LONGER LEADTIMES: A SYMPTOM OF SOVIET PROBLEMS IN USING WESTERN TECHNOLOGY

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP85T00313R000100130007-2
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
18
Document Creation Date: 
December 22, 2016
Document Release Date: 
June 11, 2009
Sequence Number: 
7
Case Number: 
Publication Date: 
June 1, 1984
Content Type: 
REPORT
File: 
AttachmentSize
PDF icon CIA-RDP85T00313R000100130007-2.pdf1.08 MB
Body: 
Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Directorate of Secret Intelligence Longer Leadtimes: A Symptom of Soviet Problems in Using Western Technology Secret SOV 84-10082D June 1984 Copy 474 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Intelligence Longer Leadtimes: A Symptom of Soviet Problems in Using Western Technology This paper was prepared b Office of Soviet Analysis. Comments and queries are welcome and may be directed to the Chief, Soviet Economy Division, SOVA~ Secret SOV 84-10082D June 1984 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Secret Longer Leadtimes: A Symptom of Soviet Problems in Using Western Technology Key Judgments Soviet use of imported Western plant and equipment has fallen far short of Information available its potential for improving the USSR's overall economic performance, in as of 15.Apri1 1984. large part because the Soviets take so long to acquire and put to use many was used in this report. of these imports. Average leadtimes are, much longer in the USSR than in the West, almost invariably exceed the plan, and show no signs of diminishing. 25X1 The picture is not uniform. Imports for projects in high-priority sectors- defense and energy, for example-usually get special handling and, as a re- sult, are acquired and assimilated promptly. In most other sectors, however, a variety of factors-some unique to imported technology and some affecting domestic as well-prolong the leadtimes: ? Divided responsibility. The lack of a single body to coordinate all stages of the import acquisition and absorption process fosters redundancy, prolongs negotiations, and slows down the assimilation of new technology. ? Administrative barriers. Official reluctance to permit personal contacts with foreign suppliers isolates production managers from important Western sources of information about the equipment, often leading to improper installation and prolonging the period of adjustment. ? Accounting practices. Because the Soviet economic system levies a very small interest charge on capital assets (both domestic and imported), no one feels obliged to get imported equipment into production quickly. ? Incentives. By emphasizing quantitative output, the Soviet incentive 25X1 system breeds resistance to technological change. Individual Soviet end users probably can save time by importing a product embodying new technology rather than waiting for its development in the USSR. However, diffusion-the widespread use of a new technology throughout the economy-may be faster with indigenous development. This is primarily because the Soviets seldom begin the research and development needed for embodying imported technology in Soviet-pro- duced equipment until the import has been operated in a "prototype factory." From initial expression of interest to factory operation generally takes two to seven years. iii Secret SOV 84-10082D June 1984 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Nevertheless, as the pinch on labor, capital, and natural resources tightens and the leading edge of Western technology continues to advance, the Soviets will continue to import Western technology and equipment to alleviate bottlenecks and modernize domestic industries. Even though effective diffusion of technology might occur more quickly through indigenous development, Moscow will continue to rely on imports because the USSR puts a greater premium on satisfying current requirements for equipment and technology than on potential long-term uses. The USSR is trying to speed up the assimilation of new technology in nonpriority civilian projects through various reorganizations and special bonuses. Results continue to be disappointing, however, to judge by the chronic official complaints. We believe the prospect for improvements will remain dim, barring a major overhaul of the system of incentives for More important, as long as the USSR relies on imported plant and equipment for its most advanced civilian technology, it will continue to lag in the generation of new technology. Even though Soviet engineers who study imported equipment may note well what the Western designers have done, they may still-not having gone through the designing experience- be ill prepared to carry the embodied technology further. Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Secret Key Judgments Acquisition, Assimilation, and Diffusion of Imports 1 Determinants of Leadtimes in Each Stage of the Import Process 4 Stage 1: Discovery of Western Plant or Equipment 4 Stage 2: Request for Funds 5 Stage 3: Negotiation With Western Suppliers 6 Stage 4: Delivery, Installation, and First Use 7 Stage 5: Assimilation 8 Stage 6: Diffusion 9 Implications 11 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11 : CIA-RDP85T00313R000100130007-2 25X1 Secret Longer Leadtimes: A Symptom of Soviet Problems in Using Western Technology Despite its high degree of self-sufficiency, the Soviet Union has traditionally imported Western technology to help ease bottlenecks, raise efficiency, and modern- ize its economy. Imports of Western plant and equip- ment expanded rapidly in the 1970s, as Moscow increased its emphasis on these goals in response to increasingly severe material and expected manpower shortages. Such imports have significantly benefited specific sectors. They contributed much, for example, to the substantial enlargement of the natural gas pipeline network and the major advances of defense industries. But the Soviets hoped that Western technology also would stimulate productivity-not only in the individ- ual plants where the imports were used but also generally, through diffusion. This has not happened. There is, in fact, direct evidence that Soviet handling of legally acquired Western technology for use in the civilian economy has been notably inefficient. A prime example is the disproportionate length of time the Soviets take in assimilating and diffusing most imports of Western plant and equipment.' These excessive leadtimes play a major role in diluting the potential benefits of such imports. Our focus in this paper is on the overall pattern of handling foreign technology. Drawing on comparisons with Western experience, we identify factors that prolong the process of acquiring and using imports in the Soviet economy. We describe the performance of the Soviet system in each stage of the assimilation and diffusion of imports and compare that to the system's performance with domestically generated technology. 'Assimilation is the mastering of new technology by a single end user. Diffusion is the use of it throughout the economy. In this paper the phrase "assimilation and diffusion" refers to all of the stages from initial Soviet interest in a technology to its economy- Obviously there are exceptions, most notably priority projects in the defense and energy sectors. Their shorter leadtimes usually reflect official actions to override the obstacles built into the system. These actions include (1) allowing the end user more direct participation in import negotiations, (2) promptly au- thorizing payment in hard currency, and (3) interven- ing to guarantee on-schedule delivery. Acquisition, Assimilation, and Diffusion of Imports The process of legal acquisition and use of Western plant and equipment for the civilian economy can be divided into six stages: ? Discovery of Western plant or equipment (initiation of interest). ? Request for funds. ? Negotiation of Soviet foreign trade organization (FTO) with Western suppliers. ? Delivery, installation, and first use. ? Assimilation of the import by the original end user. ? Diffusion of the embodied technology to relevant uses throughout the economy. To work well, the process must facilitate the flow of information, reward initiative and innovation, foster trade, and provide the know-how and resources for production with the new equipment or process. In no country, of course, does it work perfectly. But in the USSR the process is seriously flawed in almost all stages by: ? An inefficient decisionmaking apparatus. ? Lack of motivation to innovate. ? A xenophobic leadership. ? The treatment of capital assets as virtually free goods. ? Protracted construction times. 25X1 25X1 Approved For Release 2009/06/11: CIA-RDP85T00313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 In the Soviet Union, responsibilities for decisions that affect innovation and import policy in the civilian economy are shared by a number of organizations, including the State Planning Committee (Gosplan), the State Committee for Science and Technology (GKNT), the Ministry of Foreign Trade, the Ministry of Finance, and the various industrial ministries. Within these organizations, the import decisions are made primarily by a few officials in the central administrations. These officials are usually geographi- cally separate from the end users they are supposed to represent and are not always well informed about all the technologies in which they have trading inter- ests-despite the Soviets' well-organized system for collecting and disseminating information. The officials responsible for innovation are further handicapped by a frequent lack of common objectives with the end user. An enterprise manager often resists innovation because it causes downtime and other short-term disruptions of plant operations, and these jeopardize his fulfillment of immediate sales and production goals-his prime success indicators. Such resistance, in turn, tends to discourage the import decision maker, who also fears being identified with a failed innovation attempt. This conflict of objectives encourages temporizing and buckpassing and makes the import process even slower. The Soviet Union's high degree of self-sufficiency further weakens the motivation to trade. Trade has never been crucial to its economic survival, and today-despite the expansion of trade in recent years-imports account for only 5 to 10 percent of Soviet GNP. Xenophobia, deeply rooted in Russian history, has inhibited the Soviet ability to make the most of Western technology, even when imports are expanding rapidly. For example, when detente flour- ished and imports surged in the early and mid-1970s, the Soviets still severely limited Western participation in economic projects-participation that would in- crease foreign contacts and possibly diminish Soviet operational control. Even though management studies showed long ago that technology is more efficiently transferred through personal interaction than through technical documentation alone, the USSR has placed significant limitations on foreign travel for its people and on visits by Western technical advisers. The Soviets rely, for the most part, on Western publica- tions to identify and learn how to use Western imports. The Soviet economy treats capital as virtually a free good. This attitude contributes to long leadtimes by reducing the motivation to put new plant.and equip- ment into operation as promptly as possible. This particular problem is not peculiar to imported tech- nology but reflects a general managerial indifference toward having capital tied up, whether that capital is imported or domestic and whether it embodies new or old technology. This indifference prolongs construction times, and building delays in turn delay the assimilation of Western technology. During the 1970s Soviet sources estimated that the building of an enterprise from the initial design to full-capacity operation took five to seven years on average; it takes only two to three years in the West. A more recent Soviet estimate (1980) puts the average leadtime for all projects at eight to 10 years. Since new technology is generally made operational through new plant and equipment, the far longer construction times mean that all tech- nology, both imported and domestic, is brought on stream much more slowly in the USSR than in the West. In the Soviet chemical industry, for example, the time that elapses between Stages 2 and 5 (initial inquiries about import contracts and operation of the purchased plant and equipment) is roughly two to three times as long as in the West (table). In the machine tool industry, the time between contract inquiry and first production is more than twice that required by West- ern firms.' In two of the six stages of the process (negotiation and installation/first use), Soviet firms take three times as long as Western firms. 'This figure is based on a survey by Dr. M. R. Hill of eight British manufacturers that provide machine tools to both Western and Soviet purchasers; reported in Soviet Absorption of Western Tech- nology: A Survey of West European Experience, by Malcolm Hill and Philip Hanson, Stanford Research Institute, December 1978. 25X1 25X1 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Secret Leadtimes in the Chemical Industry, Soviet and Western (u) From contract inquiry through negotiations From the end of negotiations to initiation of production b Total Soviet indigenous development c Research, development, test- ing, evaluation, and achieve- ment of normal-capacity oper- ation For the Soviets, Western rates may be less important than whether they themselves can assimilate an im- ported. technology more quickly than one developed at home. As the table shows, if the technology is not available domestically, importing saves time. Howev- er, if equipment embodying the technology is already available in the USSR, assimilation is presumably speedier through its use, rather than through imports. But even in this case, Soviet enterprises sometimes prefer Western suppliers because they are supposed to be more reliable. In fact, however, this reliability can be offset by delivery delays after shipments have reached Soviet soil. Furthermore, US-Government- imposed sanctions have on occasion caused US suppli- ers to suspend contractual obligations to Soviet buy- ers Moreover, even if importing speeds up assimilation by one end user, it is not clear that it accelerates diffusion throughout the economy. Diffusion usually requires that a new technology be embodied in Soviet- produced equipment-a time-consuming process that often demands considerable research and develop- ment. The USSR seldom begins such R&D work until assimilation of imported plant and equipment is well under way or even complete. This is usually some two to seven years from the initiation of interest by the In the USSR In the West 1.5 0.8 5.2 2.3 to 3.0 6.7 3.1 to 3.8 15.0 a Soviet Absorption of Western Technology: A Survey of West European Experience, by Malcolm Hill and Philip Hanson, Stan- ford Research Institute, December 1978 (a survey of 31 projects). b Initiation of production is an earlier stage than the attainment of normal-capacity operation, the stage cited in our source for Soviet indigenous development in the chemical industry. V. S. Sominskii (survey of 132 projects); referred to in Trade and Technology in Soviet-Western Relations, by Philip Hanson, New York, Columbia University Press, 1981, p. 79. The large difference in the time required to put new technology (domestic or foreign) into operation in the USSR and in the West is also indicated by the interval between the application for an inventor's certificate on new technology and first use of that technology. For instance, a 1979 Western study com- paring the implementation of inventions in the USSR, the United States, and West Germany showed that 50 percent of those sampled had been implemented after little more than a year in the two Western countries and after over three years in the Soviet Union.' At the end of two years, 66 percent of the sampled. US inventions had been implemented, 64 percent. of the German, and only 23 percent of the Soviet. Soviet end user (Stage 1). Additionally, there is evidence that the Soviets some- times-perhaps frequently-fail in their attempts to accomplish diffusion (Stage 6).' 1 successful diffusion of an import within the civilian economy is rare. imported Western technology has not produced dra- matic changes in the economy, and technological advances in Soviet industry continue to depend pri- marily on domestic research and development. At least three Western studies have shown that in the Soviet chemical industry a high level of imports, ' It is important to note that the Soviets import for a wide variety of purposes, including alleviating bottlenecks and supplementing do- mestic production, and thus do not try to diffuse all imports 25X1 25X1 25X1 2.5X1 25X1 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 continued over a. long period of time, has tended to perpetuate dependence rather than end it. despite a need for specialized equipment (which the chemical industry has been importing for the past 20 years), the machine-building industry has made only limited progress in its produc- tion. This prolonged dependence ensures a continued lag of Soviet technology behind that of the West. Both Western and Soviet observers have noted that even if a new technology reaches Stage 6 in the Soviet Union, it often has taken so long that the diffused technology is obsolete Moreover, the Soviets evidently are not improving with experience. A statistical test-based on survey data from Western businessmen collected in Philip Hanson's chemical industry study of 31 projects-has indicated that leadtime performance has not improved over the last 20 years, despite Soviet industry's in- creasing familiarity with the same Western firms.6 F The Soviets themselves seem dissatisfied with their leadtime performance. Articles drawing attention to uninstalled or malfunctioning imports often appear in the Soviet press. One such article concluded that the actual time from plant commissioning to attainment of full capacity can be up to 50 percent longer than the planned time. A Soviet engineer has estimated that a large share of all foreign equipment is almost useless because it is delivered so late that it no longer fits in with the enterprise's plans. These problems persist, even though the Soviets seem to assign higher priority to the assimilation of Western equipment than to that of domestic equipment (see inset). F_ Determinants of Leadtimes in Each Stage of the Import Process Stage 1: Discovery of Western Plant or Equipment The Soviets have developed a massive and effective system for collecting and disseminating information on Western technology. The key organization in this effort is the large Moscow-based All-Union Institute for Scientific and Technical Information (VINITI). It collects Western materials in scores of technology areas and distributes compilations (usually monthly) to R&D institutes and ministries throughout the country. The VINITI documents are supplemented by material from other Moscow-based clearinghouses, reports filed by Soviets who have traveled abroad, and subscriptions to Western journals. The distribution system functions smoothly, but its usefulness is to a considerable degree offset by certain impediments. For example: ? A thorough grasp of the Western data often depends on instruction that can be provided only by direct personal contact with suppliers-which the Soviets often forbid or sharply limit. ? The scope of technologies in which the Soviets have trading interests is too great for the relatively limited number of import decision makers to ade- quately grasp through their own efforts. (These decisionmakers are primarily officials in Gosplan, GKNT, the Ministry of Foreign Trade, and Mos- cow- or Leningrad-based ministerial offices who are far removed from the day-to-day activities of pro- duction and R&D enterprises.) Therefore they must rely on these enterprises to accomplish the bulk of the review of Western literature and to submit pertinent information and recommendations to them. These enterprises, however, may distort the information they give to the decisionmakers-or even withhold information-in order to escape pres- sure to innovate. Central authorities attempt to counterbalance this reluctance to innovate through a combination of administrative direction and tinkering with incentives. The former are generally annual "innovation targets" levied on a ministry and its constituent enterprises. The latter involves modifying economic or organiza- tional mechanisms to provide incentives without changing the basic command structure of the system. 25X1 25X1 25X1 25X1 25X1 25X1 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85T00313R000100130007-2 Secret The high priority assigned to assimilation of Western equipment is evidenced by a decree issued in Septem- ber 1979. This established a basic bonus of 3 percent of the total value of construction and installation work for on-time project completion and provided a 25 percent increase to this bonus for projects using large amounts of imported equipment. In October 1983 a separate resolution was issued ordering minis- tries to ensure that imported equipment is put into service and brought up to capacity operation within the warranty period. Soviet officials have recently criticized the foreign. trade organizations forfoot-dragging in their negotia- tions with Western suppliers. This suggests continu- ing attention to the problem of import leadtimes. Whether inspired by the carrot or the stick, however, innovation tends to be conservative, even when it is genuine. Since many production managers view West- ern companies (especially West European and Japa- nese) as more reliable than Soviet suppliers, they often choose importing as a way to meet innovation targets. Ministries, for the most part, try to inaugurate new technologies in new facilities; because innovations in an existing plant often require production adjustments that threaten its ability to satisfy its existing perform- ance indicators. Furthermore, new facilities increase the size and prestige of the ministry Stage 2: Request for Funds After enterprise or ministry officials have identified a potentially useful import, they begin the process of getting approval to enter into trade negotiations. This is usually complex and protracted, except for imports deemed by central authorities to have high priority. Even seemingly sensible centrally directed measures often go awry, however, in the prevailing sellers' market, where chronic shortages force buyers to take what they can get. For example, guaranteeing a higher price for a new product stemming from innova- tion often leads to "gold-plating"-pseudo-innovation in which a manufacturer represents as new or im- proved a product that has in fact had only a cosmetic change. The combination of centrally controlled allo- cation of resources and the weak bargaining position of buyers enables such activity to spread widely. C Even though disincentives far outweigh incentives for innovation, not all innovation targets are met through deception. There are some reasons-although not many-for enterprise managers to pursue real innova- tion. Genuine innovation probably helps ministerial and enterprise officials gain attention from higher authori- ties and thus enhances their career prospects. In a few cases, managers may be forced to introduce real change in response to centrally exerted pressures. These pressures are applied at the enterprise level through an Enterprise Technical Council, which mon- itors the enterprise's technical achievements and re- ports to the ministry. The enterprise also has a fund for innovation, and management has an incentive to make it appear that this fund is being used well. F_ the applica- tion to purchase machinery must demonstrate that the import is needed, that the USSR has no suitable substitute, and that money would be saved by the purchase. The application must include statements from relevant Soviet ministries that they cannot pro- vide the equipment in the required quantity, quality, and time The actual purchase justification is submitted first for ministry review and then (if tentatively approved) to 25X1 25X1 the central authorities. 25X1 typed pages. such a document may contain up to 25X1 Developing a purchase justification is a time-consum- ing procedure, generally requiring the following steps: ? Consultations within an enterprise's design bureau or between it and other interested organizations to formulate a "first cut" technical specification. ? Submission of technical specifications to a ministry technical review committee with an explanation of the purpose of the import, for preliminary approval. ? Resubmission (after preliminary approval) with a detailed funding request and the documents showing that the technology is not available from domestic sources. 25X1 Approved For Release 2009/06/11: CIA-RDP85T00313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 The ministry's technical review committee evaluates the justification request and either denies it or sends it forward for funding. If approved by central authori- ties, the funds are usually included in the ministry's annual plan. Since plans are formulated three to six months before they go into effect, a significant amount of time can be lost in the budgeting cycle. long as 18 months may elapse between ministry approval and the beginning of negotiations with the foreign supplier. (Similar delays can be expected for projects involving domestic resources, since they must usually go through this same application process.) Inertia seems to be a major determinant of budgeting for imports. industrial ministries routinely win renewal of yearly allotments for imports at a nearly constant level. However, the central authorities tend to place requests for increased or new funds at the bottom of their priority list, and if the funds are approved the lag before import negotiations begin is generally longer than for renewal requests. In many instances, addiction to routine, coupled with tightening hard currency constraints, apparently takes precedence over the need for new technology from Stage 3: Negotiation With Western Suppliers UNCODEDirge Soviet foreign trade organization like Mashinoimport is responsible for conducting some 10,000 trade negotiations annually-many more than its staff can handle expeditiously. This problem is recognized by Soviet authorities. (Once negotiations do begin, they typically take three times as long as in the West-for several reasons, including the need for approval from multiple sources. An import order may need as many as 18 signatures. The bureaucratic and geographic separation of the FTO negotiating team from the Soviet end user also stretches out the process. The FTO is qualified to pursue commercial negotiations, but usually not the necessary technical discussions. Since end users are not often part of the formal negotiating team, special arrangements must be made for their participation. This requirement prolongs leadtimes by making the commercial and technical aspects of the negotiations relatively distinct and sequential, instead of overlap- ping. Still, cases exist where the end user does not participate in the negotiations at all (see inset). Leadtimes are further lengthened in Stage 3 by the incentive system for FTO negotiating teams. This usually emphasizes economizing on foreign exchange, obtaining favorable financing, and extracting price concessions. Negotiations to achieve these objectives are often time consuming, even though the interests of both individual end users and the economy as a whole might be better served by speedier import of the technology being sought. Leadtimes are also prolonged by the exclusion of foreign advisers from most projects. Western compa- nies find it difficult to supply all relevant instructions and documentation because of the Soviet reluctance to supply information on how and where the import will interface with existing systems and plants. For example, the Soviets significantly limited Western suppliers' visits to the Kama River Truck Plant and withheld drawings of the buildings in which the imported equipment was to be installed. To get as much as possible out of this one-way flow of information, the Soviets often demand vast amounts of documentation. )a typical proposal prepared by his company to oviet specifications filled a box of approximately 36 cubic feet. Furthermore, an FTO normally sends inquiries to a fairly large number of competing West- ern firms (in the case cited, seven) and must usually. study all their proposals before it selects the firms with which it will negotiate further. Great detail is later required in the contract itself in the operating instructions. ?r,x1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85T00313R000100130007-2 secret Because of information transmittal problems result- ing from bureaucratic and geographic separation, FTOs may order equipment that the end user cannot use. expensive "automated furnace" equip- ment purchased for the iron foundry at the Kama River Truck Plant has never been installed, because it was not requested by foundry managers and is inappropriate to their needs. In another case, the Ministry of Foreign Trade failed to include representatives to the negotiating team sent to purchase ccom- p equipment-even though the Ministry was not familiar with his enterprise's special requirements. As a result, the computerized banking system that the Ministry purchased from France proved to be "a colossal failure, because it was designed for a capital- ist system and could not be adapted to Soviet needs." Two other Soviet tendencies can cause delay at the negotiation stage. One is to word an initial inquiry so vaguely that many Western firms do not realize they have been asked to make a proposal, and the other is to interrupt negotiations for substantial periods with- out warning or explanation. Stage 4: Delivery, Installation, and First Use Leadtimes in Stage 4 are long; the overall leadtime from initial contact to first use of the import is often three to four times the normal leadtimes in the West, according to Western studies of the chemical and machine tool industries.' Soviet literature is replete with examples of poorly formulated shipping sched- ules, inadequate port facilities, and shortages of do- mestic transport-all of which tend to stretch out delivery of imports to the end user Another cause of delay is the fragmentation of au- thority. Domestic shipping channels are so arranged that imports must be cleared through a number of ' Soviet Absorption of Western Technology: A Survey of West European Experience, by Malcolm Hill and Philip Hanson, Stan- ford Research Institute, December 1978, and Soviet Absorption of Western Technology, by Heinrich Vogel and Karl Rothlingshofer, checkpoints, each under a different jurisdiction, be- fore final delivery. This multiplies the opportunities for bureacratic delay. Once the import arrives, the Soviet end user faces a whole new set of obstacles. If the plant is new, the lag associated with installation is particularly lengthy- primarily because of problems in the construction the purchasin officers who select imports for new plants and arrange for their delivery must do so during the planning stages of the project-years before the plant will be ready for installation of equipment. However, 50 percent of all construction projects are completed 25X1 25X1 25X1 25X1 25X1 25X1 25X1 behind schedule (even though the schedule is anything but demanding).' As a result, the Western producer 25X1 often delivers equipment long before the construction of the plant is at the stage where it can be installed. A recent example wasl la . Western firm that supplies oil production equipment to the USSR. The Soviets insisted that production units for a Caspian Sea project be delivered in 1984, even though drilling was not scheduled to be complet- A plant presumably can adjust a domestic delivery schedule more easily than it can revise an internation- al contract. Thus, the lack of coordination between equipment deliveries and plant preparation probably is greater when the equipment is imported Even if the plant is built and already producing, the lag in installing imported equipment can still be significant; it often has been the subject of criticism in the Soviet press. The chemical industry's handling of imports was derided in a Pravda cartoon of August 1981 showing a plant buried under crates of machine tools. The accompanying narrative stated that the 8 Major reasons for this are the low cost of construction investment funds and an incentive structure that rewards a new construction start more highly than a job completion. 25X1 25X1 25X1 25X1 Approved For Release 2009/06/11: CIA-RDP85T00313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 %. ~Ifiid fib,,! ..ice/%;;% ii ~. , /, I%%/% Novopolotsk Production Association "Polimer" had not made any use of imported equipment valued at 674,000 rubles and that in 1969 the Usolskiy "Khim- prom" Association had received imported equipment worth 650,000 rubles that had never been installed and had, in fact, deteriorated beyond repair while in storage. In 1979 Soviet authorities checked 45 petro- chemical complexes and found 24 at which equipment awaiting installation was lying unprotected. Such negligence results from a host of problems-many of which affect the handling of domestic as well as imported equipment.' 'These general problems include lack of tools, unpredictable fluctu- ations in the labor force, slow decisionmaking, a general lack of Still another important factor can prolong leadtimes in Stage 4: a reported Soviet procedure of sometimes requiring that 80 percent of total equipment be delivered before installation begins. Because deliveries for new plants (or for major renovation projects in old plants) are often spread out over many months or years, equipment that could have been installed may instead lie deteriorating pending arrival of additional shipments. Stage 5: Assimilation the intervals between first use of imported equipment and its use at rated capacities are frequently 50 percent longer than Sovi- et planners consider normal. There are two main reasons for this: ? Difficulty in finding reliable suppliers for the mate- rials and equipment necessary to install and service the new technology. This reflects, in part, the characteristic tautness in Soviet plans. ? Faulty coordination among central planners with responsibility for different phases of the same project. A current example of poor planning has a supplier plant and an end-use plant being built at the same time (each by a Western contractor), over 900 kilome- ters (km) apart. This distance greatly increases the probability of delivery problems. if the two plants were constructed in the West, they would be no more than 15 km apart. F Because supply uncertainty is more the rule than the exception in the USSR, Soviet enterprises tend to produce in house the items they really need. This inefficient practice can cause downtime and equip- ment malfunctions that, among other negative conse- quences, can delay the achievement of rated capacity. When new technology-foreign or domestic-is used in a new enterprise, managers may attempt to mini- mize the risk of failure by altering the criteria used to monitor their performance. They can do this, for example, by deliberately operating at less than opti- mum rates, out of fear that higher rates may convince superiors to set more demanding norms. 25X1 25X1 25X1 25X1 25X1 25X1 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85T00313R000100130007-2 Secret The difficulty the Soviets have experienced in mesh- ing imported and domestic machinery is another major cause of delay in Stage 5. In some imported ammonia plants, for example, incompatibility of do- mestic and foreign machinery has caused equipment malfunctions resulting in significant production de- lays. Other industries have been affected as well. The failure of domestic and foreign equipment to dovetail has been a major problem since 1980 at the Nairit Production Association. This incompatibility delayed the opening and impeded the subsequent smooth functioning of a synthetic rubber production line there. Furthermore, in 1982 it caused a pollution accident that prompted local sanitation authorities to order production stopped until the necessary repairs were made; this task was scheduled to be completed by the end of the current five-year plan. Malfunctions in imported plant and equipment often stem from the processing of low-quality or otherwise unsuitable materials and from inadequate preventive maintenance. Examples include the breakdown of imported machinery when it was used to make parts from steel with too great a tensile strength or parts that exceeded permissible dimensions and weights. A Western bearing cage production line at a Soviet plant went out of commission because of the use of inferior Soviet bronze. Another important constraint on putting imports into service promptly is the Soviet reliance on technical documentation for learning how to use equipment. A good example is the experience the Soviets have had in trying to use the IBM Information Management System. This was imported in 1974 but, has never worked well-mainly because the Soviets have used only the written instructions. These are incomplete because IBM expects to send its own people to help end users-an offer rejected by the Soviets. Whatever the cause of equipment malfunctions (lack of information, poor maintenance, improper raw ma- terials, or labor problems), their effect depends on how quickly the Soviets can get the equipment working again. Here their record is poor. Even when they do allow Western technicians to service imported equip- ment, bureaucratic meddling often delays the work. it is usual practice to buy few or no replacement parts to avoid spending foreign exchange. Therefore, a breakdown of the simplest part can cause an extended delay as replacements are ordered from the West or fabricated locally. This problem-a major source of delays- occurs more frequently as equipment ages. Recently one-half of the 50 Western-made bulldozers used by the Lenzoloto Production Association gold-mining facility lay idle because of a lack of spare parts. shortage has kept many of the imported US pipelay- ing machines-critical to the USSR's petroleum in- dustry-out of service for extended periods. The problem also plagues oil drilling activities. worst it is getting wo 25X1 spare parts portions of recent import contracts for 25X1 the petroleum drilling industry have in many cases been cut by over 50 percent. I --I 25X1 Stage 6: Diffusion Successful diffusion usually requires becoming inde- pendent of imports by producing the equivalent plant 25X1 and equipment domestically. This arduous technical task is becoming increasingly difficult because of the growing complexity of the imports. In many cases the Soviets lack the skills and materials needed for series production of similar items. Additionally, Soviet re- searchers do not always have access to the types of equipment and resources used in the West and thus have difficulty achieving the necessary quality stand- ards in the late 1970s the research staff at the Mechanical Project Institute for Oil and Water Equipment in Moscow spent several years trying to develop a sub- mersible pump for use in oil, wells. The staff took apart a number of US pumps and attempted to copy them with minor modifications. The major stumbling- block was the refusal of Soviet industrial officials to 25X1 25X1 25X1 25X1 25X1 Approved For Release 2009/06/11: CIA-RDP85T00313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 supply the materials on whicl. the quality and durabil- ity of imported pumps depended. Staff engineers were amazed that US companies could easily obtain nickel and other metals for their pumps, since Soviet strate- gic metals are reserved primarily for direct defense applications Soviet failures in diffusing imported technology result not only from organizational mismanagement and inferior technological capability, but also from the practice of keeping existing facilities and equipment in use far longer than in the West. Demand is so great that old and inefficient plants can still sell their output and continue to operate. Thus, there is a significant variation in physical configuration, equip- ment, and performance standards between plants producing the same goods. These variations doom to failure most attempts to force-fit to one plant the complex imported equipment that works in another. Even when the Soviets have successfully diffused imports, their leadtimes, compared to those in the West, have been extremely long. Long lags in Stage 6 are not unique to imports, however: many of the same influences also impede the diffusion of domestic tech- nology The successful adaptation of imports for use as Soviet-made products must begin with R&D concepts that are workable, but the geographic and bureau- cratic separation of most R&D organizations from end user plants deprives the R&D employees of full knowledge of the environments within which their concepts must work. The R&D incentive system in the USSR, which usually allows bonus payment before an idea is translated into production, does not encourage the R&D employee to seek such knowledge. This partially explains the significant gap between research and application in the USSR. The Soviets have attempted to close this gap and speed up the innovation process through the use of scientific-production associations (NPOs) that bring research, development, and production responsibilities together under one roof. They claim that the NPOs, which currently number more than 250, have reduced leadtimes by 50 to 65 percent. They probably are referring, however, to the time between the R&D phase and first use. in the NPO plant, not between R&D and economy-wide use. Additionally, NPOs are often assigned normal production quotas by their industrial ministry bosses, in addition to their experi- mental work toward speeding up innovation. Some- times they have even been ordered to cease experi- mental work altogether in order to make up for losses of production elsewhere in the ministry. The efficiency of Soviet R&D institutions in formulat- ing workable concepts is also impaired by the low quality (and sometimes virtual absence) of support services and equipment. A Soviet survey of 300 design institutes in different branches of industry showed that 85 percent of them copied designs and technical drawings by hand. Ithe Soviet Union has only 20,000 to 30,000 photocopiers-a small fraction of the number that a Western country of equivalent size and development would have. This is a symptom of a more general Stage 6 problem and very poor manufacturing capability to produce new types of industrial-scale equipment Misallocation of R&D labor resources also.lengthens leadtimes. This problem has two parts. First, most well-qualified scientists, for prestige and other rea- sons, pursue theoretical work in research institutes- which are not the prime movers in applied R&D and diffusion. Second, the successful performance of pilot plants developed to manufacture prototypes requires performance and prolonging leadtimes. about the same pay as the less taxing work in a production plant and that the pilot plant workers have smaller "bonus pools" than those in production. As a result, the innovating sector cannot attract the talent- ed workers it needs-significantly weakening R&D After workable R&D concepts are formulated and pilot tested, there is still no assurance they will ever be introduced into serial production. The R&D establish- ment, for the most part, lacks the authority (even when it has the desire) to force implementation of its recommendations over the objections of plant manag- ers. 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 25X1 ZoA] Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Secret Examples of Gains From the Use of Western Equipment ? The Soviets could never have accomplished their ambitious 15 year program of modernization and expansion in the motor vehicle industry without Western help. The Fiat-equipped VAZ plant, for example, produced one-half of all Soviet passenger cars when it came fully onstream in 1975; and the Kama River Truck Plant, which is based almost exclusively on Western equipment and technology, now supplies nearly 50 percent of Soviet output of heavy trucks. ? Large computer systems and minicomputers of Western origin have been imported in large num- bers-1,300 systems since 1972-because they (a) have capabilities that the Soviets cannot match and (b) use complex software that the Soviets have not developed. ? Gear-cutting machines of US origin have been used to produce military trucks, wheeled armored vehi- cles, and components for missile transporters, and US technology acquired for the Cheboksary tractor plant was used to make a new 12-cylinder tank engine. This weakness results, in part, from the absence of a single body to coordinate the diffusion process. The State Committee for Science and Technology super- vises interbranch R&D, but its authority ends with the preparation of a prototype; Gosplan handles the serial production and distribution phases. With this split, each organization under the nominal supervision of the GKNT or Gosplan has tended to.become parochial, creating barriers that inhibit the movement of an idea through the stages from concept to produc- tion. The extremely slow pace at which imported Western technology is generally assimilated and diffused in the USSR sharply limits its contribution to the modern- ization of the Soviet economy as a whole. Even in some high-priority civilian areas-such as imported gas-lift equipment used to maintain or increase oil well flow rates-the protracted delays in acquiring and installing the equipment have reduced the effec- tiveness of its use.'? F____] 25X1 As the pinch on the USSR's labor, capital, and natural resources tightens and the leading edge of Western technology continues to advance, the Soviets will continue to import Western technology and equipment to alleviate bottlenecks and modernize domestic industries. Even though effective diffusion of technology might occur more quickly through indige- nous development, Moscow will continue to rely on imports because the USSR puts a greater premium on satisfying current requirements for equipment and technology than on potential long-term uses. As in the past, some of these imports will raise the 25X1 technological level of specific industries and/or in- crease the quantity and quality of their output, and some may find application in Soviet weapons produc- tion (see inset). 25X1 Nevertheless, Moscow will find it increasingly diffi- cult to catch up with the general level of technology in advanced Western countries by relying on imports of Western plant and equipment. This is partly because some imports embody technology that is not state of the art and are bought simply to improve the average quality of the USSR's own plant and equipment. Even if the Soviets choose the most up-to-date technology, however, imports stand little chance of eliminating the Soviet lag behind the West, because: ? Widespread application of such imports probably will be rare. ? If effective application ever occurs, it is likely to take many years. ? Soviet engineers, having not gone through the de- signing experience that underlies the imported equipment, will be ill prepared to carry the embod- ied technology to a still more advanced level. 10 In 1978 the Soviets contracted with a French firm (Technip) to install gas-lift equipment in 1,800 wells at Samotlor-their largest oilfield. Similar equipment was purchased for 600 wells at the Federovo field. Completion of these projects was scheduled for 1985 but has been delayed for a year or two. If installed on schedule, this equipment could have provided some 200,000 to 300,000 barrels per day of oil output beyond that otherwise expected from these fields. Because of the delay, however, the window of opportunity for the most effective use of this equipment may have been missed, because the water cut (the amount of water mixed with the oil) at Samotlor and Federovo is now higher than optimal for extraction Secret Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Secret Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2 Secret Approved For Release 2009/06/11: CIA-RDP85TOO313R000100130007-2