GURYEV PETROLEUM REFINERY LEND-LEASE 1 GURYEV, USSR

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP79T00909A000500010004-7
Release Decision: 
RIPPUB
Original Classification: 
T
Document Page Count: 
12
Document Creation Date: 
December 28, 2016
Document Release Date: 
June 18, 2008
Sequence Number: 
4
Case Number: 
Publication Date: 
June 1, 1971
Content Type: 
REPORT
File: 
AttachmentSize
PDF icon CIA-RDP79T00909A000500010004-7.pdf521.64 KB
Body: 
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Top Secret Industrial Facilities (Non-Military) DIRECTORATE OF INTELLIGENCE Basic Imagery Interpretation Report Guryev Petroleum Refinery Lend-Lease 1 Guryev, USSR Top Secret RCS 1 /rnn c /-71 25X1 DATE JUNE 1971 COPY f 17 PAGES o 1- Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 TOP SECRET RUFF TCS - 16049/71 CENTRAL INTELLIGENCE AGENCY Directorate of Intelligence Imagery Analysis Service Guryev Petroleum Refinery Lend-Lease UTM COORDINATES 39TWN717154. GEOGRAPHIC COORDINATES 47-05-OON 051-56-50E MAP REFERENCE 2nd RTS. USATC, Series 200, Sheet M0247-6HL 3rd ed. Se 67, Scale (SECRET 25X1 25X1 25X1 Guryev Petroleum Refinery Lend-Lease 1 is one of the smaller major Soviet re- fineries. Refining components include a crude oil distillation unit, a combination crude oil distillation-thermal cracking-thermal reforming unit, a fixed-bed cataly- tic cracking unit, a gas fractionating and processing unit, and an alkylation unit. Also, a probable catalytic reforming-hydrotreating unit is in the late stages of construction. Products from the refinery include straight-run, cracked and blended gasolines, kerosene, diesel and fuel oils, gaseous hydrocarbons, and petrochemical feedstocks.' The refinery was seen on overhead coverage in August 1961, but the poor quali- ty of the photography precluded detailed analysis. In June 1962, when the refinery was seen again, all of the major equipment now operating was present except the crude oil distillation unit. There were no significant changes in facilities until late 1967, when the crude oil distillation unit was started. The distillation unit was completed by early 1970. Construction of a probable catalytic reforming-hydro- treating unit began in early 1969 and was not complete when the refinery was last seen in April 1971. At that time, unidentified construction was observed. The re- finery was in operation on all photographic coverage from August 1961 to April 1971. This report contains a detailed line.drawing, a photograph, a listing of facil- ities with measurements of storage tanks, and a discussion of the status of facilities. -1- TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 25X1 TOP SECRET RUFF TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 TOP SECRET RUFF Gury.ev Petroleum Refinery Lend-Lease 1 is located on the southeast edge of Guryev, onmthe east side of the Ural River and about 20 nautical miles northeast of the Caspian, Sea (see Figures 1 and 2). The crude oil distillation capacity of this refinery is small in comparison to many of the major Soviet refineries. Also, much'of the processing equipment is obsolescent by US standards, as it was installed between 1943 and 1945 under the Lend-Lease program. 1,2/ Most of the crude oil originally processed in the refinery was produced in the Emba'01.1 Fields. With increased production from the Mangyshlak Oil Fields starting in 1965-1966, crude oil from this area was scheduled for refining at Guryev:.andlthis necessitated the expansion of facilities at the refinery. L/ The chemical plant is about 1,700 feet northeast of the refiner?"I and receives raw materials from the refinery through aboveground pipelines. which is collocated with the Guryev Chemical PIa-25X1 25X1 LDAI Crude,oil and products are shipped into and out of the refinery by pipeline, rai.l.road-,'and barge. Rail service is provided by a spur from the Guryev-Kandagach rail.-1i`ne and barge facilities are located on the nearby Ural River. Electric power for the refinery is produced by the Guryev Heat and Thermal Physical Features .The refinery occupies a nearly rectangular area about 5,500 by 3,900 feet containing about 490 acres. The area is secured by a system of walls and fences. Most of'.the processing units are of US design and present a close-spaced, cluttered appearance. Thel.newer units are of the standard Soviet design which is character- ized by widely spaced equipment. Operational Functions The main function of this refinery is the production of fuels. .No lubricating oil production facilities, are present. The major refining equipment presently con- structed and in operation include a crude oil distillation unit, a combination crude oil distillation-thermal cracking-thermal reforming unit, a fixed-bed catalytic cracking unit, a gas. fractionating and processing unit, and a sulfuric acid alkyla- tion. unit.' .The products of this refinery include straight-run, cracked and blended gaso- lines, kerosene,; diesel and fuel oils, gaseous hydrocarbons, and petrochemical feedstocks. Construction and Operational Status In August 1961, the date of the earliest coverage used in this report, the refinery was in operation but the poor quality of the photography precluded detailed analysis. On photography of June 1962, the following refining units were complete and in operation: 1. Combination crude oil distillation-thermal cracking-thermal reforming unit. Z. Fixed-bed catalytic cracking unit. 3. Gas fractionating and processing unit. 4. Sulfuric acid alkylation unit. Also, essentially all of the storage, shipping, support, and administration facil- ities were; completed. -3- TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 TOP SECRET RUFF Gury.ev Petroleum Refinery Lend-Lease 1 is located on the southeast edge of Guryev, onmthe east side of the Ural River and about 20 nautical miles northeast of the Caspian, Sea (see Figures 1 and 2). The crude oil distillation capacity of this refinery is small in comparison to many of the major Soviet refineries. Also, much'of the processing equipment is obsolescent by US standards, as it was installed between 1943 and 1945 under the Lend-Lease program. 1,2/ Most of the crude oil originally processed in the refinery was produced in the Emba'01.1 Fields. With increased production from the Mangyshlak Oil Fields starting in 1965-1966, crude oil from this area was scheduled for refining at Guryev:.andlthis necessitated the expansion of facilities at the refinery. L/ The chemical plant is about 1,700 feet northeast of the refiner?"I and receives raw materials from the refinery through aboveground pipelines. which is collocated with the Guryev Chemical PIa-25X1 25X1 LDAI Crude,oil and products are shipped into and out of the refinery by pipeline, rai.l.road-,'and barge. Rail service is provided by a spur from the Guryev-Kandagach rail.-1i`ne and barge facilities are located on the nearby Ural River. Electric power for the refinery is produced by the Guryev Heat and Thermal Physical Features .The refinery occupies a nearly rectangular area about 5,500 by 3,900 feet containing about 490 acres. The area is secured by a system of walls and fences. Most of'.the processing units are of US design and present a close-spaced, cluttered appearance. Thel.newer units are of the standard Soviet design which is character- ized by widely spaced equipment. Operational Functions The main function of this refinery is the production of fuels. .No lubricating oil production facilities, are present. The major refining equipment presently con- structed and in operation include a crude oil distillation unit, a combination crude oil distillation-thermal cracking-thermal reforming unit, a fixed-bed catalytic cracking unit, a gas. fractionating and processing unit, and a sulfuric acid alkyla- tion. unit.' .The products of this refinery include straight-run, cracked and blended gaso- lines, kerosene,; diesel and fuel oils, gaseous hydrocarbons, and petrochemical feedstocks. Construction and Operational Status In August 1961, the date of the earliest coverage used in this report, the refinery was in operation but the poor quality of the photography precluded detailed analysis. On photography of June 1962, the following refining units were complete and in operation: 1. Combination crude oil distillation-thermal cracking-thermal reforming unit. Z. Fixed-bed catalytic cracking unit. 3. Gas fractionating and processing unit. 4. Sulfuric acid alkylation unit. Also, essentially all of the storage, shipping, support, and administration facil- ities were; completed. -3- TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 TOP SECRET RUFF Between; June 1962 and late 1967 there were no significant changes in facil- ities except-for the construction of a desalting unit near the combination crude oil distillation-thermal cracking-thermal reforming unit. This desalting unit was constructed between October 1964 and-September 1966. Photography of November 1967 showed that the refinery area had been expanded by about 20 percent. Grading and excavating had started for the new crude oil distillation unit (Area B) and the water cooling and treatment facilities (Area D). Throughout 1968 work proceeded slowly in these areas. By July 1969, the crude oil distillation unit was nearly complete and site preparation was seen for a probable catalytic reforming-hydrotreating (CR-HT) unit., By March 1970, the crude oil distillation unit was complete but not yet in opera- tion and the water cooling and treatment facilities were completed. In April 1971, when the refinery was last seen, the crude oil distillation unit appeared to be in operation and the probable CR-HT unit was in the late stages of construction. Also, a probable oil-water separating facility and its associated storage tanks had been dismantled and unidentified construction was under way (Area A). I Completion of the crude oil distillation unit probably more than doubled the charge capacity of the refinery. The probable CR-HT unit will add significantly to the refinery's capacity to produce high-octane motor fuels. The refinery was in operation on all photographic coverage from August 1961 to April 1971. Facilities and Equipment The following table lists the functional areas and the facilities and equip- ment in the refinery. All measurements are rounded to the nearest half-meter. Table 1. Equipment and Facilities at the Guryev Petroleum Refinery Lend-Lease 1 (Keyed to Figure 3) Functional Description Equipment and Facilities 5 Miscellaneous buildings 1 Water treatment reservoir 1 Cylindrical storage tank, 12 meters in diameter 2 Water storage basins 1 U/I area under construction 1 Crude oil distillation unit with a row of 9 columns (1 vacuum, 2 atmospheric, and 6 stripping/ stabilizing columns) 2 Possible rerun columns 2 Banks of heat exchangers/ accumulators 2 Pipe furnaces 10 Miscellaneous buildings 4 Horizontal treating drums, 25X1 1 Desalting unit with 1 building, 1 probable mixing column and 5 desalting/settling drums 14 Cylindrical storage tanks 2 12-meter-diameter 9 25X1 3 6-meter-diameter -6- TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 1 Cylindrical storage tank 2 Hor a sett I ing drums, 27 meters long 2 Semiburied storage tanks (not measured) 1 Flare tower E Shipping and Storage 20 Storage and shipping buildings 1 Building u/c 3 Railcar loading racks 3 Cylindrical storage tanks 1 27-meter-diameter 1 24-meter-diameter 4 Horizontal storage tanks, 12 meters long 1 Water storage basin TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Functional Description Equipment and Facilities Probable Catalytic Reforming- Late stage of construction -- Hydrotreat_ing facilities not listed 25X1 25X1 Water Cooling and Treatment 6 Miscellaneous buildings 3 Cooling towers, each with 5 cells 2 Water treatment reservoirs Crude Oil, Intermediates, 16 Miscellaneous buildings and Products Storage 67 Cylindrical storage tanks 16 36-meter-diameter 6 30-meter-diameter 1 27-meter-diameter 22 24-meter-diameter 8 21-meter-diameter 6 15-meter-diameter 4 12-meter-diameter 2 9-meter-diameter 25X1 1 Covered crude oil storage reser- voir, 210 x 48 meters 2 Water storage basins Secondary Processing (1) Alkylation 17 Horizontal storage an s, 1 Sulfuric acid alkylation unit with 4 columns (1 deisobutanizer, 1 debutanizer, 1 depropanizer, and 1 rerun), 1 distillation building, 1 reactor building with 3 possible reactors, 1 acid and. caustic settler building with 4 settling drums, 1 compressor/pump building, 1 compressor-cooling building with a bank of cooling coils/heat exchangers, 1 acid recovery building with 3 drums, 1 caustic recovery building, 3 support buildings, 5 surge and stock tanks (3-meter-diameter . 5 chemical storage tanks 25X1 meter-diameter, one 6-meter-dia- meter, one a25X1 two 3-meter-diameter), and 5 hori- zontal storage tanks (two 18 meters Ion two 15 meters long. and one 25X1 -7- TOP SECRET, RUFF- Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 TOP SECRET RUFF Area Functional Description Equipment and Facilities G (Cont) (2) Intermediates Storage 1 Compressor/control building 6 Cylindrical storage tanks 2 12-meter-diameter 2 9-meter-diameter 2 6 Horizontal storage tanks, 18 meters long Gas Fractionating and 4 Columns (1 debutanizer, 1 de- Processing propanizer, 1 butane, and 1 stabilizing column) 1 Compressor/pump building 1 Compressor building 1 Air cooler 1 Building with 1 treating drum 4 Support buildings 2 Cylindrical storage tanks/dry gasholders, 25X1 diameter 4 Hnri7nntal stnrana tankg Steam Plant Treating and Blending Secondary Processing (1) Catalytic Cracking 1 Boilerhouse 8 Miscellaneous buildings 9 Cylindrical storage tanks 2 15-meter-diameter 25X1 1 Control building 4 Miscellaneous storage/support buildings 6 Cylindrical storage/blending and treating tanks 25X1 in diameter 1 Fixed-bed catalytic cracking unit with 9 catalyst chambers, 3 fractionator/stabilizer columns, 2 probable absorbers, 2 clusters of u/i equipment, 2 pipe furnaces, 1 air cooler, 1 control/condenser building, 1 pump building, and 5 support buildings (2) Products Storage 1 Support building 11 Cylindrical storage tanks 1 24-meter-diameter 2 21-meter-diameter 2 15-meter-diameter 2 12-meter-diameter 1 9-meter-diameter 3 1 Water storage basin TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 TOP SECRET RUFF Area Functional Description Equipment and Facilities (2) Desalting Crude Oil Distillation and Secondary Processing (1) Crude Oil Distillation, Cracking and Reforming 25X1 LJ/~ I 1 Combination unit with a crude oil distillation section with 1 topping and 1 atmospheric column; a thermal cracking section with 4 columns; a thermal reforming section with processing equipment in scaf- folding; a caustic treating section with 1 row of 4 mixing/storage tanks (3-meter-diameter), 1 row of 4 mixing towers with 7 hori- zontal settlers, 1 cylindrical storage tank (3-meter-diameter), 3 horizontal tanks 25X1 meters long and one 25X1 long), and 1 building; a possible treating section with 1 building and 3 attached columns; 5 pipe furnaces; 5 air coolers; 1 con- trol/condenser building; 2 support buildings; and 5 horizontal stor- age tanks meters long, three~ long, and one25X1 F 7 25X1 1 Desalting unit with 1 building, 7 desalting drums/settlers, and 1 cylindrical storage tank,F_25X1 25X1 1 Desalting unit with 3 buildings, 2 desalting spheres, 4 desalting/ settling drums, and 1 bank of heat exchangers 2 Support buildings (3) Products and 1 Building with 2 probable settling Intermediates Storage drums 8 Cylindrical storage tanks 6 15-meter-diameter 2 Horizontal storage tan Rs 1 15-meter-long 1 Water storage M Administration and Support 21 Miscellaneous buildings TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 TOP SECRET RUFF Map 2nd RTS. US Air Target Chart, Series 200, Sheet M0247-6HI- 3rd edition September 1967 Scale 1:200,000 (SECRET Documents 1. CIA. 2. CIA. 25X1 25X1 Card No. 6036759, 19 December 1955 (SECRET25X1 JPRS 49641, 20 January 1970 (UNCLASSIFIED) 3. The Petroleum Publishing Co., International Petroleum Encyclopedia, 1969 edition (UNCLASSIFIED) Requirement COMIREX N02 Support Number 429225 -10- TOP SECRET RUFF Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7 Top Secret Top Secret Approved For Release 2008/06/18: CIA-RDP79T00909A000500010004-7