PLANS AND PROGRAMS STAFF WEEKLY REPORT FOR
PERIOD ENDING 9 MARCH 1983
1. Progress Report on Tasks Assigned by the DCI/DDCI:
No tasks assigned during this reporting period.
2. Items or Events of Major Interest that have Occurred
During the Preceding Week:
a. LIMS
(1) On 8 March the LIMS Distribution Module analyst
reviewed with a Plans Staff representative preliminary
detailed data flow diagrams and process descriptions
relative to this function. All problems surfaced in a
similar meeting of three months ago appear to be resolved;
t.ha h i l t i n n , is now taking on its final form.
will assume analyst's duties due to the
TDY assignment of the present analyst.
(2)I IQAD/ODP, provided an overview of
the quality assurance concept to the SDG and P&PS, 14
March. The CTEC project manager participated.
b. Regulation Revisions
The following regulations were reviewed, commented
upon, concurred in, or published during the past week:
Motor Vehicles - We made adjustments
requested by OGC and the SSA/DDA and returned these regu-
lations to OIS/RCD suggesting they be sent to the DDA for
approval, via the DCI as recommended by OGC. OGC still
Approved For Release 2009/05/22 : CIA-RDP87-00352R000100030035-7
Approved For Release 2009/05/22 : CIA-RDP87-00352R000100030035-7
SUBJECT: Plans and Programs Staff Weekly Report for Period
Ending 9 March 1983
c. Training
(1) presented the
Plans and Programs Staff story at the Logistics
Orientation Course, 9 March.
(2) A P&PS representative will attend the CTEC
Software Configuration Management Course, 15-16 March,
under the sponsorship of ODP.