25X1
Sanitized Copy Approved for Release 2011/08/09: CIA-RDP89B00487R000300490025-3
Sanitized Copy Approved for Release 2011/08/09: CIA-RDP89B00487R000300490025-3
0
Invoices will be submitted monthly based upon percentage of completion
of the contractor's obligation. The eight (8) week training program for
the two (2) customer technicians will be performed for a total amount of
$6,075.00.
We understand that T/.Sgt. Carrol M. Butler and S/Sgt. Dan Bullock will
be provided from Air Training Command for this special training. We
will appreciate your sending to our attention pertinent information regarding
the technical background and qualifications of these men.
We trust that this, proposal meets with your approval and recommend that
a contract item covering this training program be established on Schedule .II
of the reference (a) contract.
Very truly yours,
HYCON MFG. COMPANY
Engineering groducts Division
TLB./pe