2. STATEMENT OF WORK
DECLASS REVIEW by NIMA/DOD
The Contractor proposes to supply direct engineering and support
manpower, material and facilities to accomplish the tasks described
below over a ten (10) month period on a cost plus award fee basis.
A. Study Tasks
(1) Determine quantitative design parameters (e.g., input,
output, and response requirements in terms of volumes,
frequencies, rates, and types) for each ADP function
of the system defined by the Conceptual Design and
Functional Specifications -Report No. SCR 288). 25X1A
Develop alternative methods for performing these
functions, evaluate these methods as applied in an
integrated system design, and establish the techniques
most amenable to utilization in the IIS. During
the development of the total system design, the Con-
tractor shall place a special emphasis on the follow-
ing major areas:
a. the handling of ephemeris data;
b. formats for the various readout worksheets;
c. the set of products to be generated by the IIS
for both internal and external use;
d. procedures for the transcription, entry and
approval of material to be added to the data
base;
e. the various mensuration activities required
at NPIC during both the immediate and detailed
reporting cycles;
GRaGf i~~
7WO g r O
Approved For Release 2002/01/2~tiJJ ::@+ '9t j 78804
I Ow
'' rr f)
Womilm
Approved For Release 2002/01 ?fCR
CIAP781304747A001900040028-8
f, procedures for the prediction of the film
location of targets and a method for target
prediction which will meet the requirements
of the IIS.
g, procedures for assisting in the distribution
of film, the assignment of personnel and the
selection of supporting materials and equipment
to be used during the immediate reporting cycle;
h, the scope of information to be handled by the
IIS required to support imagery exploitation;
i. target data file structure;
file utilization program package;
k, techniques for the retrieval of information
stored in the data base;
procedures which will meet established security
regualtions for the control of film and documents;
m, procedures for the initiation of briefing
boards and for the preparation of the supporting
textual material;
n? procedures for the machine production of
graphic materials;
o. CHIVE, COINS and the data link interface with
the IIS?
Note: The study efforts "a" through "o" abov shall be developed in
close coordination with the NPIC componentsj,affected)and problem
areas brought to the attention of the technical monitor. The
Approved For Release 2002/01/29 3"- F 1 B04747AO01900040028-8
SECRET 3
Approved For Release 2002/01/29 : CIA-RDP78B04747A001900040028-8
efforts shall be described in informal memoranda submitted,
as individual tasks are completed, for review and approval by
NPIC. Approval or disapproval will be given within 10 work-
ing days of receipt at NPIC. The government shall provide the
reasons for disapproval and determine corrective action by
mutual agreement with the contractor.
(2) The results of the Task I analysis shall be reported
in a formal study entitled "NPIC IIS System Requirements."
The study will describe the overall system operation,
the cost effectiveness of the system and system
components relative to the present system, the input/
output loading factors, and present a brief description
of the system components and the interfaces between
components. Cost effectiveness shall be evaluated
utilizing the criteria established in Phase I.,as
a basis.
(3) Prepare detailed specifications for system components
including hardware, computer programs and files in
"Integrated Information System (IIS) Specifications."
These specifications shall conform to a documentation
standard agreed to by the technical monitor and the
Contractor. It is understood that the specifications
shall be sufficiently detailed to be directly applicable
as attachments to Requests for Proposal to be sent to
Approved For Release 2002/01/29 fmy B04747AO01 900040028-8
Approved For Release 2002/0 DP78B04747A001900040028-8
~~f
potential vendors. Classification shall be kept
as low as feasible.
(4) Prepare a detailed system implementation plan. This
plan shall include schedules and budgetary, costs for
procurement and installation of hardware and facilities,
generation of computer programs and files, manpower,
training, system tests and the generation of final
system documentation.
(5) Prepare presentation for NPIC technical conference to be
presented on 15 and 16 November 1966. This presentation
shall include:
a. One Year Goals
b. Detailed descriptions of major tasks
c. Accomplishments to date
1. Theoretical assumptions reached
2. Emperical Efforts
B. Reports
In addition to continuing the regular Monthly Progress
Letters required by the basic contract per Specification
No. DB-1001, 31 August 1966, the Contractor shall produce
the following technical reports during the conduct of
Phase II of the IIS study program:
(1) A detailed system description for the IIS to be composed
of two parts, "NPIC IIS System Requirements" resulting
from Task A (3). The detailed specifications contained
in the latter document should be issued as attachments
to System Requirements. The two documents should be
Approved For Release 2002/01/29 fO l 8BO4747AO01900040028-8
~S ff
-C 5
Approved For Release 2002/01/
78B04747A001900040028-8
Is E,
so structured so that they may be used either as a
comprehensive Request for Proposal or for the entire
hardware or software system or they may be divided into
logical subsets and used as RFP's for the subsets. First
attention will be given to long lead time components.
(2) A Detailed System Implementation Plan reporting the results
of Task 4.
C. Schedule
Activities undertaken in fulfillment of the Statement of Work
will be accomplished in accordance with the following schedule: