MAJOR ELECTRIC POWER PLANTS LIAONING PROVINCE, CHINA
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP79T00909A000900010044-9
Release Decision:
RIPPUB
Original Classification:
T
Document Page Count:
15
Document Creation Date:
December 28, 2016
Document Release Date:
October 6, 2008
Sequence Number:
44
Case Number:
Publication Date:
February 1, 1971
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 1.09 MB |
Body:
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Top Secret
DIRECTORATE OF
INTELLIGENCE
Industrial Facilities
(Non-Military)
Basic Imagery Interpretation Report
Major Electric Power Plants
Liaoning Province, China
Top Secret
DATE
COPY
PAGES
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
RCS - 13/0018/71
CENTRAL INTELLIGENCE AGENCY
Directorate of Intelligence
Imagery Analysis Service
This report, based on late 1969 and 1970 imagery, updates the previous basic
reporting on 12 of the major electric power plants in Liaoning Province, north-
eastern China. The cut-off date for information'is November 1970.
Changes were observed at only three of the plants. The Shen-yang Thermal
Power Plant Northeast was being converted to a heat processing plant. The
boilerhouse and generator hall roofs were modified and two of the three stacks
were dismantled between January 1969 and April 1970. At the Kai-yuan Thermal
Power Plant Ching-ho, the roofs of the boilerhouse and generator hall were re-
moved between November 1968 and December 1969. At the third plant, Lu-ta Thermal
Power Plant No. I Amanogawa, the smoke stacks were removed between September and
November 1970.
On the latest coverage, eight of the plants were operating and one plant
was probably operating.
TOP. SECRET RUFF
25X1
25X1
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
-2-
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
This report updates previous basic reporting on the following 12 major
electric power plants in Liaoning Province (see Figure I).
1. An-shan Heat and Thermal Power Plant Steel Plant
2. Chin-chou Thermal Power Plant Synthetic Fuels Plant
3. Fou-hsin Thermal Power Plant
4. Fu-shun Heat and Thermal Power Plant Liao-ning
5. Fu-shun Thermal Power Plant Shale Oil Plant No. 2
6. Fu-shun Thermal Power Plant Tai-kan-ton
7. Huan-jen Hydro Power Plant Hun-chiang
8. Kai-yuan Thermal Power Plant Ching-ho
9. Lu-ta (Dairen) Thermal Power Plant No. I Amanogawa
10. Lu-ta Heat and Thermal Power Plant No. 2 Kan-ching-tzu
II. Shen-yang Thermal Power Plant Northeast (converted to a heat
processing plant)
12. Shen-yang Thermal Power Plant Tieh-hsi
Requirement
COMIREX N01
Support Number 421951
CIA. RCS-13/0027/70, Major Electric Power Plants Liaoning Province
China, February 1970,1 I(TOP SECRET RUFF)
-3-
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
UTM COORDINATES GEOGRAPHIC COORDINATES
51TVF987529 41-07-55N 122-59-05E
15th RTS. USATC, Series 200, Sheet M0289-20HL, 3rd ed, Sep 66, Scale 1:200,000
No changes have been observed at the An-shan Heat and Thermal Power Plant
Steel Plant since November 1968, the date of the latest photography used in the
previous report.
The plant was operating when observed in March 1970. Vapor was observed
emanating from three of the eight cooling towers.
-4-
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
25X1
25X1
25X1
25X1
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Iq
Next 1 Page(s) In Document Denied
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
UTM COORDINATES
51TWG910415
GEOGRAPHIC COORDINATES
41-55-IIN 124-05-32E
6th RTS. USATC, Series 200, Sheet M0290-IIHL, 4th ed, Jan 66, Scale 1:200,000
No changes have been observed at the Fu-shun Heat and Thermal Power Plant
Liao-ning since November 1968, the date of the latest photography used in the
previous report.
The plant was operating in March 1970. Heavy smoke was observed emanating
from all three of the stacks.
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
Fu-shun Thermal Power Plant Shale Oil Plant No.
UTM COORDINATES GEOGRAPHIC COORDINATES
51TWG874315 41-49-45N 124-02-55E
MAP REFERENCE
67th RTS. USATC
Series 200. Sheet M0290-IIHL. 4th ed. Jan 66, Scale 1:200,000
LATEST IMAGERY USED I NEGATION DATE (If required)
No changes have been observed at the Fu-shun Thermal Power Plant Shale Oil
Plant No. 2 since November 1968, the date of the latest photography used in the
previous report.
The plant was operating in December 1969. Smoke was observed emanating
from the stack and vapor from one of the two cooling towers.
-8-
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
25X1 1
25X1
II
25X1
25X
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
Fu-shun Thermal Power Pla
USATC, Series 200, Sheet M0290-IIHL, 4th ed, Jan 66 Scale 1:200,000
(SECRET
I ATEST IMAGERY USED r=r.~~~na-nu-rc rr~r~irc
No changes have been observed at the Fu-shun Thermal Power Plant Tai-kan-ton
since April 1969, the date of the latest photography used in the previous report.
The plant was operating in March 1970. Smoke was observed emanating from
two of the four stacks and vapor from ten of the 13 cooling towers.
-9-
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
25X1
I
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
Huan-jen Hydro Power Plant Hun-chiang
GEOGRAPHIC COORDINATES
41-17-OON 125-23-53E
USNOO. USATC, Series 200_ Sheet M0290-17H1_ 4th PH Anr 6R craIP 1-?nn nnn
51TYFO22710
MAP REFERENCE
(SECRET
No changes have been observed at the Huan-jen Hydro Power Plant Hun-chiang
since May 1969, the date of the latest photography used in the previous report.
The plant appeared to be in operation in December 1969. Water turbulence
was observed in the tailrace.
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
25X1
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
FIGURE 2. KAI-YUAN THERMAL POWER PLANT CH!NG-HO, CHINA
- II -
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
TOP SECRET RUFF
Kai-yuan Thermal Power Plant Chin -h
UTM COORDINATES GEOGRAPHIC COORDINATES
USNOO. USATC,.Series 200, Sheet M0290-6HL 4th ed Feb 68 Scale 1:200,000
(SECRET
The roofs of the boilerhouse and generator hall have been removed at the
Kai-yuan Thermal Power Plant Ching-ho since November 1968, the date of the latest
photography used in the previous report. Photography of December 1969 revealed
that the roofs had been removed. They had not been replaced as of March 1970
(see Figure 2).
The plant was never completed and has never been observed operating.
25X1
25X1
L 25X1
TOP SECRET RUFF
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Next 4 Page(s) In Document Denied
Iq
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9
Top Secret
Top Secret
Approved For Release 2008/10/06: CIA-RDP79T00909A000900010044-9